Resolved
RESOLVED (unanimously) That the annual report and risk management arrangements be approved. The Chair declared the motion CARRIED .
Governance & Resources Committee approved this item on Thursday 18 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED (unanimously) That the annual report and risk management arrangements be approved. The Chair declared the motion CARRIED .
That the annual report and risk management arrangements be approved.
List of Appendices Appendix 1 Internal Audit Review Recommendations Appendix 2 Strategic Risk Register: Mitigating Actions
Background Papers None
Consideration of report by Council or other committee Not applicable
Council Approval Required No
Exempt from Press or Public No Risk Management Annual Report 2023/24
1.1The Council’s Risk Management Policy and Strategy, approved by this Committee in September 2023, requires the Chief Executive to report to Members, by way of an annual report on the Council’s Risk Management arrangements and how key strategic risks are being managed.
1.2This report describes the current risk management processes and working practices, which have been developed to ensure they continue to provide the Council with the correct levels of insight and support in relation to its risk exposure. The report illustrates the strategic risks and scores them as high (red), medium (yellow) or low (green). The report also shows the actions that are planned to mitigate or reduce the risks.
1.3The Council operates a risk management programme whereby risks associated with the Corporate Plan, its key strategic objectives and individual Service Plan Key Actions are formally assessed. The Council identifies risks at two levels:
• Strategic Risks: These are the risks that will significantly impact the Council in the delivery of its Strategic Objectives and Corporate Plan; and
• Operational (Service) Risks: These are the risks which will impact on the delivery of each service at an operational level. Managing these risks will assist each Head of Service in the delivery of their Service Plan objectives and key actions.
1.4Relevant individuals (the Risk Management & Continuity Group or RCG) meet on a quarterly basis to discuss the risks facing the Council and the delivery of its objectives. Those risks highlighted during these sessions are analysed and prioritised and further actions identified. These are captured within the Operational and Strategic Risk Registers.
1.5An essential part of the process involves ensuring all risks have clear ownership. Service Managers are required to identify the key internal controls for each risk they are responsible for and to identify mitigating controls. The risk management methodology provides guidance for risks to be scored, enabling officers to report risks which may prevent them from achieving their required aims.
1.6Risks are regularly reported to the Risk Continuity Group (which includes all members of the Corporate Leadership Team as well as other key colleagues), ensuring that risks, risk management etc. are challenged and reported effectively. 1.7 Further information and guidance on the Council’s risk management processes and procedures can be found in the Risk Management Policy and Strategy for 2023 to 2025.
2. Key Issues for 2023/24
2.1The Council remains committed to ongoing risk management activities. Risk management practices and procedures are well embedded. The Risk Continuity Group continues to be well attended. Key actions arising since the last annual report include:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management: Annual Report 2023/24Report | 216 KB | DownloadRead as text |
Follow Governance & Resources Committee at Derbyshire Dales and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of the meeting of the Governance and Resources Committee held on 2 July 2026 ... | Approved | Open |
| 3 Sep 2026 | Proposed Transfer of Land for Affordable Housing - Land Off Yeld Close, BakewellRESOLVED with 5 votes FOR 2 votes AGAINST 2 abstentions 1. That the consent of the Secretary of State is sought to tr... | Agreed | Open |
| 3 Sep 2026 | External Audit Progress ReportRESOLVED (unanimously) That the shown in Appendix 1 be received and noted. The Chair declared the motion CARRIED . | Noted | Open |
| 3 Sep 2026 | Annual Report on the Regulation of Investigatory Powers Act (RIPA)RESOLVED (unanimously) 1. That the Annual Report on the Council’s use of the Regulation of Investigatory Powers Act (... | Approved | Open |
| 3 Sep 2026 | Risk Management - Annual Report 25/26RESOLVED with 8 votes FOR 0 votes AGAINST 1 abstention That the annual report and risk management arrangements be app... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.