CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Derbyshire County Council

Decarbonising the Estate - Asset Disposal and Renewable Energy

Noted Scrutiny 1 paper

Improvement and Scrutiny Committee - Climate Change, Biodiversity and Carbon Reduction noted this item on Monday 1 July 2024. Below is the council's own wording, with the papers it was decided on.

Item21/24

Resolved

RESOLVED to note progress on the plans to decarbonise the Council’s estate since the previous report to committee in February 2024, and the current proposals for renewable energy generation.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Improvement and Scrutiny Committee - Climate Change, Biodiversity and Carbon Reduction

Executive summary

New data for 2023-24 indicates a further 6 million kWh reduction in energy use associated with corporate buildings in 2023-24.

Energy use has been further reduced as shown below:

year kWh tonnesC02e 2020-2021 45,169,293 9,171 2021-2022 44,963,103 8,861 2022-2023 38,860,609 7,475 2023-2024 32,820,000* 6,564* (*Final figures will be confirmed in August 2024).

Property rationalisation has delivered 75-80% of the savings achieved. The potential saving from further property rationalisation has been assessed and informs the projections for future energy use by 2032. Proposed capital projects for the installation of photo-voltaic (p.v.) panels on corporate buildings have been paused due to funding issues, so an alternative means of provision has been identified, and is progressed to approval to procure. This option - for p.v. installation by an energy provider subject to a power purchase agreement - requires no capital investment up front.

2.2Decarbonisation Progress 2020-2024.

In February 2024 the council was able to report:

• “Between 2020-21 and 2022-23 the energy use associated with the corporate estate was reduced by 14% or 6.1 million kWh (from 45 million kWh to 38.9 million kWh). • Carbon emissions were reduced by 18% or 1700 tonnes CO2e since 2021. (From 9171 to 7475 tonnes CO2e). • 5.1million kWh (80%) of this reduction has been achieved by property rationalisation. • 1 million (20%) is due to other measures including energy management, and other energy efficiency projects”.

2.3Energy Use Data 2023-24

The latest energy use data for 2023-24 shows a further reduction of energy consumption for corporate buildings, with a further 6 million kWh saving.

The total energy use for 2023-2024 is 32.8 million kWh. (Subject to final confirmation in August 2024)

year Energy use Carbon Fossil fuel Elec % kWh emissio ns 2022-2023 38,860,609 7,475 28,114,193 10,715,773 72% 2023-2024* 32,820,000* 6,564* 23,370,000 9,450,000 71%

It is estimated that 4.5million kWh (75%) of this reduction is as result of property rationalisation.1.5 million (25%) is due to other measures including energy management, and energy efficiency projects.

In February 2024 the council predicted a minimum 3.5 million kWh of further savings from property rationalisation, to be achieved in 2024. The higher figure of 4.5 million kWh saving may be due to the pace of property rationalisation.

Summary: • Total 12.1million kWh of energy savings since 2021-22. • 9.6million kWh has been saved by property rationalisation. • 2.5million kWh by other means. There is a small shift away from fossil fuels, but progress is limited by lack of available project funding to remove gas and oil fuelled heating systems in favour of cleaner renewable alternatives.

2.4Scope for further reductions in energy consumption arising from property rationalisation.

In February 2024 a comprehensive review was undertaken of the anticipated future commitment to assets across the estate (excluding schools).

o 40% of assets are in scope to be retained. o 20% of assets are under review. o 40% of assets are in scope for potential disposal.

This is an estimate which anticipates the potential outcome of future reviews. The estimated maximum energy saving associated with assets in scope for disposal is currently 17.5 million kWh.

This is an additional 13 million kWh over the 4.5million kWh saving just achieved.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Decarbonising the Estate: Asset Disposal and Renewable EnergyReport 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 13 attended
WM
Councillor Wayne MajorChairman, present
GH
Councillor Garry HicktonVice-Chairman, apologies
BB
Councillor Barry BinghamCommittee Member, present
JB
Councillor Joel BryanCommittee Member, apologies
SB
Councillor Steve BullCommittee Member, present
DC
Councillor Dean CollinsCommittee Member, present
MF
Councillor Martyn FordCommittee Member, present
AG
Councillor Aaron GibsonCommittee Member, apologies
AH
Councillor Anne-Frances HayesCommittee Member, apologies
DT
Councillor David TaylorCommittee Member, present
DB
David BeardOfficer, in attendance
JN
Juliette NormingtonClerk, in attendance

All 13 on the meeting page

More from Derbyshire Improvement and Scrutiny Committee - Climate Change, Biodiversity and Carbon Reduction

All decisions
MeetingDecisionOutcome
3 Feb 2025 Minutes of Previous MeetingRESOLVED – to confirm the non-exempt minutes of the meeting of the Improvement and Scrutiny – Climate Change, Biodive... Decided Open
3 Feb 2025 Supporting Community Climate Change InitiativesRESOLVED to note the update on the Council’s work to support climate change projects and initiatives of Derbyshire’s ... Noted Open
3 Feb 2025 Derbyshire’s Heartwood Community ForestRESOLVED to note the work the Council was conducting in respect to Derbyshire’s Heartwood Community Forest. Noted Open
3 Feb 2025 Bus Service Improvement Plan UpdateRESOLVED to: 1) note the work undertaken to implement the various elements in the Bus Service Improvement Plan over t... Noted Open
3 Feb 2025 Work ProgrammeRESOLVED to note the work programme for April 2025. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies