RESOLVED to: 1) Approve to commence the commissioning work for the Bus Service Improvement Plan (BSIP) Programme, in terms of preparing tender specifications, terms of reference, and publishing tender contracts to procure relevant goods and services, using existing Frameworks and the Council’s tendering processes; and 2) Grant the Executive Director – Place, in consultation with the Cabinet Member – Highways, Assets and Transport, delegated powers to agree the award of BSIP contracts via existing internal and external Frameworks or by other relevant tender processes in line with the Council’s Financial Regulations, to the most cost effective and competent organisations or individuals.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Approval to Procure Goods and Services to Enable the Delivery of the Bus Service Improvement Plan (BSIP) (Cabinet Member for Highways, Assets and Transport)
1. Divisions Affected
1.1County-wide.
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To seek Cabinet approval to commence the commissioning work for the Bus Service Improvement Plan (BSIP) Programme, in terms of preparing tender specifications, terms of reference, and publishing tender contracts to procure relevant goods and services, using existing Frameworks and the Council’s tendering processes. This preparatory work is required to enable the BSIP work to begin immediately once funding is confirmed by the Department for Transport (DfT).
3.2To grant the Executive Director – Place, in consultation with the Cabinet Member – Highways, Assets and Transport, delegated powers to agree the award of BSIP contracts via existing internal and external Frameworks or by other relevant tender processes in line with the Council’s Financial Regulations, to the most cost effective and competent organisations or individuals.
4. Information and Analysis
4.1On 28 July 2022, Cabinet agreed to delegate the acceptance of the final BSIP award from the DfT to the Executive Director – Place and the Cabinet Member - Highways, Assets and Transport (Minute No. 142/22 refers). The exact level of grant funding is still not known. Although an indicative award of £47m was announced on 4 April 2022, the Council has yet to receive confirmation of the final settlement.
4.2The DfT has confirmed that the funding period will run from 2022-23 for three years, rather than the previously expected five years. Due to the delays in the allocation the first year of delivery will only be a part year, i.e. less than six months, with an anticipated start date of October 2022.
4.3The programme of BSIP work incorporates a wide range of ambitious projects ranging from the application of bus priority measures for late running buses at all traffic signalled junctions in Derbyshire, renewal of branding and marketing, through to fare support for young people and for other specific groups, such as jobseekers. The BSIP also includes for an important project to introduce Transport Hubs to a wide range of locations to improve connectivity and accessibility for residents, businesses, and visitors to Derbyshire.
4.4The Council, using some DfT preparatory funding, has established a small BSIP Delivery Team. That team, reporting through normal Council governance channels, as well as to the Enhanced Partnership Board, is preparing tender specifications and terms of reference for the delivery of the various multidisciplinary work packages. This preparation work is deemed to be critical as:
• The DfT will require work to commence quickly when the funding is confirmed. As there is a significant lead time to some work packages, preparatory work such as tender specifications and publication is necessary to avoid time loss associated with mobilisation. • There is an acute national shortage of competent and experienced specialist labour resources to deliver the majority of the work required in BSIP. This will be greatly compounded when BSIP funding is announced nationally, as approximately 25 Local Transport Authorities (LTAs) are likely to be competing to secure the best and most skilled specialist staff. Seeking tenders at this time in anticipation of the funding award, will provide the maximum chance of engaging the best resources at the most cost-efficient rates.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.