Decision That the Capital Highways Forward Programme, as set out in the appendices of the Lead Members’ report, be approved. Reason for Decision Effective asset management required a clear forward capital programme to be developed according to a consistent set of principles and criteria. The County Council’s approach as set out in the approved Highways Asset Management Plan satisfied the criteria in the Department for Transport self-assessment process, contributing to the Council securing the maximum incentivised funding. This forward programme was subject to consultation ahead of programming and construction.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
Lead Member Cllr Daryl Turner, Lead Member for the Environment, Roads and Parks
Officer Mike Harries, Corporate Director for Environment & Economy
Capital Highways Forward Programme 2019/20, 2020/21 and Subject of Report 2021/22
Executive Summary Ordinarily reports relating to the functions of a predecessor council but with implications for the new Dorset Council come forward as recommendations to the Shadow Executive from the predecessor council.
This report has been submitted directly to the Shadow Executive Committee without prior consideration by the County Council’s Cabinet as it is time critical to the need to make a self-assessment submission to the Department for Transport, due on the 1st February 2019.
The report summarises proposals for the Capital Highways forward programme, which is inclusive of maintenance programmes across different asset groups as well as proposed Highway Improvement programmes.
The report includes proposed schemes for Christchurch and so recommendations are being made to the Bournemouth Christchurch and Poole Shadow Executive as well as to the Dorset Shadow Executive Committee.
The £2.3million incentivised element of our funding from the Department for Transport has criteria that we must conform to, to ensure we remain in the top band, securing 100% funding. One of those criteria is to ensure forward programmes of work are signed off by senior decision makers.
Impact Assessment: Equalities Impact Assessment:
This report does not contain a new strategy, policy or function which would require an EQIA to be completed.
Use of Evidence: Page 2 – Capital Highways Forward Programme
The sites are based on existing strategies and supporting data used in both identification and prioritisation of schemes.
Budget:
The programmes are based on expected budgets, to include a carry over of capital maintenance funds into 2019/20, arising from the allocation of additional funds from the DfT being credited to the 2018/19 programme.
Risk Assessment:
Having considered the risks associated with this decision using the LGR approved risk management methodology, the level of risk has been identified as: Current Risk: MEDIUM (Delete as appropriate) Residual Risk: MEDIUM (Delete as appropriate)
Other Implications: None.
Recommendation That the Shadow Executive approves the Capital Highways Forward Programme as set out in the appendices
Reason for Effective asset management requires a clear forward capital programme Recommendation developed according to a consistent set of principles and criteria. The County Council’s approach as set out in the approved Highways Asset Management Plan satisfies the criteria in the Department for Transport (DfT) self-assessment process, contributing to the Council securing the maximum incentivised funding. This forward programme is subject to consultation ahead of programming and construction.
Appendices Appendix 1 - Capital Highways Forward Programme
Date agreed by Lead Member 3 January 2019 Page 3 – Capital Highways Forward Programme
Capital Highways Forward Programme
1. Introduction
1.1This report sets out the proposals for the capital Highways forward programme to include maintenance across a number of asset groups and activities, based on current policies and strategies documented in the Highways Asset Management Plan, approved in December 2018.
1.2These programmes have been derived from strategies linked to outcomes that support key corporate objectives such as safety, accessibility of the network linked to road condition, schemes to promote walking and cycling encouraging healthier lifestyles, as well as seeking to promote social and economic benefits.
1.3It also documents the Highways Improvements forward programme, which links to the Local Transport Plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.