Derbyshire Dales District Council
Council, Thursday 29 January 2026 at 6.00pm

Procurement Update - Independent Person - Task and Finish Working Group - Gritstone Road Appeal Review

Approved Committee 2 papers

AI summaryDerbyshire Dales District Council approved an extra £5,000 for the Gritstone Road appeal review, taking the budget to £20,000, and cut the working group from six to five councillors.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedExtra £5,000 approved; working group reduced
Money£5,000 supplementary, total £20,000Financed from general reserve in 2025/26
What happens nextClarifications sought from two ChambersTask and Finish Working Group continues work
Who it affectsTask and Finish Group membershipMatlock East & Tansley and Matlock West replaced

What was decided

Council noted the procurement outcome and the steps taken to secure an independent person with appropriate expertise for the review. Report P1

Council approved a supplementary revenue budget of £5,000 for 2025/26, bringing the total to £20,000, financed from the general reserve.

Council reduced the Task and Finish Working Group from six to five councillors, replacing the Matlock East & Tansley and Matlock West ward members with one Liberal Democrat nominee. Report P3, 7.1, 7.2

Why

The original competitive procurement received only one bid, which failed the required criteria, due to supplier capacity, specification and location issues. Report 2.1, 2.2, 2.3, P12

A targeted approach was adopted: five legal Chambers were contacted directly for expressions of interest, and two submitted proposals now under review. Report 3.1, 5.1

The two Matlock ward councillors asked to appear as witnesses rather than group members to avoid a potential conflict of interest. Report 7.1

What happens next

The Working Group is awaiting clarifications from the two responding Chambers before selecting the independent person. Report 5.1

A further update will be given to Council once the clarifications are received and the appointment is made. Report 5.1

The money

  • £5,000 Supplementary revenue budget approved for 2025/26, bringing total to £20,000
  • £20,000 Total approved budget for the commission in 2025/26
  • £30,000 Estimated cost of the commission based on the two Chambers' proposals Report 6.2, 10.2
  • £15,000 Original budget approved by Council on 25 September 2025 Report 6.1
  • £2.45m Current balance of the general reserve Report 10.2

Options considered

  • Rejected: Do nothing. Would risk delay to the programme and undermine confidence in delivery Report 8.1
  • Rejected: Re-run the original market invitation. Feasible but likely to repeat capacity constraints and cause timetable slippage
  • Chosen: Targeted approach to five legal Chambers. Proportionate and necessary given the specialist nature and time-sensitive context Report 3.1, 11.2

Implications

  • Financial: Additional £5,000 drawn from the general reserve; risk assessed as low because the expenditure is non-recurring. Report 10.2, 10.3
  • Legal: Procurement followed Contract Standing Orders and is compliant with the Local Government Act 1972; UK GDPR obligations must be maintained. Report 11.1, 11.4
  • Risk: Failure to secure an appointment promptly could expose the Council to reputational risk and challenges to the review's effectiveness. Report 11.6, 14.1
  • Equalities: No direct equalities impacts are anticipated. Report 12.1
  • Climate: No perceived climate change impacts. Report 13.1
  • Other: The commission aligns with the Corporate Plan by strengthening governance, transparency and community engagement in planning. Report 9.1

Who and where

  • Members of the Task and Finish Working Group Report 7.2
  • Councillors for Matlock East & Tansley Ward and Matlock West Ward Report 7.1
  • The Liberal Democrat Group Report P3
  • Two legal Chambers that submitted proposals Report 3.1, 5.1

Timeline

  • 25th September 2025: Council established the Task and Finish Working Group and approved the original £15,000 budget. Report 1.1, 6.1
  • 14th November 2025: Formal procurement exercise initiated. Report 1.1
  • 12th December 2025: Deadline for expressions of interest from the five legal Chambers. Report 3.1
  • 7th January 2026: Task and Finish Working Group met to review the two Chambers' proposals. Report 5.1
  • 8th January 2026: Governance and Resources Committee meeting postponed due to adverse weather.
  • 22nd January 2026: Reconvened Governance and Resources Committee meeting.
  • 29th January 2026: Full Council considered and decided on the procurement update and budget.

Plain English for the jargon

  • Task and Finish Working Group: A short-term council group set up to review a specific matter and report back.
  • Rule 6 parties: Parties given rights to take part in a planning appeal under procedural rules.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item309/25

Resolved

RESOLVED 1. That Council notes the outcome of the procurement exercise and the steps taken to secure an independent person with appropriate expertise. 2. That Council approves a supplementary revenue budget of £5,000 (bringing the total to £20,000) for the financial year 2025/26 to be financed from the general reserve. 3. That, following representations from the relevant ward councillors, Council reduces the membership of the Task and Finish Working Group to 5 Councillors by replacing the two Councillors representing the wards of Matlock East and Tansley and Matlock West with one member nominated by the Liberal Democrat Group. Voting 28 For 01 Against 00 Abstained The Chair declared the motion CARRIED.
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Council

Recommendations

1. That Council notes the outcome of the procurement exercise and the steps taken to secure an independent person with appropriate expertise.

