RESOLVED that the Committee, subject to the approval of Cabinet of these recommendations on 5 December 2024: a) Notes the timetable for completion of the 2025-26 budget, including arrangements for consultation with stakeholders and the carrying out of an assessment of the need for a full equality impact assessment on budget saving proposals; b) Notes the commencement of annual pre-budget engagement activities including the Your Council, Your Voice Survey; c) Notes the proposals for reviewing and updating the Five Year Financial Plan; and d) Notes the arrangements for reviewing Earmarked Reserves and updating the General Reserve projections.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
1.1To provide Members with an update on the proposed timetable for the Council’s 2025-26 budget preparation and procedures and the associated consultation arrangements and pre-budget engagement activities. The recommendations in this report are subject to approval by Cabinet on 5 December 2024.
2. Information and Analysis
Preparation of Budget 2025-26
2.1The production of the Council’s budget is undertaken in accordance with the requirements of the Council’s Constitution. The Constitution requires that a timetable is publicised by Cabinet for making proposals to the full Council in relation to the annual Revenue Budget, along with arrangements for consultation with stakeholders, which should be for a period of not less than six weeks. The proposed timetable is attached at Appendix 2. Public
2.2A key element of the Council’s budget setting process is consultation with stakeholders.
2.3It is proposed to undertake the following engagement and consultation activities:
Pre-Budget Engagement
• The annual “Your Council, Your Voice Survey” launched in the week commencing 11 November 2024. A representative sample of residents are being asked how much they support a range of broad options to save money or generate extra revenue. Respondents also have the opportunity to make suggestions on other possible saving or revenue generating proposals in order that they can inform the proposed budget. • A sampling framework was used to target a representative and proportionate number of households across Derbyshire’s districts and boroughs. • It is anticipated that the Your Council, Your Voice Survey fieldwork will be for a period of six weeks, with interim results provided before the end of December 2024.
Budget Consultation
• Specific budget proposals will be considered by Cabinet in January 2025 and may require separate and targeted consultation, depending on the nature of the proposal. The scope of consultation activity for individual proposals will be determined if supported in principle by Cabinet. Any required consultation on specific proposals will be carried out, where required, ahead of any decisions being made on implementation, where required, in 2025-26.
• The methodology of consultation for individual proposals will be tailored depending on the nature of the proposals, including direct communication to service users where required.
• Statutory consultation with business ratepayers, corresponding with representatives of the East Midlands Chamber of Commerce, the Confederation of British Industry (CBI) East Midlands and the Nottinghamshire and Derbyshire Federation of Small Businesses (FSB) on the Council’s budget proposals.
• Consultation with the trade unions at a Corporate Joint Committee. Public
• Consultation with the Council’s Resources Improvement and Scrutiny Committee.
2.4As a result of this combined approach (pre-budget engagement through the Your Council, Your Voice Survey and specific and targeted consultation), the Council will have a blend of both quantitative and qualitative information available, to not only support this year’s budget setting, Council Plan development and service planning but to also form the basis for further work, to build a better insight into residents’ views about the Council, their local area and services.
2.5Cabinet will take account of the consultation when drawing up firm proposals to the Council. Results will be communicated after the consultation has ended.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Place Department Risk ManagementIt was agreed that the Chairman take a request to Cabinet to open the project to scrutiny by the Committee bearing in...
National Fraud Initiative UpdateRESOLVED that the Committee note the outcomes to date of the Council’s participation in the NFI 2024-25 exercise and ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.