RESOLVED to: 1) Approve the acceptance of the Local Transport Plan Highways Capital Settlement 2025-26; 2) Approve the additional schemes outlined in Appendix 2 of the report; 3) Delegate authority to the Highways Director, as a Chair of the Highways Capital Programme Board, in consultation with the Cabinet Member for Potholes, Highways and Transport for the approval of any changes to the programme within the tolerance of the overall budget; 4) Delegate acceptance of Bus Services Grant funding, Bus Service Improvement Plan funding and other funding allocations for public transport from the East Midlands Combined County Authority (EMCCA) to the Executive Director Place, in consultation with the Cabinet Member for Potholes, Highways and Transport; 5) Approve the extension of the existing contract arrangements for Traffic Management (Contract reference PLACE 145) to £8.2m; 6) Delegate to the Authority’s Section 151 Officer that the relevant grant conditions be accepted and discharged appropriately; and 7) Note the work on-going to access and accept EMCCA regeneration funding as originally set out in the Cabinet report (minute 64/25 refers) of 13th March 2025 and note that a further report be brought to the Cabinet to confirm regeneration priorities, updating the Council’s Regeneration and Commercial Pipeline.
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
Local Transport Plan Highways Capital Settlement and Public Transport Funding 2025-26 (Cabinet Member for Potholes, Highways and Transport)
1. Divisions Affected
1.1County-wide.
2. Key Decision
2.1This is a key decision because it is likely to result in the Council incurring expenditure which is, or savings which are significant having regard to the budget for the service or function concerned (this is currently defined as £500,000) and it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more electoral areas in the County.
3. Purpose
3.1To seek Cabinet approval to accept the Local Transport Plan Highways Capital Settlement 2025-26.
3.2To seek Cabinet approval to the additional Highways schemes outlined in Appendix 2.
3.3To seek Cabinet approval to delegate authority to the Highways Director, as Chair of the Highways Capital Programme Board, for the approval of any changes to the programme within the tolerance of the overall budget.
CONTROLLED 3.4 To seek Cabinet approval to extend existing contract arrangements for Traffic Management (Contract reference PLACE145) to £8.2m in order to support the expanded programme.
3.5To seek Cabinet approval to delegate acceptance of Bus Services Grant funding, Bus Service Improvement Plan (BSIP) funding and other funding allocations for public transport from the East Midlands Combined County Authority (EMCCA) to the Executive Director Place, in consultation with the Cabinet Member for Potholes, Highways and Transport.
3.6To ask the Cabinet to note work on-going to access and accept EMCCA regeneration funding as originally set out in Cabinet Report, Regeneration Programme Pipeline of 13 March 25 (Minute No. 64/25 refers) and that a further report will be brought to Cabinet, updating the Council’s Regeneration and commercial Pipeline.
3.7To seek Cabinet approval to delegate to the Authority’s Section 151 Officer that the relevant grant conditions are accepted and discharged appropriately.
4. Information and Analysis
4.1Set up in 2024, EMCCA is now in receipt of significant funding allocations from central Government, to enable it to invest in the region’s transport, regeneration and highways infrastructure. As one of four Constituent Authorities, Derbyshire County Council has been allocated funding from EMCCA for 2025/26 in order to support delivery of its functions within the County. This includes:
• Local Transport Plan Funding: Highways Maintenance Block and Integrated Transport Block • Bus Grant Award funding, BSIP funding and other one-off funding allocations for Public Transport • Delivery of capital and revenue regeneration projects/programmes.
4.2This report focuses on decisions to receipt and then provide for the expenditure of this funding. EMCCA is responsible for a range of other funding which falls outside the scope of this report. Subsequent reports will be brought to Cabinet as appropriate.
Local Transport Plan Funding
4.3The Local Transport Plan Funding Award for 2025-26 has now been confirmed but was delayed by the Government’s Autumn 2024 spending review. To enable the early design and delivery of the 2025-
CONTROLLED 26 Highways capital programme, Cabinet therefore approved the indicative 2025-26 Programme at its meeting on 14 November 2024 (Minute No. 171/24 refers).
4.4The amount of funding the Council receives is based on the application of various criteria relating to its highway assets, such as the total length of road (by road type), the number of maintainable bridge structures, and the number of lamp columns that need to be maintained. The award generally consists of two main funding blocks:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.