AI summaryDerbyshire Dales Community and Environment Committee approved £34,900 of capital spending to replace three pumps with two at Bakewell Swimming Pool, with £6,800 revenue to compensate operator Freedom Leisure for a 5-day closure.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedReplace 3 pumps with 2 improved pumps at Bakewell Swimming Pool
Money£34,900 capital + £6,800 revenueCapital programme 2026/27 plus revenue compensation to Freedom Leisure
What happens nextCouncil to decide on 27 Nov 2025Full Council to consider capital programme inclusion
Who it affectsBakewell Swimming Pool users5-day pool closure required for installation
What was decided
Committee approved replacement of the three current pumps with two improved pumps, raised onto an Inertia Base filled with concrete, with pipework realignment. Report P1
Committee asked Council to include £34,900 in the capital programme for 2026/27. Report P2
Committee authorised £6,800 from the revenue budget to reimburse Freedom Leisure for the 5-day closure caused by the works. Report P3
Why
The landlord changed upstairs use to private accommodation and noise from the plant room stopped a tenant being found; a formal notice to repair has been issued through solicitors. Report 1.1, 1.2, 2.1
The pumps are identified in the asset replacement programme as reaching end of life in 2028, beyond the initial 10-year Freedom Leisure contract which ends in 2027. Report 1.4, 2.2
Officers consider the works a reasonable and proportionate response to reduce the risk of further legal action from the landlord. Report 2.6, 7.2
What happens next
Council will consider the capital programme revision at its meeting on 27th November 2025, with financing from capital receipts. Report 5.1, 8.1
Installation lead time is 8 to 10 weeks after the order is placed. Report 5.2
If a 5-year contract extension is agreed after 2028, Freedom Leisure must reimburse the Council £14,785, with the £34,900 figure then being a like-for-like replacement cost. Report P4, 2.5
The money
£34,900 Capital cost of replacing 3 pumps with 2 improved pumps and installing an Inertia Base Report P2, 8.1
£6,800 Revenue compensation to Freedom Leisure for 5-day pool closure Report P3, 8.2
£14,785 Reimbursement due from Freedom Leisure if a 5-year extension is agreed after 2028 Report P4, 2.5
£6,930 Quote for Freedom Leisure to improve bearings on existing pumps Report 2.3
£7,315 Quote for the Inertia Base installation only Report 2.4
£22,100 Alternative like-for-like pump replacement plus Inertia Base Report 3.1
£6,390 Quote for refurbishing current pump bearings Report 3.3
£1,360 Approximate daily loss of income for pool closure
Options considered
Chosen: Replace 3 pumps with 2 improved pumps plus Inertia Base, £34,900. Better noise reduction for landlord, more efficient, lower power use Report P1, P2, 3.2, 10.1
Rejected: Like-for-like replacement of 3 pumps plus Inertia Base, £22,100. Not guaranteed to satisfy landlord on noise; higher total with closure cost Report 3.1, 3.2
Rejected: Refurbish existing pumps and install Inertia Base, £6,390 plus £7,315. Replacements still needed around 2028 and unlikely to satisfy landlord on noise Report 3.3
Implications
Legal: A formal notice to repair has been received from the landlord; failure to act could lead to further legal action. Report 2.1, 7.2
Financial: Capital funding available from capital receipts; financial risk assessed as low. Report 8.1
Climate: Two new pumps will replace three and run with improved efficiency, reducing power consumption. Report 10.1
Risk: If the project timeline overruns, the capital spend can be carried over into 2027/28. Report P41
Other: Reimbursement arrangement with Freedom Leisure provides a safeguard for public funds if a contract extension is agreed. Report 7.3
Who and where
Users of Bakewell Swimming Pool, who will face a 5-day closure
Freedom Leisure, the operator of the pool Report 4.1, 2.3
The landlord of Bakewell Swimming Pool, who issued the notice to repair Report 1.1, 2.1
Derbyshire Dales District Council, in its role as landlord and asset owner Report 1.3
Timeline
13th November 2025: Community and Environment Committee approves the recommendations
27th November 2025: Council to consider inclusion of £34,900 in the capital programme Report 5.1, 8.1
8 to 10 weeks after order: Installation of new pumps and Inertia Base Report 5.2
2027: Initial 10-year Freedom Leisure contract term ends Report 2.2
2028: Pumps identified as reaching end of life in asset replacement programme Report 1.4, 2.2
Plain English for the jargon
Inertia Base: A concrete-filled mounting that the pumps sit on, designed to reduce vibration and noise transmitted through the floor.
