Update on the Cloud Strategy and Cloud Migration Programme
ApprovedExecutive1 paper
AI summaryCabinet approves £0.95m of capital funds to procure a cloud implementation partner and migrate remaining council systems and data from the County Hall datacentre to Microsoft Azure Cloud.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedApproves procurement of implementation and hosting partners
MoneyNot stated
What happens nextProcure implementation partnerApril to August 2026, then migration
Who it affectsCouncil digital services and dataAbout 200 systems still on County Hall datacentre
What was decided
Cabinet approved using £0.95m of the £3.95m capital budget to procure a cloud implementation partner to move all remaining council applications and data from the County Hall datacentre into Microsoft Azure Cloud. Report P62, 4.25
Cabinet approved moving from the completed design stage (£0.095m spent with the design partner Expert Thinking) into a full implementation and migration stage. Report P62, 4.4
Cabinet approved procuring the council's existing hosting partner for Microsoft Azure Cloud hosting services, and authorised the Executive Director for Corporate Services and Transformation, with the relevant cabinet members, to award the contracts. Report P63, P64
Why
The County Hall datacentre is now the only on-site facility after Shand House closed in October 2025, and it is ageing, unsuitable and untested for disaster recovery, creating risks of outages, cyber attack and data loss. Report 4.7, 4.8, 4.9, 4.10, P7
Staying on-site would need a new purpose-built datacentre costing £2m-£3m capital, without the resilience and flexibility benefits of cloud. Report 4.13, 6.1, P54, P55
Cloud migration removes the single point of failure, improves cyber security, supports future demands such as Local Government Reorganisation and EMCCA partnerships, and delivers a better capital and revenue position than the original 2024 plan. Report 4.20, 4.21, 4.26, 4.31, 4.33, 11.1, 11.4, 11.6
What happens next
Procure the implementation partner between April and August 2026, then run implementation phases starting September 2026, including environment build, pilot, test, server and data migrations, and handover. Report P34, 4.29, 4.30
Decommission the physical County Hall datacentre and associated legacy infrastructure between week 29 and week 52 of the implementation, with a full date-specific schedule set after the partner is appointed. Report P34, P35, P36
Project oversight will be provided through the PMO, with monthly highlight reports to the CST Change Board and the Portfolio Direction Group, and governance classified as Category A. Report 4.27, P29
The money
£0.95m Capital to procure cloud implementation partner from the approved £3.95m Report P62, 4.25
£3.95m Approved capital for the cloud programme, reduced from original £6.2m Report 4.4, 4.20
£0.576m Estimated revenue cost in year one (2026-27) for cloud hosting Report 4.23, 4.24
£0.095m Capital already spent on the design stage with Expert Thinking Report 4.4, P62
£2m-£3m Estimated capital cost of a new on-premises datacentre if not moving to cloud Report 4.13, 6.1
£1.056m Original annual revenue estimate, now reduced to £0.576m-£0.400m Report 4.21
Options considered
Chosen: Migrate to a best-in-class cloud datacentre (Microsoft Azure) using a new implementation partner and the existing hosting partner. Removes single point of failure, improves cyber security, is cheaper than a new on-premises datacentre, and supports LGR and EMCCA readiness. Report P42, 4.13, 4.20, 4.26, 6.1, P55
Rejected: Maintain current County Hall datacentre or build a new on-premises facility. Not fit for purpose, would need £2m-£3m of new capital, and would not deliver the resilience, security or flexibility of cloud. Report 6.1, P54, P55
Implications
Financial: £0.95m capital plus £1.576m revenue over three years; year-one revenue largely covered by savings when SAP migrates from Microsoft Azure to SAP Rise in August 2026, with the £0.400m pressure bid acting as contingency. Report 4.23, 4.24, P97, 1.1
Legal: Procurements will follow the council's Contract Standing Orders and relevant procurement legislation, and legacy data will be retired in line with GDPR. Report 2.1, 11.5, P84
Risk: Risks include data loss, project overspend, limited internal capacity, nearly 200 systems to migrate, legacy site failure before completion, LGR timing in April 2028, scope creep and possible service delays during cutover. Report 4.10, P97, P98, P100, P101, P102
Staffing: No formal organisational change planned, but one or two technology support roles may become unnecessary over the next 12 months; the report says turnover should absorb this. Report 3.1, 5.1, P86
Equalities: Equalities impact assessment marked not applicable. Report 5.1, P90
Other: Supports the Council Plan outcomes on efficiency, integration, digital and financial transformation, and best-value service reviews. Report 6.1, P92, P94
Who and where
Council digital services and users of the approximately 200 systems still hosted at County Hall Report 4.18, P98
Directorates relying on the systems being migrated, including Children's Services, case management, websites and data storage Report 4.18
Council IT and digital teams, with potential small reduction in technology support roles Report 3.1, 5.1
Future Local Government Reorganisation and EMCCA arrangements, which the migration is designed to support Report 4.33, 11.4, P100
Timeline
9 April 2026: Cabinet approval received Report P34
April, August 2026: Procure the implementation partner Report P34
August 2026: SAP systems scheduled to migrate from Microsoft Azure to SAP Rise Report 4.24
September 2026 onwards: Implementation phases: pre-migration, environment build, pilot, test, development server migrations (week 8-11), production server and data migrations (week 12-25), documentation and handover (week 26-28) Report P34
Week 29, 52: Internal DCC staff phase and decommissioning of the physical datacentre Report P34
Plain English for the jargon
Cloud: Remote datacentre services provided over the internet, replacing servers held on the council's own premises.
