Decision That a decision be deferred to enable further exploration of alternative options. Reason for decision : A deferral will provide the Council with the opportunity to explore alternative options for the funding of the improvements project.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
Dorset Council Cabinet Capital funding option for the West Bay Coastal Improvements Project
Date of Meeting: … 31st July 2019
Lead Member: … Cllr T Ferrari – Lead Member for Finance, Commercial and Assets. Cllr R Bryan – Lead Member for Highways, Travel and Environment
Local Member(s) Cllr David Bolwell, Cllr Kelvin Clayton and Cllr Sarah Williams
Lead Officer: … Greg Northcote Estates Manager
Appendix 1 is not for publication by virtue of paragraph 3 of Schedule 12A, Part 1 of The Local Government Act 1972, as amended. The public interest in maintaining the exemption outweighs the public interest in disclosing it.
Executive Summary: This Report proposes to secure a capital funding contribution towards works forming part of the current West Bay Coastal Improvements Project from the tenant of the Council’s Campfield Site in exchange for granting a lease extension.
Equalities Impact Assessment: None required.
Budget: Consideration should be given to Opt to Tax the Campfield Site for VAT purposes if the Council is seeking to recover VAT expended on the site.
Part of the capital premium will be recovered by the tenants after 2024 through a 7 year repayment arrangement as detailed in the Report. No interest is payable on the recoverable capital in the intervening period.
Risk Assessment:
Having considered the risks associated with this decision, the level of risk has been identified as: Current Risk: HIGH/MEDIUM Residual Risk LOW
There is a I in 50 year probability of flooding affecting properties in Forty Foot Way and the Campfield campsite with consequential financial, health and safety and Page 2
reputational risks.
Climate implications: None
Other Implications: Property and Assets; Considered in detail in the Report and Confidential Appendix.
Community Safety: The recommendations assist reducing the risks identified above.
Recommendation: To either approve a lease extension of the Campfield Site at West Bay until 31st January 2084 on the terms described in the Report or delay implementation of this phase of the Coastal Improvements.
Reason for Recommendation: The proposed lease extension secures a significant capital funding contribution towards the cost of required riverbank improvements from the Council’s current tenants Parkdean Resorts in return for the Council granting an extended lease for an additional 60 years on commercial terms.
Appendices: Confidential Appendix identifies the terms of the proposed lease extension.
Background Papers: West Bay Coastal Improvements - Outline Business Case. October 2018
1. Background and Reason Decision Needed 1.1 The West Bay Coastal Improvements Project is being led by the Environment Agency and is predicted to cost £10 million of which £1.2 million is the associated cost of required river bank improvements. While most of the works are funded and already include a £3 million capital contribution from Dorset Council the cost of the river bank improvements is still to be funded.
1.2The West Bay Coastal Improvements Business Case states that ‘The structural integrity of the Parkdean embankment along the River Brit is low, with damage to the toe causing localised slip failures in several Page 3
locations. Breaching of this embankment would lead to widespread flooding of the caravan park and backdoor flooding of properties in the town.’ The Report states that a 1 in 50 year flooding event will cause a 50 metre breach to the embankment. This section of the river bank adjoining the Council’s Campfield site is leased to Parkdean Resorts and was last strengthened by the Council’s tenants as a condition of the grant of their current lease in 2003. The riverbank improvements are expected to reduce the prospect of riverine flooding from 1 in 50 years to 1 in 200 years. Without the improvements a 1 in 200 year event is currently predicted to flood much of the Campfield site to a depth of 1 metre.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.