External Auditor's Progress Report and Draft Auditor's Annual Report for the Financial Year Ended 31 March 2025
NotedCommittee3 papers
AI summaryDerbyshire Dales Governance and Resources Committee received the draft auditor's annual report and progress report from Forvis Mazars LLP for the year ended 31 March 2025, with an unqualified opinion anticipated and 2025/26 audit fees budgeted at £142,687.
Written from the decision and the officer reportPDF Pro
OutcomeNotedDraft auditor's report and progress report accepted
Money£142,687 budgeted for 2025/26 audit feesFees for 2024/25 audit not yet finalised
What happens nextAudited accounts approval in January 2026Publication deadline 27 February 2026
Who it affectsCouncil's 2024/25 financial accountsFinal accounts and audit completion process
What was decided
The committee received the Draft Auditor's Annual Report for the year ended 31 March 2025 from Forvis Mazars LLP. Report P1, 2.1
The committee received and noted the External Audit Progress Report from Forvis Mazars LLP. Report P2, 1.1
The external auditor anticipates issuing an unqualified opinion on the 2024/25 financial statements, with no significant weaknesses identified in value for money arrangements. Report 2.3, P21
Why
The reports are part of the process for finalising and approving the Council's Statement of Accounts for 2024/25. Report 1.1, 2.1
The draft was brought to this meeting rather than waiting for the final version, to be more expedient than presenting the final at the January 2026 meeting. Report 2.1
National audit backlog led to amended Accounts and Audit Regulations extending publication deadlines for local authorities. Report 1.2, 1.3
What happens next
The Draft Auditor's Annual Report will be published on the Council's website as soon as practicable after committee approval. Report 4.2, 5.1
The audited financial statements for 2024/25 and Audit Completion Report are scheduled for approval at the January 2026 committee meeting. Report 2.1, 4.3
Final audited financial statements must be published by 27 February 2026 under the revised statutory deadline. Report 1.3, P12
The money
£142,687 2025/26 budget for external audit fees Report 7.2
Options considered
Chosen: Receive and note both reports (unanimously approved). Standard process for finalising the 2024/25 accounts Report 3.1, P1, P2
Implications
Financial: External audit fees for 2024/25 have yet to be finalised; fees are set by Public Sector Audit Appointments Ltd. Financial risk assessed as low. Report 7.1, 7.2, 7.5
Legal: External audit process conducted in accordance with the Accounts and Audit Regulations; legal risk assessed as low. Report 8.2, 8.3
Risk: No significant weaknesses identified in arrangements for economy, efficiency and effectiveness; work should provide reassurance on financial management. Report 11.1, 11.2
Equalities: No equalities issues arising from this report. Report 9.1
Climate: No climate change issues arising from this report. Report 10.1
Who and where
The Council's 2024/25 financial accounts and audit process Report 1.1, 2.1
Local electors and other parties (no questions or objections received on the financial statements) Report 2.3, P21, 4.1
The Council's finance team (described as responsive and helpful during the audit) Report P21
Timeline
8 August 2024: Draft Statement of Accounts for 2024/25 and Notice of Public Rights placed on the Council's website Report 4.1
8 August to 23 September 2024: Accounts available for public inspection; no objections received Report 4.1
November 2025: Draft Auditor's Annual Report and External Audit Progress Report considered by committee Report P5, 2.1
January 2026 (currently scheduled): Audited financial statements for 2024/25 and Audit Completion Report to be approved by committee Report 2.1, 4.3
27 February 2026: Statutory deadline for publication of audited financial statements for 2024/25 Report 1.3, P12
31 January 2027: Statutory deadline for publication of audited financial statements for 2025/26 Report P13
Plain English for the jargon
VFM (Value for Money): The auditor's assessment of whether the Council has proper arrangements to secure economy, efficiency and effectiveness in its use of resources
Unqualified opinion: An auditor's opinion that the financial statements give a true and fair view, with no material concerns raised
PSAA: Public Sector Audit Appointments Ltd, the body responsible for appointing auditors and setting fee scales for opted-in principal authorities
S.151 Officer: The statutory chief finance officer responsible for the proper administration of a council's financial affairs
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item214/25
Resolved
RESOLVED (unanimously) 1. That the “Draft Auditor’s Annual Report for the year ended 31 March 2025”, shown in Appendix 1, be received. 2. That the External Audit Progress Report, shown in Appendix 2, be received and noted. The Chair declared the motion CARRIED .
Word for word from the decision Derbyshire Dales published for this meeting.Source: democracy.derbyshiredales.gov.uk
1. That the “Draft Auditor’s Annual Report for the year ended 31 March 2025”, shown in Appendix 1, be received.
2. That the External Audit Progress Report, shown in Appendix 2, be received and noted.
List of Appendices
Appendix 1 Draft “Auditor’s Annual Report for the year ended 31 March 2025” from Forvis Mazars.
Appendix 2 “External Audit Progress Report for the year ended 31 March 2025: November 2025” from Forvis Mazars LLP
Background Papers None
Consideration of report by Council or other committees No Council Approval Required No
Exempt from Press or Public No External Auditor’s Progress Report and Draft Auditor’s Annual Report For The Financial Year Ended 31 March 2025
Background
1.1Members are requested to note the reports from the external auditor as part of the process for finalising and approving the Council’s Statement of Accounts for 2024/25. It is expected that Alastair Newall (Director of Forvis Mazars LLP) and Jennifer Norman (External Audit Manager from Forvis Mazars LLP) will attend the meeting to take members’ questions on the reports.
1.2As a result of the national audit backlog, the Accounts and Audit Regulations have been amended to extend the deadlines for local authorities to publish financial statements with an auditor’s certificate or opinion. The following deadlines now apply:
Financial year covered by Deadline for publication of statements: audited financial statements:
2024/25 27th February 2026
2025/26 31st January 2027
2026/27 30th November 2027
2027/28 30th November 2028
1.3The audited financial statements in respect of the financial year 2024/25 must be published by 27th February 2026.
2. Key Issues
2.1The Council’s external auditors, Forvis Mazars LLP, have issued their Draft Auditor’s Annual Report for the year ended 31 March 2025 covering the 2024/25 accounts. This version of the Auditor’s Annual Report is issued as “Draft” because the external auditor can only issue the final version of the Auditor’s Annual Report after the Audit Opinion on the financial statements has been signed. It was felt that it would be more expedient to bring the draft report to this committee meeting, rather than present the final version at the committee meeting when the audited financial statements will be presented (currently scheduled for January 2026).
2.2The Draft Auditor’s Annual Report summarises the work the external auditor has undertaken for the year ended 31 March 2025. A copy of the report is shown at Appendix 1; the external auditor has requested that it be brought to Members’ attention.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Governance & Resources Committee at Derbyshire Dales and we tell you when its next papers are published, before the meeting rather than after it.
Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of the meeting of the Governance and Resources Committee held on 2 July 2026 ...
Risk Management - Annual Report 25/26RESOLVED with 8 votes FOR 0 votes AGAINST 1 abstention That the annual report and risk management arrangements be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.