Development of Small Solar Farms on Council Owned Land

Approved Committee 5 papers

Council approved this item on Tuesday 26 July 2022. Below is the council's own wording, with the papers it was decided on.

Item77/22

Resolved

RESOLVED (Unanimously) 1. That the report attached in Appendix One and the associated business and financial cases in Appendix Two are received. 2. That Council approves the recommendation in the attached report to move to ‘phase two’ of development work in respect of the Watery Lane, Ashbourne site. 3. That approval is given to a supplementary revenue budget of £40,000 for consultancy relating to the next stage of work required, to be financed from the General Reserve. 4. That authority be given to write to Ofgem to consider improving access for smaller and larger developments to feed into the National Grid. The Chairman declared the motion CARRIED .
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Council

Recommendations

1. That the report attached in Appendix One and the associated business and financial cases in Appendix Two are received 2. That Council approves the recommendation in the attached report to move to ‘phase two’ of development work in respect of the Watery Lane, Ashbourne site 3. That approval is given to a supplementary revenue budget of £40,000 for consultancy relating to the next stage of work required, to be financed from the General Reserve.

Wards affected

Ashbourne North

STRATEGIC LINK

The Corporate Plan 2020-24 identified climate change as a key strategic priority under the theme ‘Place - keeping the Derbyshire Dales clean green & safe’. The recommendations in this report support the specific aim to ‘Achieve net zero carbon emissions from District Council operations by 2030’ The project should generate net revenue income for the Council from 2024/25, which will assist in meeting to Corporate Savings Target and the Council becoming more financially sustainable.

Background

1.1In May 2019 the Council declared a Climate Emergency and pledged to make the authority net zero by 2030. In October 2020 the Council unanimously approved a Climate Change Strategy and Action Plan which set out a potential pathway to achieving net zero in terms of direct emissions. The pathway to net zero, identified in the Strategy, is listed as:

• Energy efficiency improvements to existing facilities; • Installation of biomass heating at Matlock Town Hall; • Electrification of heating at 3 key facilities; • Installation of roof mounted solar photovoltaics (PV) at 2 key facilities; • Development of 2MW ground mounted solar PV; • Electrification of the Council’s vehicle fleet.

1.2The plan outlined in broad terms the level of investment - around £2.7 million - that would be required to meet net zero and the period over which that investment would need to be made. Council noted the need to obtain funding to undertake the programme of works required.

1.3On the 14th of October 2021 the Council approved a revenue budget of £30k to fund the engagement of a partner to carry out a detailed feasibility study into the technical and financial viability of ground mounted solar PV arrays. Actual expenditure incurred in 2021/22 was £14,589, an under-spend of £15,411.

2 REPORT

2.1APSE Energy were commissioned to undertake the study - a local authority energy collaboration, part of APSE, a not for profit local government body who work with over 300 local authorities across the UK. The consultants engaged through APSE Energy have worked on many local authority solar farm projects and have a sound understanding of the relevant context, technology, financial and environmental considerations. They have undertaken many and varied consultancy projects which are similar in nature to the Council’s brief.

2.2The resulting report is attached in Appendix One and the Business and Financial cases for the Watery Lane site referred to on page 14 in Appendix Two.

2.3The report concludes that while two of the five sites could be developed the Stoney Middleton site is not viable due the cost of grid connection and the sale of power.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Development of Small Solar Farms on Council Owned LandReport 509 KB DownloadRead as text
PDF
Solar Farms Appendix 1 /22Appendix 365 KB Download
PDF
Solar Farms Appendix 2a /22Appendix 552 KB Download
PDF
Solar Farms Appendix 2b /22Appendix 473 KB Download
PDF
Solar Farms Appendix 2c /22Appendix 554 KB Download

At this meeting

Whole meeting

Who was there

28 of 46 attended
SB
Sue Bull CONChair, present
AS
Andrew Shirley CONVice-Chair, apologies
JA
Jacqueline Allison GPCommittee Member, present
RA
Robert Archer LIBDEMCommittee Member, apologies
JA
Jason Atkin CONCommittee Member, present
RB
Richard Bright INDCommittee Member, apologies
MB
Matt Buckler GPCommittee Member, present
MB
Martin Burfoot LIBDEMCommittee Member, present
SB
Sue Burfoot LIBDEMCommittee Member, present
NB
Neil Buttle GPCommittee Member, present
DC
David Chapman CONCommittee Member, present
PC
Paul Cruise LIBDEMCommittee Member, apologies

All 46 on the meeting page

More from Derbyshire Dales Council

All decisions
MeetingDecisionOutcome
23 Jul 2026 CommitteesRESOLVED (unanimously) That the non-exempt minutes of the listed in the Minute Book for the period 14 May 2026 to 02 ... Decided Open
23 Jul 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a... Approved Open
23 Jul 2026 Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31RESOLVED (unanimously) 1. That the provisional Capital Out-Turn of £15,075,300 as detailed in Appendix 1 be approved.... Approved Open
23 Jul 2026 Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m... Noted Open
22 Jul 2026 Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ... Decided Open