RESOLVED (Unanimously) That approval be given to a supplementary revenue budget of £39,778 a year from 2022/23 to allow for increased annual costs for the Council’s Financial Management System ( Agresso Business World), to be financed from the General Reserve. The Chairman declared the motion CARRIED . The meeting was briefly adjourned from 7:41pm to 7:50pm.
Word for word from the decision Derbyshire Dales published for this meeting.Source: democracy.derbyshiredales.gov.uk
That Council approves a supplementary revenue budget of £39,778 a year from 2022/23 to allow for the increased annual costs for the Council’s Financial Management System (Agresso Business World), to be financed from the General Reserve.
Wards affected
None
STRATEGIC LINK
A fully supported Financial Management System will help to provide services efficiently and to reduce the risks of service disruption. The provision of sound financial information supports the achievement of all council priorities, but is especially helpful in monitoring the achievement of savings or additional income required to achieve a sustainable financial plan.
1 REPORT
1.1The Council uses Unit 4’s “Agresso Business World” as its corporate Financial Management System. Agresso is one of the Council’s core systems and encompasses all of the Council’s financial functions, except payroll. The Council currently uses the following Agresso modules:
• General Ledger • Budgeting • Requisition and Purchase Order Processing • Payment of suppliers and other creditors • Invoicing for Sundry Debtors • Bank Reconciliation • VAT Accounting • Report writing tools. 1.2 The Agresso system is hosted on servers that are maintained by North East Derbyshire District Council (NEDDC) as part of the ICT partnership. The servers that host Agresso use SQL 2013 as an operating system. NEDDC has informed the Council that the support agreement for SQL 2013 will expire in July 2022. Arrangements are being made to extend this, but this can only be achieved for a temporary period.
1.3Running an unsupported system is a risk. As well as providing management information, such as for budget monitoring, Agresso is used to pay suppliers, to raise invoices for trade waste, rents and other fees and charges and account for VAT. If the service was not available, such transactions would be delayed resulting in service disruption for our suppliers and customers; there is also a risk of a financial penalty for late submission of VAT claims. As the extended SQL 2013 support is a temporary period, we must upgrade Agresso to a version that is compatible with SQL 2016 or later, or move to the cloud, so that we have a supported system by the time that the extended support expires.
1.4Ruling out the option of “doing nothing”, there are two options for the upgrade:
a) Stay ‘on premise’ and upgrade Agresso to a version compatible with all the latest SQL
- the annual license would cost less than for the cloud version;
However,
- The cost of upgrades has averaged £20,661 a year (with inflation), increasing the annual cost; - DDDC / NEDDC would continue to be responsible for maintenance, patches, upgrades etc. which haven’t been kept up to date in the past as this is a significant demand on teams that are already stretched; - Unit 4 has indicated that they might have more frequent upgrades (quarterly), meaning more DDDC / NEDDC resources are required.
b) to move to a Cloud-based version, hosted by Unit 4.
- This seems inevitable, so it would be inefficient to upgrade on premise now and have to upgrade to cloud later; better to go to cloud in one step; - All upgrades, security patches & maintenance will be done by Unit 4, reducing the level of involvement of DDDC / NEDDDC staff; - Improvements in accessibility, business continuity etc.
However,
- There is an increase in the annual cost of licenses (revenue expenditure).
1.5Following discussions between DDDC and Unit4, it was mutually agreed that this has presented itself as a good opportunity for the Council to strongly consider migrating to Unit4’s “Software As A Service” (SaaS) offering and ensuring that the Council benefits from being in the Cloud.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a...
Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m...
Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.