Cabinet, Thursday 11 January 2024 at 2.00pm

County Hall Options Appraisal - Outline Business Case for the Future of CCHQ

Noted Executive 6 papers

Cabinet noted this item on Thursday 11 January 2024. Below is the council's own wording, with the papers it was decided on.

Item9/24

Resolved

RESOLVED to: 1) Receive and note the findings of the Outline Business Case for the future of County Hall; 2) Approve the recommended option, in which the Council moves to a smaller new headquarters on the Matlock Campus site and that the main County Hall campus is redeveloped to deliver a mixed use; 3) Approve taking the recommended Option 3 forward to the more detailed business case stage and due diligence; 4) Support the inclusion of £0.375m in the Capital Programme for 2024/25 to fund the development of the full detailed business case and request approval for the funding of this next stage of work in the sum of £0.375m, subject to approval of the 2024/25 Capital Programme by Full Council in February 2024; and 5) Approve the delegation to the Director of Property in consultation with the Director of Legal and Democratic Services the power to procure and appoint such consultants as may be required for due diligence and development of the Option 3 detailed business case including where appropriate the extension or variation of existing contracts within the funding envelope of £0.375m (Subject to this amount being approved by Full Council in February 2024 as part of the 2024/25 Capital programme).
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

County Hall Outline Business Case

November 2023

County Hall, Matlock: Outline Business Case November 2023 Contents Executive summary 3 Annex A: Specialist reports 154

Strategic case 27 HLM Architects - Design and Masterplanning HLM Sustainability - Sustainability Economic case 55 Montagu Evans – Planning Strategy Mott Macdonald – Transport Review Financial case 117 Baker Hicks – Building Services Ekos – Economic Impact Assessment Commercial case 129 Soft Market Test Prospectus

Management case 138 Annex B: Project management arrangements 156 Key conclusions and recommendations 149

2 County Hall, Matlock: Outline Business Case November 2023 Executive summary The project and Outline Business Case (OBC)

The project The OBC will

• Derbyshire County Council (the Council) has • Review and update the relevant strategic context for the commissioned HLM Architects, with support from project outlined in the Strategic Outline Business Case (SOBC) realestateworks Ltd and a wider consultancy team, to • Confirm a clear and evidence-based case for change prepare an OBC for County Hall in Matlock • Draw on the findings and conclusions from specialist • The project aims to identify a financially sustainable consultants – legal, transport, building and operating costs, workplace for the Council’s headquarters functions while mechanical and electrical systems, economic impact, property also ensuring the long-term preservation and market, sustainability and design enhancement of County Hall through its transformation • Evaluate in detail the short list of options from the SOBC • The Council recognises the economic impact of its presence within Matlock and is committed to maintaining • Consider affordability and the funding options available its support for the locality through the outcomes of the • Assess economic impact of options project • Identify a preferred option • Set out the commercial and management arrangements to deliver the project • Confirm the next steps 4 County Hall, Matlock: Outline Business Case November 2023 The County Hall project objectives – a reminder

The purpose of the project is to:

• Identify a long-term financially sustainable future for the Council’s headquarters operations

• Capitalise on the hidden value of the County Hall complex by attracting private sector investment

• Provide a more efficient and flexible workplace

• Deliver a significant economic impact to Matlock and the surrounding area

• Enable the Council’s strategic priorities and objectives to be better supported

5 County Hall, Matlock: Outline Business Case November 2023 What the SOBC said

The overarching conclusion and recommendations:

• Remaining on site in County Hall is not financially sustainable

• County Hall should be transformed into a mixed-use destination centred on a hotel

• Maximum economic impact to the area would be achieved if the Council remained on site

• Four options out of 12 to be taken forward for further analysis • Do Minimum – remain in existing buildings • Relocate from Matlock • Remain in new office on site • A hybrid of 2 and 3

6 County Hall, Matlock: Outline Business Case November 2023 Action taken to inform the OBC

The OBC and its conclusions were informed by:

• Talking to users to understand current and future use of space

• Reviewing what other councils are doing

• Engaging with the market via a soft market testing exercise

• Preliminary meetings with District Council planners and heritage specialists

• Working with a team of specialist sub-consultants

• Updating all financial and economic impact assumptions

• Refreshing the masterplan

7 County Hall, Matlock: Outline Business Case November 2023 The case for change

Problems to solve:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
231115 OBC redacted 24 /24Report 19 MB DownloadRead as text
PDF
County Hall Options Appraisal: Outline Business Case for the Future of CCHQReport 289 KB Download
PDF
Enclosure 1 /24Report 106 KB Download
PDF
Enclosure 4 /24Report 8.5 MB Download
PDF
Enclosure 5 /24Report 515 KB Download
PDF
Enclosure 6 /24Report 3 MB Download

At this meeting

Whole meeting

Who was there

9 of 20 attended
BL
Councillor Barry LewisChairman, present
SS
Councillor Simon SpencerVice-Chairman, present
CC
Councillor Charlotte CupitCommittee Member, present
AD
Councillor Alex DaleCommittee Member, present
CH
Councillor Carol HartCommittee Member, present
NH
Councillor Natalie HoyCommittee Member, apologies
TK
Councillor Tony KingCommittee Member, present
JP
Councillor Julie PattenCommittee Member, present
CR
Councillor Carolyn RenwickCommittee Member, present
EA
Emma AlexanderOfficer, in attendance
HB
Helen BarringtonOfficer, in attendance
CC
Carol CammissOfficer, in attendance

All 20 on the meeting page

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open
10 Sep 2026 Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies