Presentation on the Regeneration Pipeline

Noted Scrutiny 1 paper

AI summaryDerbyshire County Council's Place Scrutiny Committee noted a presentation on the county's Regeneration Pipeline, with no direct financial implications arising from the report itself.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee asked only to note the Regeneration Pipeline update
MoneyNo direct financial implicationsExisting project funding monitored via EMCCA and DfT returns
What happens nextNone specifiedDecision was to note only; no further committee action set
Who it affectsCouncil services and external partnersWorkload implications for Economy and Regeneration, Highways, Legal, Property and Finance

What was decided

The Committee noted the report and presentation on the Regeneration Pipeline. Report 8.1, P9

Why

The report and presentation were brought to inform members of the Place Scrutiny Committee about the Regeneration Pipeline. Report 9.1, P11

The Regeneration Programme addresses several Council Plan objectives, including supporting places to live and work, boosting the economy, protecting the environment and public spaces, and keeping roads safe and well maintained. Report 6.1, P25, P26, P27

What happens next

No direct next steps arise from this noting item; individual projects within the pipeline continue to be developed and monitored through existing governance, including project control boards and quarterly funding returns to EMCCA and the Department for Transport. Report 1.1, P15

Options considered

  • Rejected: Consider alternative options at this stage. The report states no alternatives are directly relevant to this overview, although most substantive projects have separately gone through project development processes where alternatives were considered. Report 4.1, P4

Implications

  • Financial: No direct financial implications from this report. Funding allocations for existing projects are monitored through quarterly returns to EMCCA and the Department for Transport, with project control boards overseeing budget, costs and spend profile. Report 1.1, P15
  • Legal: All projects in receipt of external funding have a grant funding agreement setting out the terms, required outputs and any clawback conditions. Report 2.1, P17
  • Staffing: The regeneration portfolio has significant workload implications for staff in the Economy and Regeneration Service, alongside Highways, Legal, Property and Finance. External support is being used and additional in-house capacity is being established. Report 3.1, P19
  • Equalities: Individual projects within the Regeneration Pipeline are subject to equalities impact assessment at the appropriate stages of their development. Report 5.1, P23

Who and where

  • Economy and Regeneration Service staff, with workload implications for Highways, Legal, Property and Finance services Report 3.1, P19
  • Partners including local authorities and the East Midlands Combined County Authority (EMCCA) Report 3.1, P2
  • The Department for Transport, as a funder receiving quarterly returns Report 1.1, P15

Timeline

  • 16 October 2025: Cabinet report on the Regeneration Project Pipeline (Minute No. 122/25) is listed as a background paper. Report 6.1

Plain English for the jargon

  • EMCCA: East Midlands Combined County Authority, a regional combined authority covering parts of the East Midlands including Derbyshire.
  • Regeneration Pipeline: The portfolio of regeneration projects being developed and delivered by the council with partners.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17/26

Resolved

RESOLVED that the Committee note the report and presentation.
Word for word from the decision Derbyshire published for this meeting. Source: democracy.derbyshire.gov.uk

Follow this further

Built from Derbyshire's papers

What the report saysPro

Report to Place Scrutiny Committee

Consultation

3.1None as a direct result of this report but a wide range of engagement and consultation exercises have taken place with partners, including local authorities and the East Midlands Combined County Authority

CONTROLLED (EMCCA) in the development of the Regeneration Pipeline outlined here.

Alternative options considered

4.1None directly relevant to this overview but most of the substantive projects identified for the Regeneration Pipeline have been subject to ‘project development’ processes where alternatives have been considered.

5. Implications

5.1Appendix 1 sets out the relevant implications considered in the preparation of the report.

Background papers

6.1Cabinet Report, Regeneration Project Pipeline, dated 16 October 2025 (Minute No. 122/25 refers).

Appendices

7.1Appendix 1 – Implications.

Recommendation

8.1That the Committee:

a) Notes the presentation.

Reason for recommendation

9.1This report and presentation is to inform members of the Place Scrutiny Committee on the Regeneration Pipeline.

Report Karl Apps Contact [email protected] Author: details:

CONTROLLED Appendix 1 Implications

Financial

1.1There are no direct financial implications because of this report. The funding allocations for existing projects are monitored through quarterly returns to both EMCCA and the Department for Transport. The governance arrangements for individual, active projects include project control boards, at which budget, costs and spend profile are discussed.

Legal

2.1All projects in receipt of external funding have a grant funding agreement in place. This sets out the terms of the grant allocation, the outputs required to be achieved, and any conditions linked to clawback of funding.

Human Resources

3.1There are no human resource issues directly associated with this report. However, the portfolio of regeneration projects has significant implications for the workload of staff within the Economy and Regeneration Service, alongside Highways and Legal, Property and Finance services. External support is secured to help manage key aspects of projects and ensure programme delivery and additional in- house capacity is being established.

Information Technology

4.1None.

Equalities Impact

5.1Individual projects within the Regeneration Pipeline are subject to equalities impact assessment at the appropriate stages of their development.

Corporate objectives and priorities for change

6.1The Regeneration Programme addresses directly several objectives set out in the Council Plan. Specifically:

o Great places to Live and Work o Boost the economy

CONTROLLED o Protect and improve our environment and public spaces o Keep Derbyshire’s roads safe and well maintained

Other (for example, Health and Safety, Environmental, Sustainability, Property and Asset Management, Risk Management and Safeguarding)

7.1None.

CONTROLLED

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Presentation on the Regeneration PipelineReport 92 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 13 attended
SR
Councillor Sam RedfernChairman, present
RS
Councillor Richard SmithVice-Chairman, apologies
SB
Councillor Steve BullCommittee Member, present
DH
Councillor David HarveyCommittee Member, apologies
JH
Councillor Jamie HodgsonCommittee Member, apologies
GK
Councillor Gez KinsellaCommittee Member, present
AM
Councillor Alex MillwardCommittee Member, present
MS
Councillor Melandra SmithCommittee Member, apologies
DT
Councillor Dawn TaylorCommittee Member, present
CB
Claire BrailsfordOfficer, present
KA
Karl AppsOfficer, present
DA
Daniel AyrtonOfficer, present

All 13 on the meeting page

More from Derbyshire Place Scrutiny Committee

All decisions
MeetingDecisionOutcome
22 Jul 2026 Presentation on Collection and Packaging ReformsRESOLVED that the Committee note the report and presentation. Noted Open
25 Feb 2026 Update on the Development of the Environmental Sustainability Strategy (2026-2030)RESOLVED that: a) The Committee notes the progress made in developing the Environmental Sustainability Strategy (2026... Noted Open
24 Sep 2025 Presentation on the East Midlands Combined County Authority and the Transition of the Transport FunctionRESOLVED that the Committee notes the report and presentations. Decided Open
26 Feb 2025 Management of Section 278 and Section 38 Highway Legal AgreementsRESOLVED that the Committee: a) Acknowledges and endorses the processes outlined in the ... view the full minutes tex... Decided Open
20 Nov 2024 Work Programme 2024-25RESOLVED that the Committee notes the 2024-25 work programme. Decided Open