Capital programme: The Council's approved plan for long-term spending on assets, set each year by full Council.
Capital receipts: Income the Council receives from selling assets, which can be used to fund new capital spending.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item201/25
Resolved
RESOLVED (unanimously) 1. That Committee approve the replacement of the 3 current pumps at Bakewell Swimming Pool with 2 improved performing pumps, raise the pumps onto an Inertia Base filled with concrete and realignment of pipe work. 2. That Council be requested to approve the inclusion of £34,900 in the capital programme for 2026/27 to replace the 3 current pumps with 2 higher quality and more efficient pumps. 3. That provision of £6,800 be authorised from the revenue budget to reimburse Freedom Leisure for the 5-day closure caused by the works. 4. That Freedom Leisure be required to reimburse the Council in the sum £14,785 should a contract extension of 5 years be agreed following the end of the initial 10 year contract in 2028. The Chair declared the motion CARRIED .
Word for word from the decision Derbyshire Dales published for this meeting.Source: democracy.derbyshiredales.gov.uk
1. That Committee approve the replacement of the 3 current pumps at Bakewell Swimming Pool with 2 improved performing pumps, raise the pumps onto an Inertia Base filled with concrete and realignment of pipe work.
2. That Council be requested to approve the inclusion of £34,900 in the capital programme for 2026/27 to replace the 3 current pumps with 2 higher quality and more efficient pumps.
3. That provision of £6,800 be authorised from the revenue budget to reimburse Freedom Leisure for the 5-day closure caused by the works.
4. That Freedom Leisure be required to reimburse the Council in the sum £14,785 should a contract extension of 5 years be agreed following the end of the initial 10 year contract in 2028.
List of Appendices None
Background Papers None
Consideration of report by Council or other committee Yes Council Approval Required Yes
Exempt from Press or Public No BAKEWELL SWIMMING POOL PUMP REPLACEMENTS
Background
1.1Following the landlord of Bakewell Swimming Pool changing the use of the upstairs space from commercial letting to private accommodation the noise from Bakewell Swimming Pool (BSP) has affected the ability to find a tenant.
1.2Following a noise survey carried out by DDDC’s Estates Team and a separate investigation from the landlord it was identified that work was required to improve the sound volume being generated by the plant room, one key area was to carry out work on the pumps and raise them off the ground.
1.3It has been deemed reasonable that the Council / Freedom Leisure are required to carry out some works to improve the current sound being made from the Plant Room of Bakewell Swimming Pool.
1.4Bakewell pumps have been identified in the asset replacement programme as reaching end of life in 2028.
2. Key Issues
2.1The landlord has not been satisfied with the response from Officers previously and has now instructed solicitors to issue a notice to repair.
2.2As the asset replacement programme identifies the pumps would require replacing around 2028 this is outside of Freedoms current contract length as the initial 10-year term ends in 2027.
2.3Freedom would have a responsibility at this stage to improve the bearings on the pumps to ensure the current pumps are in good working condition. This has been quoted as £6,930. On its own this would not satisfy the landlord with a sufficient reduction in noise.
2.4It’s been identified the pumps need raising off the floor as they currently sit and placed onto an Inertia Base filled with concrete. This work is quoted as £7,315. As this work is only required to reduce the sound and satisfy the landlords request, it’s felt this would be unreasonable to assume Freedom would cover the costs and aren’t obliged to do more than keep the current pumps in good working order.
2.5Should the 5-year extension be agreed Freedom would be responsible for replacing the pumps like for like, this has been identified for 2028. To replace the 3 pumps with equal quality replacements has been quoted at a cost of £14,785. Recommendation 4 is to note Freedom Leisure pay this amount back to the Council should the contract extension be agreed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Community & Environment Committee at Derbyshire Dales and we tell you when its next papers are published, before the meeting rather than after it.
Approval of Minutes of Previous MeetingRESOLVED That the minutes of the meeting of the Community and Environment Committee held on 14 May 2026 be approved a...
Approval of Minutes of Previous MeetingRESOLVED That the minutes of the meeting of the Community and Environment Committee held on 15 January 2026 be approv...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.