High Needs Block Funding Settlement 2024-25

Noted Executive 1 paper

Cabinet noted this item on Thursday 14 March 2024. Below is the council's own wording, with the papers it was decided on.

Item55/24

Resolved

RESOLVED to: 1) Note the high needs settlement for 2024-25; 2) Approve the places commissioned in Appendix 3 to the report; 3) Approve the increases to special school, support centre and Enhanced Resource Element 3 profiles in top ups as set out in section 4.2 and Appendix 4 to the report; 4) Approve the central high needs budgets in Appendix 5 to the report; and 5) Agree to accept the Forum’s request to de-delegate funds for the functions listed in section 4.6 of the report.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Cabinet

FOR PUBLICATION

DERBYSHIRE COUNTY COUNCIL

CABINET

Thursday, 14 March 2024

Report of the Director - Finance and ICT, Executive Director - Children's Services

High Needs Block Funding Settlement 2024-25 (Cabinet Member for Education)

1. Divisions Affected

1.1County-wide

2. Key Decision

2.1This is a key decision because it is likely to

a) result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000); and

b) It is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.

3. Purpose

3.1To inform Cabinet of the High Needs Block settlement of the Dedicated Schools Grant (DSG) and to seek approval to its allocation for 2024-25.

4. Information and Analysis

4.1The High Needs Block settlement for 2024-25 was published on 19th December 2023, summary details are set out in Appendix 2. Derbyshire’s allocation is set to increase by £5.783m next year, equivalent to 5.2% of the 2023-24 figure, giving a 2024-25 allocation of £117.009m. Proposals set out in this report will allocate this in full and require further delivery of savings of £3.708m.

Derbyshire’s current financial year expenditure on the High Needs Block is estimated to be significantly higher than the current year grant, with the latest budget monitoring estimates showing an overspend of £11.476m in 2023-24. A significant factor in this overspend is the increase in the number of Education, Health and Care Plans (EHCPs) which stood at 6,429 at the time of the latest budget monitoring and represents a 26% increase from the level when the 2023- 24 budgets were originally set. Further increases in EHCP’s are anticipated in 2024-25.

Derbyshire carried forward an accumulated Dedicated School Grant (DSG) deficit at 1 April 2023 of £4.775m and this is expected to rise to £15.499m by the end of the 2023-24 financial year due to pressures from the High Needs Block. The DSG statutory override rule, which reduces the overall financial risks of the deficit falling on the council’s unearmarked general fund reserves, will end on 31st March 2026 and is not expected to be extended. Local Authorities must therefore take steps to ensure relevant spending is kept within the grant available and that plans are in place to recover existing DSG deficits.

The DfE have previously signalled that future increases in high needs funding will be much lower than received for 2022-23 and 2023-24. As a result, future year increases are unlikely to have sufficient headroom to meet the expected continued growth in demand or make a significant contribution to our accumulated DSG deficit. It is therefore essential that the allocations for next year are affordable and provide sufficient scope to contain demographic pressures within the grant.

4.2Proposed allocations - Places

Following the annual commissioning process, the Authority has now agreed the number of places required in special schools, Enhanced Resource (ER) schools, Alternative Provision (AP) centres and Further Education (FE) Colleges for 2024- 25. The planned cost is £18.436m which is a £1.736m (10.4%) increase on the 2023-24 base (£16.700m). An analysis of the current and provisional places for 2024-25 is provided at Appendix 3. The main increase is in respect of AP support centres and special schools and academies.

4.3Proposed allocations – Top up funding (also known as Element 3)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
High Needs Block Funding Settlement 2024-25Report 256 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 18 attended
BL
Councillor Barry LewisChairman, present
SS
Councillor Simon SpencerVice-Chairman, present
CC
Councillor Charlotte CupitCommittee Member, present
AD
Councillor Alex DaleCommittee Member, present
CH
Councillor Carol HartCommittee Member, apologies
NH
Councillor Natalie HoyCommittee Member, present
TK
Councillor Tony KingCommittee Member, present
JP
Councillor Julie PattenCommittee Member, present
CR
Councillor Carolyn RenwickCommittee Member, present
EA
Emma AlexanderOfficer, in attendance
MK
Mark KenyonOfficer, in attendance
JO
Joe O'SullivanOfficer, in attendance

All 18 on the meeting page

On this subject at Derbyshire

Search all
  1. High Needs Block Funding Settlement 2024-25This decision
  2. Allocation of Funding from the Children's Services School Condition Allocation and High Needs Provision Capital AllocationNoted
  3. High Needs Block Funding Settlement 2026-27Noted
  4. Children's Services SEND Capital Budget (High Needs Provision Capital) AllocationsApproved
  5. Children's Services SEND Capital Budget (High Needs Provision Capital) AllocationsApproved
  6. Children's Services SEND Capital Budget (High Needs Provision Capital) AllocationsApproved

More from Derbyshire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Outcome of Rapid Options Assessment into Future Use of The Derby and Derbyshire Waste Treatment Centre (DDWTC)1) To note the content of the report and its appendices including the financial implications of the recommendations; ... Noted Open
10 Sep 2026 To approve, as a correct record, the non-exempt minutes of the meeting held on 30 July 2026To approve, as a correct record, the minutes of the above meeting. Approved Open
10 Sep 2026 Delivery of Quarter One of the 2026-27 Highways Capital ProgrammeRESOLVED to: 1) Note the £17.500m delivery of the annual Highways Capital Programme in Quarter 1 of 2026-27; and 2) N... Noted Open
10 Sep 2026 Derbyshire Employment and Skills Strategy 2026-2030RESOLVED to: a) Approve the formal adoption of the Derbyshire Employment and Skills Strategy 2026-30; b) Support the ... Approved Open
10 Sep 2026 Collaboration Agreement between Derbyshire County Council and Elvaston Castle and Gardens TrustRESOLVED to: 1) Approve the Council entering into the proposed Collaboration Agreement with Elvaston Castle and Garde... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies