to 1) Approve to use of non-Derbyshire County Council frameworks, following Protocol 2(a) of the Council’s Financial Regulations to commission Professional Consultancy and Construction providers to support the delivery of a wide variety and volume of projects within the Place directorate; and 2) Approve that the award of contracts, under Protocol 2(b) of the Council’s Financial Regulations, to support the delivery of the Council’s Capital programmes is delegated to the Executive Director for Place. to 1) Approve to use of non-Derbyshire County Council frameworks, following Protocol 2(a) of the Council’s Financial Regulations to commission Professional Consultancy and Construction providers to support the delivery of a wide variety and volume of projects within the Place directorate; and 2) Approve that the award of contracts, under Protocol 2(b) of the Council’s Financial Regulations, to support the delivery of the Council’s Capital programmes is delegated to the Executive Director for Place.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Use of Professional Consultancy and Construction Frameworks for Delivery and Implementation of Projects within Place Directorate in Derbyshire County Council (Cabinet Member for Potholes, Highways and Transport)
1. Divisions Affected
1.1County-wide.
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To seek Cabinet approval to utilise non-DCC frameworks, following Protocol 2(a) of the Council’s Financial Regulations to commission Professional Consultancy and Construction providers to support the delivery of a wide variety and volume of projects within the Place Directorate.
3.2To seek Cabinet approval that the award of contracts, under Protocol 2b of the Council’s Financial Regulations, to support the delivery of the Council’s Capital programmes is delegated to the Executive Director - Place.
4. Information and Analysis
4.1Since the late 1990s, the Council has adopted a mixed economy of in- house and partner consultants and contractors in the delivery of Capital Projects. This model has provided operational flexibility, at the same time as providing a wide range of services, to address peaks and to provide specialist services and capabilities, some of which are not available in-house.
4.2Over the past few years, the Council has seen a significant increase in Government funding for the Capital Programmes. At the same time, the Council has experienced shortages in staff which has led to a backlog in delivery of the increased Capital Programme. The Council has initiated a new recruitment drive and various transformation programmes to address these shortages and engaged with a wide variety of alternative providers to identify the options available in supporting the in-house services.
4.3For example, since 2021, the Highways Capital Delivery Programme has seen a significant increase growing from c£17m per annum to currently c£40m per annum for the last three financial years. The Service has had to adapt and flex to accommodate this growth whilst growing the capacity of the in-house service.
4.4With the recent establishment of the East Midlands Combined County Authority (EMCCA), there is clear intention that highways will receive significant investment going forward. The service is currently looking at an increase in capital programme to approximately £70m in 2025-26 and is highly likely to remain at this investment level for the foreseeable future.
4.5On 14 January 2021, Cabinet approved a report which gave approval for the commissions from various Professional Consultancy and Construction providers to support the delivery of a wide variety and volume of projects within the Place Directorate (Minute No. 07/21 refers).
4.6In the short term, whilst the Council has successfully procured and established its Professional Services Partnership (PSP), it is now two years into that relationship and there is still a requirement given the scale of the capital programmes over the next five years to establish routes to sufficient professional consultancy and design services to aid the delivery of the programmes across Place.
4.7With respect to construction projects, the Council has an established relationship with its regional supplier on the Midlands Highways Alliance plus - Medium Schemes Framework which gives access to Tier 1 contractors, but wider access to Tier 2 contractors and specialists are required through access to other frameworks.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Use of Professional Consultancy and Construction Frameworks for Delivery and Implementation of Projects within Place Directorate in Derbyshire County CouncilReport
87/25Use of Professional Consultancy and Construction Frameworks for Delivery and Implementation of Projects within Place Directorate in Derbyshire County CouncilThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.