AI summaryDenbighshire Cabinet approves procurement strategy for residential and commercial works in Rhyl town centre, with a pre-tender estimate of £2,224,370.00 inclusive of VAT.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCompetitive bids invited for works
Money£2,224,370.00 inclusive of VATPre-tender estimate for the works
What happens nextInvitation of competitive bidsFor a Principal Contractor
Who it affectsRhyl town centre properties64 High Street and 2 to 4 Wellington Road

What was decided

Cabinet approved the procurement strategy and the invitation of competitive bids for works to provide residential units on the upper floors and to renovate the ground floor commercial units at the Rhyl properties. Report 3.1, 4.4

Cabinet confirmed it had read, understood and taken account of the Well-Being Impact Assessment in Appendix 2 as part of its consideration.

Why

Works are needed to create residential units on the upper floors and to renovate the ground floor commercial units of council-owned properties in Rhyl town centre, originally acquired to deliver an outline project within the North Wales Regional Regeneration Plan. Report P7, 4.2, 4.3

The scheme supports the Corporate Plan 2022 to 2027 objective to provide good quality housing and the aim to deliver 170 Council homes, as well as the Housing and Homelessness Strategy and the Climate and Ecological Change Strategy. Report 5.2

What happens next

Competitive bids are to be invited for a Principal Contractor to carry out the works, in line with the Commissioning and Contract Award Form at Appendix 1. Report 3.1, 4.4

The Procurement team in the Council's Corporate Support Service (People) has been involved throughout the procurement process. Report 8.2

The money

  • £2,224,370.00 inclusive of VAT Pre-Tender Estimate for the cost of the works

Options considered

  • Chosen: Approve the procurement strategy and invite competitive bids for the Rhyl works. Enables delivery of additional council homes and renovated commercial units in line with the Corporate Plan and regeneration strategies. Report 3.1, 4.4, 5.2
  • Rejected: Refer the procurement decision to Cabinet under Contract Procedure Rule 2.7.2 (ii). Cabinet has chosen to consider the strategy itself, treating it as a Key Decision under the Cabinet Members' Scheme of Delegation. Report 11.2, 11.3

Implications

  • Financial: The Pre-Tender Estimate is £2,224,370.00 inclusive of VAT, with cost over-run identified as the principal risk, mitigated by specialist consultants and industry cost data.
  • Legal: The decision relies on Section 9 of the Local Housing Act 1985 and Contract Procedure Rule 2.7.2 (ii), with agreement required from the Head of Service, Section 151 Officer and Monitoring Officer. Report 11.2
  • Equalities: The Well-Being Impact Assessment concludes the proposal has a positive impact on all well-being goals, including fuel poverty reduction, Active Travel, mental health and Welsh language use.
  • Climate: The works are expected to provide energy efficient Council homes and minimise carbon emissions, and will place sleeping accommodation above the modelled flood level. Report 5.2
  • Other: Additional affordable Council homes are expected to have a positive impact on Adult Social Care and Homelessness services. Report 6.2

Who and where

  • Households in Denbighshire, including those presenting as homeless to the Adult Social Care and Homelessness service Report 6.2
  • Future residents of the upper floor residential units, who will be offered affordable rented Council homes
  • Shops, services and the night time economy in Rhyl town centre, expected to benefit from increased footfall and dwell time
  • Local supply chain businesses in the region, with opportunities through the construction of the scheme
  • Welsh language users, who will benefit from bilingual signage and bilingual lettings particulars

Timeline

  • 22nd May 2018: Cabinet approved the North Wales Regional Regeneration Plan 2018 to 2035 and outline projects including Rhyl High Street buildings.
  • Over a 12-month period before 17th June 2019: More than 2,500 local people were involved in developing the Rhyl Town Centre Masterplan and Vision.
  • 8th December 2020: County Council adopted the Housing and Homelessness Strategy, including actions to facilitate building of Council homes.
  • 23rd February 2021: County Council adopted the Climate and Ecological Change Strategy. Report 5.2
  • 28th July 2026: Cabinet approved the procurement strategy and confirmed the Well-Being Impact Assessment had been considered. Report P2

Plain English for the jargon

  • Pre-Tender Estimate: The estimated cost of the works prepared before competitive bids are sought from contractors.
  • Principal Contractor: The main contractor appointed to manage and deliver the construction works.
  • Well-Being Impact Assessment: An assessment of the effects of a proposal on the well-being goals set out in Welsh legislation.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED that Cabinet – (a) approves the procurement strategy and the invitation of competitive bids for works to provide residential units on the upper floors and to renovate the ground floor commercial units of properties at 64 High Street and 2 – 4 Wellington Road in Rhyl as set out in the Commissioning and Contract Award Form (Appendix 1 to the report), and (b) confirms that it has read, understood and taken account of the Wellbeing Impact Assessment (Appendix 2 to the report) as part of its consideration.
Word for word from the decision Denbighshire published for this meeting. Source: moderngov.denbighshire.gov.uk

Follow this further

Built from Denbighshire's papers

What the report saysPro

Report to Cabinet, 5 pages

Report to Cabinet

Date of meeting 28th July 2026

Lead Member Councillor Rhys Thomas - Lead Member for Housing & Communities

Head of Service Heidi McDougall - Head of Housing & Communities

Report Author Mark Dixon - Lead Officer Housing Development

Title Procurement Strategy for works to properties at 64 High Street and 2-4 Wellington Road in Rhyl

1. What is the report about? 1.1. The report is about the strategy for procuring a Principal Contractor to undertake works to provide residential units on the upper floors of properties owned by the Council at 64 High Street and 2-4 Wellington Road in Rhyl and to renovate the ground floor commercial units at the properties.

2. What is the reason for making this report? 2.1. A decision is required about the procurement strategy for works to provide residential units on the upper floors and to renovate the ground floor commercial units of properties at 64 High Street and 2-4 Wellington Road in Rhyl and to approve the invitation of competitive bids for the works.

3. What are the Recommendations?

3.1That Cabinet approves the procurement strategy and the invitation of competitive bids for works to provide residential units on the upper floors and to renovate the ground floor commercial units of properties at 64 High Street and 2-4 Wellington Road in Rhyl as set out in the Commissioning & Contract Award Form in Appendix 1. 3.2. That Cabinet confirms that members have read, understood and taken account of the Well-Being Impact Assessment in Appendix 2 as part of their consideration.

4. Report details 4.1. At its meeting on 22nd May 2018, Cabinet approved the North Wales Regional Regeneration Plan 2018-2035 which enabled investment to be secured for the region through the Welsh Government Targeted Regeneration Investment programme. Cabinet also approved outline projects for submission by the Council and delegated authority to accept and undertake expenditure on projects accessing support through the programme. One of the outline projects cited involved the acquisition and renovation of key buildings on Rhyl High Street to provide modern contemporary residential living space on upper floors and shared retail space on the ground floor.

4.2Amongst the properties subsequently acquired by the Council to deliver the project were the former Granite store at 64 High Street and 2 Wellington Road, and the adjacent retail premises at 4 Wellington Road.

4.3Works are now required to create residential units on the upper floors of the properties and to renovate the ground floor commercial units.

4.4Cabinet is requested to approve the procurement strategy and the invitation of competitive bids as set out in the Commissioning & Contract Award Form in Appendix 1 to the report.

5. How does the decision contribute to the Corporate Plan 2022 to 2027: The Denbighshire We Want? 5.1. The Council’s Corporate Plan includes a strategic objective to ensure that sufficient good quality housing is available to meet the needs of all Denbighshire residents, and an aim to deliver 170 Council homes subject to the availability of Welsh Government funding. Theme 2 of the Housing & Homelessness Strategy adopted by the County Council at its meeting on 8th December 2020 concerns creating a supply of affordable homes and includes headline actions to facilitate the building of Council homes. This decision will contribute towards the delivery of the Corporate Plan and Housing & Homelessness Strategy by enabling the provision of additional Council homes to be let on an affordable rent.

5.2The proposed works will contribute towards the delivery of the Climate & Ecological Change Strategy adopted by the County Council on 23rd February 2021 by providing additional energy efficient Council homes which will minimize the amount of carbon dioxide emitted.

6. What will it cost and how will it affect other services? 6.1. The Pre-Tender Estimate for the cost of the works is £2,224,370.00 inclusive of VAT.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PROCUREMENT FOR WORKS: Appendix 1 Commissioning and Contract Award Form 64 High Street RhylAppendix 14 pages Download
PDF
PROCUREMENT STRATEGY FOR WORKS: Appendix 2 WBIA Conversion of Rhyl High Street PropertiesAppendix 17 pages Download
PDF
PROCUREMENT STRATEGY FOR WORKS TO PROPERTIES AT 64 HIGH STREET AND 2: 4 WELLINGTON ROAD IN RHYLReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Denbighshire

Search all
  1. PROCUREMENT STRATEGY FOR WORKS TO PROPERTIES AT 64 HIGH STREET AND 2 - 4 WELLINGTON ROAD IN RHYLThis decision
  2. Denbighshire procurement strategyApproved
  3. Consideration of final draft procurement strategy & cpr'sApproved

More from Denbighshire Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 ApologiesChief Executive Decided Open
28 Jul 2026 Declaration of interestsCouncillor Jason McLellan – Personal and Prejudicial Interest – Agenda Item Nos. 9 & 10 Decided Open
28 Jul 2026 Urgent mattersNo urgent matters had been raised. Decided Open
28 Jul 2026 MINUTESRESOLVED that the minutes of the meeting held on 30 June 2026 be received and confirmed as a correct record. Decided Open
28 Jul 2026 Denbighshire county council digital strategy 2026 - 2031RESOLVED that Cabinet – (a) approve the Denbighshire County Council Digital Strategy 2026 – 2031 (Appendix 1 to the r... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies