Shadow Executive Committee decided this item on Monday 12 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision 1. That the decision of the ... view the full minutes text for item 84.
Peninsula Redevelopment Scheme, Weymouth
Date of Meeting 12th November 2018
Martin Hamilton Officer Strategic Director – Weymouth & Portland Borough Council
Subject of Report Peninsula Regeneration Scheme, Weymouth
Executive Summary Phase 1 Peninsula Regeneration Scheme delivers:- Economic growth for Weymouth and the Harbour Revitalisation of prominent site redundant since 2015 Improved Statutory Harbour Authority (SHA) income & facilities Reduced liability for Dorset Council to provide capital funds for harbour walls, by giving the SHA the ability to generate surplus income for a works reserve fund
The development proposal reflects the approved town centre masterplan and draws on LEP funded redevelopment options appraisals and study of tourism potential.
The business case for Phase 1 Regeneration has been considered by the Dorset Section 151 officers and approved by:- Harbour Management Board – 13th September 2018 Management Committee - 18th September 2018 WPBC’s Full Council – 11th October 2018
The Phase 1 Regeneration Scheme entails expenditure of £14.445m to construct a hotel, pub/diner with accommodation, café, and public realm and harbour improvements including essential repairs to Harbour Wall D. Of this sum £11.441m will be borrowed from Public Works Loan Board and the balance coming from Weymouth & Portland Borough Council budgets. The business case for Phase 1 shows the scheme generating a surplus annual income whilst repaying both capital and interest of the loan.
The report sets out safeguards for Dorset Council including a requirement for pre-lets and agreed construction costs prior to committing resources to build.
Impact Assessment: Budget:
If approved the whole scheme would be built into the 2019/20 capital programme. WPBC has already approved funding for improvements to the harbour walls totalling £1,955,000. The business case shows that the scheme generates annual income of £213,000 after repaying the PWLB loan. This would be built into the ring fenced harbour account and available to contribute to future harbour wall repairs.
Risk Assessment:
Having considered the risks associated with this decision using the LGR approved risk management methodology, the level of risk has been identified as: Peninsula Redevelopment Scheme, Weymouth
Current Risk: MEDIUM (but mitigated to LOW due to safeguards built into the project delivery mechanism) Residual Risk: LOW
Other Implications:
The Dorset Council will be the successor organisation from Weymouth & Portland Borough Council for the Weymouth Statutory Harbour Authority.
The Phase 1 delivery of this regeneration project enables a resolution of a redundant site, produces a surplus annual income, and removes the need for Dorset Council to repeat the lengthy and costly process undertaken to date by Weymouth & Portland Borough Council. In addition Phase 1 addresses a critical risk of infrastructure failure at Harbour Wall D.
Recommendation Shadow Executive is recommended to endorse the decision taken by Weymouth & Portland Borough Full Council, acting as the Statutory Harbour Authority (SHA) which recommended to:
a) Note progress with the regeneration scheme for the peninsula.
b) Approve the business case as attached in confidential Appendix 3.
c) Approve borrowing of £11,441,000 for Phase 1 of the regeneration scheme, with arrangements for draw down of funds delegated to the Section 151 Officer.
d) Delegate to the Strategic Director in consultation with the Section 151 Officer and Regeneration Asset Management Group, to undertake the necessary actions to progress this scheme including but not limited to securing planning consents, procuring contracts and agreeing pre-lets. With consultation to the Harbour Management Board and full Council as the SHA as appropriate on layout and any changes which affect the business case and matters which might impact the core statutory functions associated with the running of the harbour (safety of navigation, open port duty, conservancy etc.)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Peninsula Redevelopment SchemeReport | 3.6 MB | DownloadRead as text |
Follow Shadow Executive Committee at Dorset and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Mar 2019 | Adoption of Overarching Enforcement PolicyDecision That the draft overarching enforcement policy be adopted. Reason for Decision The adoption and compliance wi... | Approved | Open |
| 25 Mar 2019 | Internal Audit Forward PlanDecision That the Internal Audit plan be adopted. Reason for Decision To ensure that the new Council maintains an eff... | Approved | Open |
| 25 Mar 2019 | Dorset History Centre - Capital Project UpdateDecision That as a matter of urgency after 1 April 2019, a report be considered by the Dorset Council Cabinet on this... | Decided | Open |
| 11 Mar 2019 | Adoption of RIPA PolicyDecision 1. That the draft RIPA policy attached as Appendix 1 of the Lead Member’s report be adopted; 2. That the Chi... | Approved | Open |
| 11 Mar 2019 | Tricuro: Shareholder Viability Assessment ReportDecision That the recommendation be withdrawn from the meeting. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.