RESOLVED (Unanimously) 1. That the recommendation of the Governance and Resources Committee of 8 th March 2023 to accept the grant offer, as set out in this report, be approved. 2. That the recommendation of the Governance and Resources Committee of 8 th March 2023 be approved for the addition of £2,189,500 to the Capital Programme for 2024/25 for ‘PSDS3b Decarbonisation at Arc Leisure Centre Matlock and Wirksworth Leisure Centre’, to be financed by a grant of £1,925,000 and a ‘like for like’ contribution of £264,000, the latter being financed from the capital receipts reserve. 3. That authority be delegated to the Director of Community and Environmental Services, the Director of Resources and the Chief Executive to utilise Leisure Centre support funding, should it become available. The Chairman declared the motion CARRIED .
Word for word from the decision Derbyshire Dales published for this meeting.Source: democracy.derbyshiredales.gov.uk
To gain agreement for the acceptance of a grant offer from the Public Sector Decarbonisation Scheme (PSDS) phase 3b of £1.9m in order to decarbonise the Arc Matlock and Wirksworth Leisure Centre.
Recommendations
1. That the recommendation of the Governance and Resource Committee of 8th March 2023 to accept the grant offer, as set out in this report, be approved.
2. That the recommendation of the Governance and Resource Committee of 8th March 2023 be approved for the addition of £2,189,500 to the capital programme for 2024/25 for ‘PSDS3b Decarbonisation at Arc Leisure Centre Matlock and Wirksworth Leisure Centre’, to be financed by a grant of £1,925,500 and a ‘like for like’ contribution of £264,000, the latter being financed from the capital receipts reserve.
List of Appendices
None
Background papers
None
Consideration of report by Council or other committee None
Council Approval Required Yes
Exempt from Press or Public No Decarbonisation of the Arc Leisure Centre (Matlock) and Wirksworth Leisure Centre
Background
1.1The PSDS provides grants for public sector bodies to fund heat decarbonisation and energy efficiency measures, putting the public sector at the forefront of decarbonising buildings in the UK and in a leadership role to create exemplar projects in our communities that pave the way to help the UK meet its Carbon Budgets and Net Zero commitments. It is aimed at taking a ‘whole building’ approach to heat decarbonisation, combining heat decarbonisation with energy efficiency measures. Most of the buildings in the public sector still rely on fossil fuel-based heating and, as these heating systems approach the end of their working lives, it is an ideal opportunity to transition those systems to low carbon heating.
1.2Reflecting the importance of the public sector’s role in meeting the government’s commitment to net zero by 2050, the Net Zero Strategy and Heat and Buildings Strategy confirmed that Phase 3 of the PSDS would comprise of £1.425 billion of funding over the period 2022/2023 to 2024/2025.
1.3The approved Climate Change Strategy and Action Plan set out a pathway to reducing emissions from Council operations in order to achieve net zero by 2030. This included energy efficiency projects at key sites, electrification of heating and installation of roof mounted solar PV panels to reduce electricity consumption.
1.4Emissions from leisure centres were not included in the Council’s estimated baseline carbon footprint in 2019-20 due to their outsourced management arrangement. However, the strategy and action plan recommended that their emissions were addressed in addition to the emissions that the Council is directly responsible for. As such, an emissions report for 2021-22 was produced. This estimated the emissions from the leisure centres in Ashbourne, Bakewell, Matlock and Wirksworth as 995t CO2e. For context, the rest of the Council’s estate and operations generated 605t CO2e in total in the same year. It is therefore clear that emissions from the leisure centres are significant.
1.5The PSDS grants are available through a competitive process administered by Salix on behalf of BEIS (now ESNZ – Department of Energy Security and Net Zero). The Council has previously been successful in being awarded Phase 1 funding (£734k – Ashbourne Leisure Centre) and Phase 3a funding (£562k – Town Hall and ABC). The Phase 1 project is nearing completion and the Phase 3a project is just about to start delivery, due to complete by end July 2023.
1.6In addition to PSDS, the government also offers funding for the necessary technical studies and design work required before installations can begin – Low Carbon Skills funding (LCSF). Again, this funding is competitive.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a...
Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m...
Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.