Governance & Resources Committee, Thursday 3 April 2025 at 6.00pm

Asset Management Plan - Land Holdings Review Phase 9

Noted Committee 2 papers

Governance & Resources Committee noted this item on Thursday 3 April 2025. Below is the council's own wording, with the papers it was decided on.

Item421/24

Resolved

RESOLVED (unanimously) 1. That the leases at Sites nos. 1 and 2 be renewed at the Agricultural Business Centre to Bagshaws LLP and Derbyshire Dales Council for Voluntary Services on the terms outlined in Appendix 1 of this report. 2. That a lease at Site 3, be renewed at Bath Gardens Bakewell to the Bakewell Town Bowling Club on the terms outlined in Appendix 1 of this report. 3. That Site no. 4. Station House, Matlock be declared as surplus to requirements and that the Estates and Facilities Manager be delegated to proceed with disposal of the site in accordance with that outlined in Appendix 1 of this report. 4. That it is noted that the disposal of site no. 3 above comprises an undervalue transaction permitted under the General Disposal Consent 2003. 5. Responsibility for legal and surveyors’ costs in respect of all the transactions above are detailed in Appendix. 1 of this report. The Chair declared the motion CARRIED.
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Governance & Resources Committee

Recommendations

1. That the leases at Sites nos. 1 and 2 be renewed at the Agricultural Business Centre to Bagshaws LLP and Derbyshire Dales Council for Voluntary Services on the terms outlined in Appendix 1 of this report.

2. That a lease at Site 3, be renewed at Bath Gardens Bakewell to the Bakewell Town Bowling Club on the terms outlined in Appendix 1 of this report.

3. That Site no. 4. Station House, Matlock be declared as surplus to requirements and that the Estates and Facilities Manager be delegated to proceed with disposal of the site in accordance with that outlined in Appendix 1 of this report.

4. That it is noted that the disposal of site no. 3 above comprises an undervalue transaction permitted under the General Disposal Consent 2003.

5. Responsibility for legal and surveyors’ costs in respect of all the transactions above are detailed in Appendix. 1 of this report.

List of Appendices

Appendix 1 Land Holdings Review Phase 9 by Property Background Papers Non-applicable

Consideration of report by Council or other committee Not applicable

Council Approval Required No

Exempt from Press or Public No Asset Management Plan – Land Holdings Review Phase 8

Background

1.1The Asset Management Plan (AMP) is intended to set out the Council’s strategic approach to the management of its land and property and to provide a framework within which property asset decisions can be made in support of the Council’s corporate aims and objectives.

1.2The Asset Management Plan recommends that unused or surplus buildings and land (of area 0.1ha and above excluding parks and pleasure grounds and public open space) be reviewed to establish whether they should be sold or whether they could contribute to the Council’s key objectives of economic development and affordable housing or whether they could form part of a Community Asset Transfer.

1.3This the ninth of a number of phases of reports consider the future arrangements for surplus land and buildings across the district.

2. Key Issues

2.1Phase 9 of the Land Holdings Review covers 4 sites; 2 which require leases to be renewed on commercial terms for a term of 21 years, 1 site where a lease is required to be surrendered and a longer Community Asset transfer via lease is entered into and 1 site disposal of surplus land & building. Following consideration of planning, legal and estate management factors, together with operational requirements, recommendations are made regarding whether the sites should be retained, allocated for a particular use or leased and the terms which would apply.

2.2An appraisal of each site has taken place comprising advice on any planning constraints, legal restrictions, and maintenance liabilities/costs.

2.3Site nos. 1 and 2. involve renewing the lease of offices to the existing tenants at Agricultural Business Centre, Bakewell.

2.4Site 3 concerns surrendering the existing lease and entering into a new lease to the existing tenant at Bath Gardens Bakewell.

2.5Site 4 concerns the former Station Master’s House and associated gardens of 0.03acres (0.01ha) located adjacent to the railway station in Matlock.

2.6The results and recommendations for the four sites are summarised in Appendix 1 together with plans of each site.

3. Options Considered and Recommended Proposal

3.1Where appropriate, these are outlined in the appendices in respect of each site. 4. Consultation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1a. AMP Land Holdings Review Phase 9 Appendix 1 Final /24Appendix 936 KB Download
PDF
Asset Management Plan: Land Holdings Review Phase 9Report 98 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 21 attended
NW
Nick Wilton LIBDEMChair, present
NB
Neil Buttle GREENVice-Chair, present
AB
Anthony Bates CONCommittee Member, present
GB
Geoff Bond CONCommittee Member, present
BB
Bob Butcher LABCommittee Member, present
GG
Gareth Gee CONCommittee Member, apologies, sent representative
DG
Dawn Greatorex LABCommittee Member, present
SF
Steve Flitter LIBDEMCommittee Member, present
DH
David Hughes LIBDEMCommittee Member, present
SR
Simon Ripton LABCommittee Member, present
RS
Roger Shelley LIBDEMCommittee Member, apologies, sent representative
SH
Susan Hobson CONSubstitute, present as substitute

All 21 on the meeting page

On this subject at Derbyshire Dales

Search all
  1. Asset Management Plan - Land Holdings Review Phase 9This decision
  2. Asset management plan - land holdings review phase 11Agreed
  3. Asset management plan 2025-2030Approved
  4. Asset Management Plan - Land Holdings Review Phase 10Agreed
  5. Asset Management Plan - Land holdings Review Phase 8Agreed
  6. Asset Management Plan - Land Holdings Review Phase 7Agreed

More from Derbyshire Dales Governance & Resources Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of the meeting of the Governance and Resources Committee held on 2 July 2026 ... Approved Open
3 Sep 2026 Proposed Transfer of Land for Affordable Housing - Land Off Yeld Close, BakewellRESOLVED with 5 votes FOR 2 votes AGAINST 2 abstentions 1. That the consent of the Secretary of State is sought to tr... Agreed Open
3 Sep 2026 External Audit Progress ReportRESOLVED (unanimously) That the shown in Appendix 1 be received and noted. The Chair declared the motion CARRIED . Noted Open
3 Sep 2026 Annual Report on the Regulation of Investigatory Powers Act (RIPA)RESOLVED (unanimously) 1. That the Annual Report on the Council’s use of the Regulation of Investigatory Powers Act (... Approved Open
3 Sep 2026 Risk Management - Annual Report 25/26RESOLVED with 8 votes FOR 0 votes AGAINST 1 abstention That the annual report and risk management arrangements be app... Approved Open