Recommended That Council: 1. adopts the Bournemouth, Christchurch, Poole and Dorset Waste Plan subject to the inclusion of the main modifications that are appended to the Inspector’s Report; 2. confirms that the formal adoption date will begin two weeks from the date at which both BCP Council and Dorset Council have resolved to adopt the plan; 3. delegates to the Lead Member for Planning, after consultation with the Executive Director for Place: a. any additional (non-material) modifications to the Plan which were the subject of consultation, together with any other additional modifications which benefit the clarity of the Plan; b. authority to expedite any technical/procedural matters associated with adoption of the plan, including those connected with Dorset Council’s role as the Competent Authority on matters relating the Habitats Regulations Assessment1 of the Plan. Reasons for Decisions 1. To ensure Dorset Council had an up-to-date statutory policy framework for considering planning applications for waste development. 2. To comply with the requirements of the statutory/consequential orders concerning Shaping Dorset Council which required a council-wide local plan by 2024.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
In March 2018 the draft Bournemouth, Dorset and Poole Waste Plan was submitted to the Secretary of State and an independent inspector was appointed to hold an examination into the plan’s soundness. Public hearings were held in June 2018. The inspector was invited to include in his report any recommendations needed to make the plan sound and therefore capable of adoption.
The Inspector’s report has now been issued and it concludes that, subject to the inclusion of the modifications, the plan is legally compliant and sound. The modifications do not significantly alter the thrust of the overall strategy that was submitted for examination.
Under the provisions of the Planning and Compulsory Purchase Act 2004 (as amended), it is the responsibility of the Local Planning Authority to adopt the Waste Plan. It can only be adopted if it includes the modifications that the inspector considers are needed to make it sound.
As the Plan covers the two administrative areas of Bournemouth, Christchurch and Poole Council (BCP) and Dorset Council, it will need to be adopted by both unitary authorities. Once this occurs, there will follow a 6-week legal challenge period from the date of adoption during which interested parties have the right to challenge the plan on legal/procedural matters under the provisions of the Planning and Compulsory Purchase Act 2004.
The Waste Plan will be the first local plan adopted by Dorset Council and it will provide an up-to-date statutory planning framework for waste matters across the entire local authority area, as well as that of Bournemouth, Christchurch and Poole. This will enable both Councils to plan positively for waste needs up to 2033 in compliance with national policy. It will also supersede the remaining ‘saved’ policies from the 2006 Bournemouth, Dorset and Poole Waste Plan.
Equalities Impact Assessment:
The Waste Plan has been the subject of an Equalities Impact Assessment (including EqIA screening) and issues identified in the assessment have been taken into consideration in preparing the plan.
Budget:
There are no immediate budget implications associated with adoption of the Waste Plan, although there is a right of legal challenge for a six-week period immediately following the Page 2
adoption of a plan. In the event of such a challenge there may be legal costs associated with defending the challenge. In the event that the Council opts not to adopt the plan, it would expose the authority to the risk of on-going significant costs in dealing with planning appeals and having to commission extra evidence to justify its decisions on waste applications. This is because there would not be an up-to-date development plan and so the presumption in favour of sustainable development would prevail, with decisions having to be judged directly against the National Planning Policy Framework. It would also pose a risk to the waste management responsibilities of Dorset Council in terms of planning to meet future needs.
Risk Assessment:
Having considered the risks associated with this decision, the level of risk has been identified as: Current Risk: LOW Residual Risk LOW
Other Implications:
The plan was the subject of a Sustainability Appraisal (incorporating Strategic Environmental Assessment) and a Habitats Regulations Assessment. It has also involved all relevant service providers within Dorset Council. Any issues regarding sustainability or corporate interests have been taken into account in preparing the plan.
Recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.