2. That Council approves a supplementary revenue budget of £15,000 (bringing the total to £30,000) for the financial year 2025/26 to be financed from the general reserve.

3. That, following representations from the relevant ward councillors, Council reduces the membership of the Task and Finish Working Group to 5 Councillors by replacing the two Councillors representing the wards of Matlock East and Tansley and Matlock West with one member nominated by the Liberal Democrat Group. List of Appendices Appendix 1 - Terms of Reference – Task and Finish Group

Background Papers Planning Appeal – Land at Gritstone Road, Matlock – Council 25th September 2025

Consideration of report by Council or other committee Not applicable

Council Approval Required No

Exempt from Press or Public No PROCUREMENT UPDATE – INDEPENDENT PERSON – TASK AND FINISH WORKING GROUP – GRITSTONE ROAD APPEAL REVIEW

Background

1.1To facilitate the work of the Task and Finish Working Group, established to review the Gritstone Road Planning Appeal by the Council at its meeting on 25th September 2025, it was necessary to appoint an impartial independent person with relevant knowledge and experience of the planning appeal process. In line with the Council’s Contract Standing Orders, a formal procurement exercise was prepared during October 2025 and initiated on the 14th November 2025. 2. Procurement Process

2.1A formal procurement exercise was undertaken in accordance with the Council’s Contract Standing Orders. Nine experienced suppliers comprising specialist experts in planning and appeal procedures, including four from a list submitted by the Planning Advisory Service on 13th November 2025, were invited to submit quotations for the commission.

2.2In response to this invitation, only one submission was received. Following evaluation, the submission did not meet the required criteria and was therefore deemed unsuccessful.

2.3Following the outcome, all invited suppliers were contacted to provide feedback on their reasons for not submitting a response. The feedback identified several factors:

• Capacity constraints: Some suppliers indicated they lacked the capacity to undertake additional work within the specified timeframe. • Specification alignment: Certain suppliers reported that they did not meet the specific requirements outlined in the brief. • Interest in commission: Others advised that they were not interested in this commission due to distance/location.

3. Next Steps

3.1Given the constraints mentioned in paragraph 2.3 above a targeted approach was adopted to ensure continuity of the project and avoid undue delay. Five legal Chambers with relevant planning law and appeals expertise were contacted directly and promptly invited to submit an Expression of Interest by 12th December 2025. This targeted approach was considered proportionate and necessary given the specialist nature of the work and the time-sensitive context.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement Update: Task and Finish Working Group: Terms of Reference /25Appendix 1 84 KB Download
PDF
Procurement Update: Independent Person: Task and Finish Working Group: Gritstone Road Appeal ReviewReport 112 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

29 of 41 attended
RS
Roger Shelley LIBDEMChair, present
LP
Lucy Peacock LABVice-Chair, present
DG
Dawn Greatorex LABCommittee Member, apologies
RA
Robert Archer LIBDEMCommittee Member, present
AB
Anthony Bates CONCommittee Member, present
JB
John Bointon CONCommittee Member, present
GB
Geoff Bond CONCommittee Member, present
MB
Matt Buckler GREENCommittee Member, present
SB
Sue Bull CONCommittee Member, present
MB
Martin Burfoot LIBDEMCommittee Member, present
SB
Sue Burfoot LIBDEMCommittee Member, present
DB
David Burton LIBDEMCommittee Member, present

All 41 on the meeting page

On this subject at Derbyshire Dales

Search all
  1. Procurement Update - Independent Person - Task and Finish Working Group - Gritstone Road Appeal ReviewThis decision
  2. Procurement update - independent person - task and finish working group - gritstone road appeal reviewApproved

More from Derbyshire Dales Council

All decisions
MeetingDecisionOutcome
23 Jul 2026 CommitteesRESOLVED (unanimously) That the non-exempt minutes of the listed in the Minute Book for the period 14 May 2026 to 02 ... Decided Open
23 Jul 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of a meeting of Council held on 28 May 2026 and 18 June 2026 be approved as a... Approved Open
23 Jul 2026 Provisional Capital Out-Turn 2025/26 and Revised Capital Programme 2026/27 to 2030/31RESOLVED (unanimously) 1. That the provisional Capital Out-Turn of £15,075,300 as detailed in Appendix 1 be approved.... Approved Open
23 Jul 2026 Provisional Revenue Outturn 2025/26RESOLVED (unanimously) That in accordance with Procedure Rule 13 the meeting continue until 9.00pm. The substantive m... Noted Open
22 Jul 2026 Questions (rule of procedure 15)Decision making on planning applications is informed by the Local Plan, but each application for planning permission ... Decided Open