Internal Audit Progress Update 2024/25

Approved Committee 3 papers

Governance & Resources Committee approved this item on Thursday 3 July 2025. Below is the council's own wording, with the papers it was decided on.

Item38/25

Resolved

RESOLVED (unanimously) That the report be approved. The Chair declared the motion CARRIED .
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Governance & Resources Committee

Wards affected

District Wide

Report Summary The report provides a progress update in respect of the 2024/2025 Internal Audit Plan and provides assurance on the governance, risk and control arrangements in place. The report includes a summary of internal audit reports issued since the last meeting of this committee.

Recommendation

1. That the report be approved.

List of Appendices

Appendix 1 Internal Audit Reports Issued Mid- February 2025 to June 2025

Appendix 2 Final progress update on the completion of the 2024/2025 Internal Audit Plan

Background papers

None

Consideration of report by Council or other committee

Not Required Council Approval Required No

Exempt from Press or Public No Progress Update on the 2024/25 Internal Audit Plan

Background

1.1The 2024/25 Operational Audit Plan was approved by the Governance and Resources Committee on the 21st of March 2024. The plan provides a framework by which service functions are reviewed to test and report on the adequacy and effectiveness of the governance, risk and control arrangements in place.

1.2This report details the results of the internal audit reviews undertaken since the last meeting and the final progress update on the 2024/2025 Internal Audit Plan.

2. Report

2.1Attached, as Appendix 1, is a summary of reports issued since the Committee last met in respect of the 2024/2025 financial year. The Appendix shows for each report the level of assurance given in respect of the audit area examined and the number of recommendations made / agreed where a full response has been received.

2.2The table below provides the meaning of the assurance levels that can be awarded in terms of risk and control. Assurance Level Definition Substantial There is a sound system of controls in place, designed to Assurance achieve the system objectives. Controls are being consistently applied and risks well managed. Reasonable The majority of controls are in place and operating Assurance effectively, although some control improvements are required. The system should achieve its objectives. Risks are generally well managed. Limited Assurance Certain important controls are either not in place or not operating effectively. There is a risk that the system may not achieve its objectives. Some key risks were not well managed. Inadequate There are fundamental control weaknesses, leaving the Assurance system/service open to material errors or abuse and exposes the Council to significant risk. There is little assurance of achieving the desired objectives.

2.3This period, two reports have been issued, both with reasonable assurance.

2.4In respect of the audits being reported, no fraud was identified.

2.5Attached at Appendix 2 is the final position in respect of the completion of the 2024/2025 internal audit plan, the majority of the plan has been completed. The whole of the plan would have been completed however the full time Auditor went on maternity leave at the beginning of October 2024 and has not yet returned to work. Consequently, a few low-risk audits have been deferred to future year plans – election expenses, parks, VAT and recruitment and selection. Health and safety is a medium-risk audit that has been deferred as the Council has only recently appointed a health and safety officer and this audit is currently in progress.

3 Options Considered and Recommended Proposal

3.1N/A

Consultation

4.1No public consultation is required.

5 Timetable for Implementation

5.1N/A

6 Policy Implications

6.1Audit reviews help to ensure that the Council’s resources and priorities are focused on achieving the objectives within the corporate plan and that there are appropriate governance, risk and control arrangements in place. 7 Financial and Resource Implications

7.1There are no financial implications arising from this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2a. Internal Audit Progress Report: Appendix 1 Internal Audit Reports Issued 2024.25 /25Appendix 63 KB Download
PDF
2b. Internal Audit Progress Report: Appendix 2 Final progress on the 2024.25 Internal Audit Plan /25Appendix 65 KB Download
PDF
Internal Audit Progress Update 2024/25Report 99 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 22 attended
NW
Nick Wilton LIBDEMChair, present
NB
Neil Buttle GREENVice-Chair, present
AB
Anthony Bates CONCommittee Member, present
GB
Geoff Bond CONCommittee Member, present
SB
Sue Bull CONCommittee Member, present
BB
Bob Butcher LABCommittee Member, present
NN
Nigel Norman Edwards-Walker DFCommittee Member, present
SF
Steve Flitter LIBDEMCommittee Member, apologies, sent representative
DH
David Hughes LIBDEMCommittee Member, apologies, sent representative
SR
Simon Ripton LABCommittee Member, present
RS
Roger Shelley LIBDEMCommittee Member, present
MB
Martin Burfoot LIBDEMSubstitute, present as substitute

All 22 on the meeting page

On this subject at Derbyshire Dales

Search all
  1. Internal Audit Progress Update 2024/25This decision
  2. Internal Audit Progress UpdateNoted
  3. Internal Audit Annual Report 2025/26Decided
  4. Review of the Effectiveness of Internal AuditAgreed
  5. Internal Audit Strategy 2026 - 2028Approved
  6. Internal Audit CharterAgreed

More from Derbyshire Dales Governance & Resources Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of the meeting of the Governance and Resources Committee held on 2 July 2026 ... Approved Open
3 Sep 2026 Proposed Transfer of Land for Affordable Housing - Land Off Yeld Close, BakewellRESOLVED with 5 votes FOR 2 votes AGAINST 2 abstentions 1. That the consent of the Secretary of State is sought to tr... Agreed Open
3 Sep 2026 External Audit Progress ReportRESOLVED (unanimously) That the shown in Appendix 1 be received and noted. The Chair declared the motion CARRIED . Noted Open
3 Sep 2026 Annual Report on the Regulation of Investigatory Powers Act (RIPA)RESOLVED (unanimously) 1. That the Annual Report on the Council’s use of the Regulation of Investigatory Powers Act (... Approved Open
3 Sep 2026 Risk Management - Annual Report 25/26RESOLVED with 8 votes FOR 0 votes AGAINST 1 abstention That the annual report and risk management arrangements be app... Approved Open