Microsoft Azure: The cloud platform the council will use for hosting.
IaaS / PaaS / SaaS: Infrastructure, Platform and Software as a Service: different levels of cloud service where the provider hosts infrastructure, a platform, or the full application.
EDRMS: Electronic Document and Records Management System, which is being migrated separately through SharePoint.
LGR: Local Government Reorganisation, scheduled for April 2028, which the migration is designed to support.
EMCCA: East Midlands Combined County Authority, a strategic partnership the migration is designed to support.
PDG: Portfolio Direction Group, the internal body overseeing the project.
DOGE: Department of Government Efficiency, the title used for the Cabinet Member for Council Efficiency in this report.
DR: Disaster Recovery, the ability to restore services and data after a major failure.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item55/26
Resolved
RESOLVED to: 1) Approve the use of capital funds £0.95m from the approved £3.95m, to procure a cloud implementation partner to build our cloud infrastructure and migrate all remaining Council applications and onsite Council data from the physical datacentre at County Hall into the Microsoft Azure Cloud; 2) Approve progressing from the completed Design stage, delivered under the existing procurement (£0.095m), to a conclusive implementation and migration stage with an implementation partner; 3) Approve the Procurement of our existing Hosting Partner for the cloud hosting services (Microsoft Azure Cloud); and 4) Authorise the Executive Director – Corporate Services and Transformation, in consultation with the Cabinet Member for Business Services and Cabinet Member for Council Efficiency (DOGE), to award the contract(s).
Word for word from the decision Derbyshire published for this meeting.Source: democracy.derbyshire.gov.uk
4.1The Cloud Strategy was approved by Cabinet in April 2024, setting out a transition from traditional, largely on-premises Digital infrastructure to a cloud-first approach over five years, to underpin the Council Plan up to 2029-30.
4.2The strategy aligns with DCC’s Digital Strategy and broader ambitions for modern, efficient, and resilient service delivery.
4.3A Cloud Migration Programme Mandate was approved by the Portfolio Direction Group (PDG) in October 2024.
4.4In 2024, a requested capital budget of £6.2m (since reduced to £3.95m due to being less complex) over three years was approved by Cabinet for FY2026-28. £0.095m capital has been utilised in this 2025 to a fixed cost, cloud design and migration strategy only phase with design partner, Expert Thinking.
4.5Since the 2024 approval, a detailed assessment by Socitm, Shaping Cloud, and Expert Thinking, along with further project planning have refined both the scope and costings of the migration.
4.6As the scope has evolved and several major platforms have already migrated, the remaining activity is now defined as the Platforms and Infrastructure Cloud Migration Project.
Business Case for Change and Current Infrastructure Risks
4.7County Hall decant: The closure of Shand House as an office and a secondary datacentre in October 2025, alongside aging server and ancillary infrastructure, and the poor suitability of County Hall as a datacentre site, requires a timely decant of the County Hall datacentre. This also removes any future dependency on the County Hall site for Digital services.
4.8Physical hardware and datacentre obsolescence: End-of-life equipment, risk of hardware failure, cyber threats, and lack of vendor support.
4.9Single points of failures: With Shand House decommissioned, all remaining on-premises digital operations are concentrated in a single, aging datacentre at County Hall, increasing operational risk.
4.10Lack of disaster recovery and resilience: Current disaster recovery capabilities are untested and inadequate; physical risks include water ingress, outdated electrical backup generators, abandoned cabling and network bearer locations.
4.11Resource and skills constraints: Legacy systems require specialist knowledge not widely available in the market. Existing skills are at risk due to staff turnover and legacy Digital governance.
4.12Budget and investment constraints: Historical underinvestment has led to technical debt and increased risk profile.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.