RESOLVED (unanimously) That the proposed internal audit plan for 2026/27 be agreed. The Chair declared the motion CARRIED .
AI summaryDerbyshire Dales Governance and Resources Committee approved the 2026/27 internal audit plan with 377 operational days, covering financial systems, IT, corporate areas and contingency work.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED (unanimously) That the proposed internal audit plan for 2026/27 be agreed. The Chair declared the motion CARRIED .
1. That the proposed internal audit plan for 2026/27 be agreed.
List of Appendices
Appendix 1 Internal Audit Plans 2025/26 to 2027/28
None
Consideration of report by Council or other committee
No
Council Approval Required
No
Exempt from Press or Public
No INTERNAL AUDIT PLAN 2026/27
1.1` The Global Internal Audit Standards require that the Head of Internal Audit creates an internal audit plan that supports the achievement of the Council’s objectives. The plan should be based on the strategies, objectives and risks of the Council and the Head of Internal Audit’s understanding of the governance, risk management and control processes in place.
1.2The Global Internal Audit Standards require that the Governance and Resources Committee (highest level body charged with governance) approve the plan.
2 Key Issues
2.1The internal audit establishment consists of a full-time Senior Auditor and a full time Auditor (2 part-time auditors in post) with management support from the Head of the Internal Audit Consortium who is employed by Chesterfield Borough Council. The number of operational days available is calculated by taking the number of weekdays in the year and deducting days for annual leave, bank holidays, training, administration, team meetings etc.
2.2The Internal Audit Section is currently fully staffed so the number of operational days for 2026/27 has been calculated on this basis (377 operational days in total).
2.3It is anticipated that 2 audits from the 2025/26 plan will be rolled forward to 2026/27 (choice-based lettings and grant compliance). One audit that was on the reserve list for 2025/26 has been completed (taxi licensing).
2.6The plan has been prepared considering the following factors: -
• The Council’s objectives and priorities, • Local and national issues and risks, • The requirement to produce an annual internal audit opinion – adequate coverage of risk, governance and control arrangements, • Information technology governance, fraud risk, the effectiveness of the Council’s compliance with ethics programs and other high risk areas, • The Council’s Strategic and Operational Risk Registers, • The views of the Director of Resources and Corporate Leadership Team.
2.7A summary of the internal audit plan is shown below and in detail at Appendix 1: Internal Audit Plan 2026/27
Summary Planned Audit Days Main Financial Systems 104 Other Operational Audits 90 Computer / IT Related 15 Corporate / Cross Cutting 81 Special Investigations & Contingency 25 Provision of financial advice 25 Working on elections 2 Local Government Review 5 Management Service 30 Grand Total 377
3 Options Considered and Recommended Proposal
3.1The recommended proposal is to approve the internal audit plan shown at Appendix 1. Failure to approve a plan would result in a breach of Global Internal Audit Standards and would increase the risk that the Council’s objectives might not be achieved.
4.1The views of the Director of Resources and Corporate Leadership Team have been considered when developing this plan.
5 Timetable for Implementation
5.1If approved by the Committee, the Internal Audit Plan will be delivered during the financial year 2026/27.
6 Policy Implications
6.1Effective Internal Audit arrangements contribute to good governance and to the corporate priority of a “Financially sound, fair and responsive Council”. 6.2 Audit reviews help to ensure that the Council’s resources and priorities are focused on achieving the objectives within the corporate plan and that there are appropriate governance, risk and control arrangements in place.
7 Resource Implications (Finance, HR, Estates and IT)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
4a. Internal Audit 26.27 Plan Appendix 1 /25Appendix | 100 KB | Download |
PDF |
INTERNAL AUDIT PLAN 2026/27Report | 117 KB | DownloadRead as text |
Follow Governance & Resources Committee at Derbyshire Dales and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the minutes of the meeting of the Governance and Resources Committee held on 2 July 2026 ... | Approved | Open |
| 3 Sep 2026 | Proposed Transfer of Land for Affordable Housing - Land Off Yeld Close, BakewellRESOLVED with 5 votes FOR 2 votes AGAINST 2 abstentions 1. That the consent of the Secretary of State is sought to tr... | Agreed | Open |
| 3 Sep 2026 | External Audit Progress ReportRESOLVED (unanimously) That the shown in Appendix 1 be received and noted. The Chair declared the motion CARRIED . | Noted | Open |
| 3 Sep 2026 | Annual Report on the Regulation of Investigatory Powers Act (RIPA)RESOLVED (unanimously) 1. That the Annual Report on the Council’s use of the Regulation of Investigatory Powers Act (... | Approved | Open |
| 3 Sep 2026 | Risk Management - Annual Report 25/26RESOLVED with 8 votes FOR 0 votes AGAINST 1 abstention That the annual report and risk management arrangements be app... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.