Audit Planning Update 2022/23 Purpose of this report Our planning work for the 2022/23 audit year is in progress. We are liaising with the finance team and completing our normal procedures plus the enhanced procedures required this year by ISA315 (revised). This work will continue through March and April and we expect to present our final Audit Strategy Memorandum to the Audit Committee at its June 2023 meeting. This report provides the Audit Committee’s March 2023 meeting with an update on the conclusions and any significant matters arising to date from the 2022/23 audit planning. Scope of the Audit and our responsibilities The scope of our audit is unchanged engagement and is set out in the Statement of Responsibilities of Auditors and Audited Bodies, issued by Public Sector Audit Appointments Ltd (PSAA) available from the PSAA website: https://www.psaa.co.uk/managing-audit-quality/statement-of-responsibilities-of-auditors-and-audited-bodies/. Our responsibilities continue to be are principally derived from the Local Audit and Accountability Act 2014 and the Code of Audit Practice issued by the National Audit Office (NAO), as outlined below. • Audit Opinion – giving an opinion on the 2022/23 Financial Statements • Value for Money - forming a view on the arrangements that the Council has in place to secure economy, efficiency and effectiveness in its use of resources • Electors’ rights - The 2014 Act requires us to give an elector, or any representative of the elector, the opportunity to question us about the accounting records of the Council and consider any objection made to the accounts. We also have a broad range of reporting responsibilities and powers that are unique to the audit of local authorities in the United Kingdom • Reporting to the NAO - We report to the NAO on the consistency of the Council’s financial statements and the matters arising from our audit which are relevant to the Council’s Whole of Government Accounts (WGA) submission Audit Engagement Team Your audit engagement team continues to be lead by Mark Surridge (Director and Key Audit Partner) and Mike Norman (Senior Manager). The Vikash Patel is taking over from Bethan Frudd as Assistant Manager on the audit and they are liaising with the finance team regarding any continuing audit issues.
Audit scope and responsibilities, Audit Engagement Team Audit Approach and Timelines Audit Reporting and Significant Audit Risks Materiality, Value for Money and non-Audit Work
2 Audit Approach and timelline Our audit approach is risk based; primarily driven by the risks we consider to result in a higher risk of material misstatement of the financial statements. The diagram below outlines the procedures we perform at the different stages of the audit and the indicative timeline at this stage based on the current national timetable. We will agree the specific timetable with the finance team and provide more details in our final Audit Strategy Memorandum. There are no significant matters arising from the Planning and Interim visits to date to bring to the Committee’s attention. We will present the agreed Audit Strategy Memorandum to a future meeting of the Committee. The completion of the 2021/22 audit was significantly delayed due to the late clarification by CIPFA and DLUHC of the national Infrastructure accounting issue which was reported in our 2021/22 Audit Completion Report. No change to these requirements is expected for 2022/23 so one of the objectives for this year is to complete the audit in line with the national timetable. We will keep the Committee informed as the audit progresses.
Audit scope and responsibilities, Audit Engagement Team Audit Approach and Timelines Audit Reporting and Significant Audit Risks Materiality, Value for Money and non-Audit Work
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Audit Planning Update 2022/23Report | 428 KB | DownloadRead as text |
Follow Audit Committee at Derbyshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Place Department Risk ManagementIt was agreed that the Chairman take a request to Cabinet to open the project to scrutiny by the Committee bearing in... | Agreed | Open |
| 14 Jul 2026 | Performance Monitoring and Budget Monitoring Outturn 2025-26 as at Quarter 4 (31 March 2026)RESOLVED that the Committee notes: a) The Council Plan performance and Revenue outturn position for 2025-26; b) The c... | Decided | Open |
| 14 Jul 2026 | Internal Audit Charter UpdateRESOLVED that the Committee approve the Council’s Internal Audit Charter. | Approved | Open |
| 14 Jul 2026 | Counter Fraud Strategy UpdateRESOLVED to approve the Counter Fraud Strategy 2026-27 as appended at Appendix 2 to the report. | Approved | Open |
| 14 Jul 2026 | National Fraud Initiative UpdateRESOLVED that the Committee note the outcomes to date of the Council’s participation in the NFI 2024-25 exercise and ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.