Derbyshire Dales District Council
Ashbourne Reborn Programme Board, Thursday 3 September 2026 at 2.00pm

Ashbourne Reborn Programme Report (Derbyshire Dales District Council)

Approved Committee 3 papers

AI summaryAshbourne Reborn Programme Board notes completion of grant funded works, with a forecast £0.299m overspend on the highways scheme to be addressed by the two councils.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedOutputs and forecast outturn noted
Money£0.299m forecast overspendPlus or minus 10% on Highways and Public Realm
What happens nextFinal report later in 2026/27Once final cost information available
Who it affectsAshbourne town centreResidents, businesses and visitors

What was decided

The Board approved the report and its recommendations unanimously, noting the outputs achieved and the forecast outturn position as at 31/08/26. Report 2.1, 2.14

Members noted that practical completion has been issued for both main contracts and the formal opening of Ashbourne Reborn took place on 26 June 2026. Report 2.14, 2.23

A final report covering programme finances and outcomes is to be considered later in 2026/27 when final information is available. Report 8.3, 7.7

Why

The report covers progress on an approved scheme, summarising outputs delivered and forecast outturn expenditure following completion of grant funded works. Report 3.1, 2.1, P6

Monitoring is required under the updated MoU with MHCLG signed in March 2026, replacing the previous Levelling Up Fund agreement. Report 8.1

A positive Business Improvement District ballot was announced on 9 July 2026, providing revenue funds and local capacity to continue regeneration. Report 2.28

What happens next

Derbyshire County Council and Derbyshire Dales District Council are to meet in September to discuss the final budget position and finalise the approach to meeting cost overruns on the Highways and Public Realm scheme. Report 7.5, P118

The next monitoring report to MHCLG is expected at the end of October 26, with the remaining LRF grant funding profiled for expenditure in Q2 2026/27. Report 2.27, 7.2

Match funded works at the Methodist Church (community garden, bike store and Chapel House) are now forecast to complete in Q3 2026/27, with Chapel House by Christmas. Report 6.1, P68

The money

  • £15.9m Total Ashbourne Reborn programme value Report 1.1
  • £13,373,509 LUF funding allocation, Round Two Report 1.1
  • £9.05m Project A: Highways and Public Realm (DCC led) Report P2
  • £7m Project B: Link Community Hub (AMC led) Report P3
  • £0.299m Forecast overspend on Highways and Public Realm Report 2.19, P54
  • £0.466m DCC client owned project risk allowance Report 2.18
  • £25,000 Link Community Hub cost increase since June, met from AMC loan Report 2.20
  • £16.135m Programme total budget (forecast outturn) Report P54
  • £16.434m Programme forecast outturn (August 26) Report P54
  • £8.25 EMCCA grant forecast underspend (in £000s) Report P64

Options considered

  • Rejected: Not Applicable. The report covers progress on an approved scheme, so no options were considered. Report 3.1

Implications

  • Financial: Highways and Public Realm scheme forecast to overspend by £0.299m plus or minus 10%, with the approach to meeting the overrun to be agreed between the two councils. Report 2.19, 7.5
  • Legal: Updated MoU signed with MHCLG in March 2026 and GFA signed with EMCCA in March 2026; aggregate legal risk assessed as Low to Medium. Report 8.1, 8.4
  • Risk: Financial risk remains assessed as Medium pending final completion of works and additional costs on the Highways scheme. Report 7.8
  • Equalities: Equalities Impact Assessment completed and recommendations reflected in delivery; additional on-street disabled parking on Church Street still under consideration by the County Council. Report 11.1, 11.2
  • Climate: No additional climate change implications identified beyond the original assessment; local supply chains encouraged where compliant. Report 12.1
  • Staffing: Programme draws on DDDC Finance, Estates, Events, Clean and Green and Legal teams; demands will decrease as final information is prepared. Report 9.3

Who and where

  • Ashbourne town centre residents, businesses and visitors Report P11
  • Derbyshire Dales District Council as Accountable Body Report 1.2, 8.1
  • Derbyshire County Council as lead delivery partner for Project A Report P2, 1.2
  • Ashbourne Methodist Church as lead delivery partner for Project B Report P3
  • East Midlands Combined County Authority (EMCCA) as additional funder Report 2.10, 8.1
  • Pupils of St Oswald's Primary who placed a time capsule at Millennium Square

Timeline

  • 26 June 2026: Formal opening and celebration event for Ashbourne Reborn Report 2.23
  • 9 July 2026: Positive Business Improvement District ballot announced Report 2.28
  • 31/08/26: Cut-off date for outputs and forecast outturn figures Report 2.1, 2.14
  • Q3 2026/27: Revised programme completion profile (previously Q2) Report 6.1, P120
  • End of October 26: Next monitoring report due to MHCLG Report 2.27
  • End of October: Community garden and bike store completion forecast Report P68
  • Christmas: Chapel House visitor accommodation completion forecast Report P68
  • Later in 2026/27: Final report on programme finances and outcomes to Board Report 7.7, 8.3

Plain English for the jargon

  • LUF: Levelling Up Fund, the original UK Government funding source
  • LRF: Local Regeneration Fund, the successor programme to which LUF funding has transferred
  • DDDC: Derbyshire Dales District Council, the Accountable Body for the programme
  • DCC: Derbyshire County Council, lead delivery partner for Project A
  • AMC: Ashbourne Methodist Church, lead delivery partner for Project B
  • MHCLG: Ministry of Housing, Communities and Local Government, the funding department
  • EMCCA: East Midlands Combined County Authority, additional funder for Access Ashbourne works
  • MoU: Memorandum of Understanding with MHCLG, updated and signed in March 2026
  • GFA: Grant Funding Agreement, including one signed with EMCCA in March 2026
  • HVM: Hostile Vehicle Mitigation measures, including bollards introduced in the Market Place
  • BID: Business Improvement District, voted in by Ashbourne ballot on 9 July 2026
  • EIA: Equalities Impact Assessment, undertaken during scheme development
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15/26

Resolved

That the recommendations within the report be approved unanimously.
Word for word from the decision Derbyshire Dales published for this meeting. Source: democracy.derbyshiredales.gov.uk

Follow this further

Built from Derbyshire Dales's papers

What the report saysPro

Report to Ashbourne Reborn Programme Board

Background

1.1As set out in the papers of previous Programme Board meetings, Ashbourne Reborn is a £15.9m programme aimed at transforming Ashbourne town centre through significant improvements to highways and public realm and the development of the Link Community Hub. Originally with a budget of £15.22m, this has increased to over £16m through the agreement of additional partnership match funding. The programme is funded by the UK Government through a £13,373,509 funding allocation from the Levelling Up Fund, Round Two. Levelling Up Funding is now part of the Government’s Local Regeneration Fund (LRF). The programme comprised two projects:

Project A: Highways and Public Realm Improvements led by Derbyshire County Council - £9.05m

Project B: Link Community Hub led by Ashbourne Methodist Church - £7m

1.2Derbyshire Dales District Council (DDDC) is the Accountable Body for Ashbourne Reborn. Matters that could have a significant impact on the programme in terms of deliverables, timescales, cost, outputs / outcomes and risk, potentially resulting in a change to the approved bid / Memorandum of Understanding between the District Council and MHCLG should be matters for consideration by the strategic Programme Board. Such matters are required to be escalated by Project Boards.

1.3Should these matters be considered material in relation to commitments to MHCLG, under agreed programme governance arrangements, this must be approved by Derbyshire Dales District Council’s Community and Environment (C&E) Committee prior to submission as this would constitute a formal request to change the terms of the agreement between Derbyshire Dales District Council as the Accountable Body for Ashbourne Reborn and MHCLG.

2. Key Issues

A) PROGRAMME OUTPUTS, FINANCES & ACHIEVEMENTS:

2.1This report focuses on the outputs delivered and forecast outturn expenditure position as at 31/08/26 for the Ashbourne Reborn programme. Further detail regarding programme finances is included in section 7 of this report, including updates to partner funding contributions.

2.2As a reminder, the aims of the LUF bid for Ashbourne town centre were:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Before and After Images /26Appendix 1 4.4 MB Download
PDF
Ashbourne Reborn Communications and Engagement Activity /26Appendix 2 128 KB Download
PDF
Ashbourne Reborn Programme Report (Derbyshire Dales District Council)Report 1.7 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
DH
David Hughes LIBDEMChair, present
SB
Sue BridgettAppointed Member, present
PD
Peter Dobbs LIBDEMAppointed Member, present
SF
Steve Flitter LIBDEMAppointed Member, present
SL
Stuart Lees CONAppointed Member, present
TW
Tony WalkerAppointed Member, present
JW
John WhitbyAppointed Member, absent
AW
Anne WrightAppointed Member, present
NA
Nick AdamsAppointed Member, apologies
SB
Steve BullAppointed Member, apologies
SM
Sue MooreAppointed Member, present

On this subject at Derbyshire Dales

Search all
  1. Ashbourne Reborn Programme Report (Derbyshire Dales District Council)This decision
  2. Ashbourne Reborn Programme Report (Derbyshire Dales District Council) Including Updated Programme Board Terms of ReferenceAgreed
  3. Ashbourne Reborn Programme Report (Derbyshire Dales District Council)Agreed
  4. Ashbourne Reborn Update and Proposed Support Measures ContinuedNoted
  5. Ashbourne Reborn Programme UpdateNoted
  6. Ashbourne Reborn Programme UpdateAgreed

More from Derbyshire Dales Ashbourne Reborn Programme Board

All decisions
MeetingDecisionOutcome
3 Sep 2026 Approval of Minutes of Previous MeetingRESOLVED That the minutes of the meeting of the Ashbourne Reborn Programme Board held on 18 06 2026 be approved as a ... Approved Open
18 Jun 2026 Approval of Minutes of Previous MeetingRESOLVED That the minutes of the meeting of the Ashbourne Reborn Programme Board held on 26 02 2026 be approved as a ... Approved Open
26 Feb 2026 Approval of Minutes of Previous MeetingRESOLVED (unanimously) That the Non-Exempt and Exempt minutes of the meeting of the 11 December 2025 be approved as a... Approved Open
11 Dec 2025 Approval of Minutes of Previous MeetingRESOLVED That the minutes of the meeting of the Ashbourne Reborn Programme Board held on 16 October 2025 be approved ... Approved Open
11 Dec 2025 Ashbourne Reborn Programme Report (Derbyshire Dales District Council) Including Updated Programme Board Terms of ReferenceRESOLVED (unanimously) 1. That the amended Programme Board Terms of Reference are received and agreed. 2. That the Bo... Agreed Open