RESOLVED to: 1) Note the progress made on implementing the Low Emissions Vehicles Infrastructure Strategy as set in paragraph 4.7 of the report; 2) Approve the launch of an online community engagement exercise to create a robust evidence base and more clearly define where resident, business and visitor demand for public charge points exist; 3) Approve the proposed strategic approach to creating and delivering a comprehensive network of electric vehicle charge points across the County as set out in the report; 4) Delegate to the Executive Director of Place, in association with the Cabinet Member for Infrastructure and Environment, the authority to amend or modify the strategic approach to charge point delivery as required, if it remains consistent with the Council’s approved Low Emissions Vehicles Infrastructure implementation; 5) Approve the framework procurement approach that utilises Oxford City Council Dynamic Purchasing System (DPS) framework, as set out in 4.21 of the report; 6) Note that further monitoring and evaluation reports will be submitted for member consideration for this stage of work prior to commencing the next phase of the Low Emissions Vehicles Infrastructure implementation; and 7) Note that the Council will explore opportunities and submit bids where applicable for further grant funding through the Office for Zero Emission Vehicle and Low Emissions Vehicles Infrastructure fund.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Low Emission Vehicle Infrastructure Programme Update and Forward Programme of Activity (Cabinet Member for Infrastructure and Environment)
1. Divisions Affected
1.1County-wide.
2. Key Decision
2.1This is a key decision because it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To provide an update on progress in delivering the Council’s Low Emission Vehicle Strategy and seek approval of further proposals to deliver a comprehensive network of public charge points, including approval to launch a community engagement exercise, approval of the strategic approach to chargepoint delivery and approval of the proposed procurement approach. This report also notes the Council will explore future funding opportunities and that monitoring, and evaluations reports will be submitted for member consultation at key stages in this process. 4. Information and Analysis
Background 4.1 Derbyshire County Council recognises that demand for low emission vehicles is growing as the conscience around the need to support low carbon travel deepens and benefits in relation to air quality and public health become increasingly evident. To respond to this growing demand a Low Emission Vehicle Infrastructure (LEVI) Strategy and Action Plan was developed in 2019. The primary policy action ZEVI 1: Derbyshire County Council will work with partners on the provision and delivery of zero emission vehicle infrastructure across the county’’ sets out the Council’s plans as to how it intends to support the development of a growing public charging network that will provide confidence to residents and visitors to transition and use low emission vehicles in Derbyshire.
4.2Providing this infrastructure is also an essential part of the Council’s low carbon mobility ambitions and an integral part of the Council’s wider priority to reduce harmful carbon emissions, as confirmed in the Climate Change Strategy.
4.3Following adoption of the LEVI Strategy and Action Plan in 2019, a report was commissioned to provide an evidence base for the identification of strategic locations for electric vehicle (EV) charge point installation in Derbyshire. The analysis focused both on the County as a whole and on the individual local authorities of Amber Valley, Bolsover, Chesterfield, Derbyshire Dales, Erewash, High Peak, North East Derbyshire and South Derbyshire.
4.4The outputs from the report (Derbyshire Electric Vehicle Study, June 2022) provided recommendations on the steps needed to be taken by the Council to establish a base charging network in the immediate term, whilst also creating the investment framework to ensure that charging infrastructure is rolled out with flexibility and at the required pace to meet local demand.
4.5There are three main types of public charge point available providing for a variety of different uses: Charge point type Purpose Residential charging Typically focused on those homes that do (long stay charging) not have off street parking. Developing a residential, low power, overnight charging network is essential to provide confidence to those wanting to make the switch to electric vehicles. Destination charging Generally located in public car parks. – (medium to long Building on sites identified as part of the stay) Derbyshire EV Strategy report, the Council will develop a network of destination charging sites that provide charging options for visitors, tourists, and shoppers. In-Transit charging - In order to facilitate longer journeys, and to Rapid (<2hours) ensure commercial fleets and high mileage drivers can operate on electric, a network of Rapid and Ultra Rapid charge points will need to be developed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.