Dorset Council
Cabinet, Tuesday 3 September 2019 at 10.00am

Procurements over £5 million in respect of: Highways Contractor Resource

Approved Executive 1 paper

Cabinet approved this item on Tuesday 3 September 2019. Below is the council's own wording, with the papers it was decided on.

Item45

Resolved

Decision That the procurement and award of a Dorset Highways Contractor Resource (Labour Top-Up) Framework (re-procurement exercise) be approved. Reason for the Decision Cabinet is required to approve all key decisions with a financial consequence of £500k or more, and procurements over £5m are subject to individual reports (Cabinet 04-06-19 refers). The technical summary for reasons for the recommendation is as follows: · The pre-agreed rates and contract conditions allows Dorset Highways to respond to changing demands / circumstances quickly and efficiently. · The quick procured method - call off, is far quicker than the traditional quote, tender and mini-competition methods of procurement. This reduces administration and back office costs · The multi supplier lots provide resilience if the preferred supplier cannot fulfil the call-off · The multi supplier lots provide technical expertise in a variety of specialist areas · The multi-supplier framework has worked for the last eight years. · The organisation risk is LOW
Word for word from the decision Dorset published for this meeting. Source: moderngov.dorsetcouncil.gov.uk

Follow this further

Built from Dorset's papers

What the report saysPro

Report to Cabinet

Cabinet Procurement over £5m Report: Dorset Highways Contractor Resource (Labour Top-Up) Framework

Date of Meeting: 3rd September 2019 Lead Member: Cllr Tony Ferrari, Lead Member for Finance, Commercial and Assets Local Member(s): All Lead Officer: Aidan Dunn, Executive Director for Corporate Development (S151)

Executive Summary: The Dorset Highways Construction Delivery Team has, and continues to have, a requirement to procure additional labour resources to operate as part of its mixed economy delivery model. The mixed economy model provides suitable resilience and business continuity to ensure that Dorset Council can meet its statutory highway duties. Additional labour resources are required to cover the following specific areas:  Highway Construction Operatives - of various skill types  Traffic Management Operatives - of various qualifications  Specialist Plant Operatives - of various plant and equipment For the last four years this requirement has been fulfilled by utilising a Top-Up Resource (Multi-Supplier) Framework. The Framework is structured in Lots and all Lots are multi- supplier which ensures that flexibility, capacity, and best value for money services is secured. This Framework was set up with a maximum four-year term which expires at the end of March 2020. Various options have been considered over recent months to determine the best solution to fulfil these requirements from April 2020:  Do Nothing  Employ significant number of new skilled operatives  Procure additional resources through a Contractor Resource (Labour Top-Up) Multi- Supplier Framework  Procure additional resources through a Dynamic Purchasing System (DPS)  Procure additional resources through the Highway Works Term Service Contract  Procure additional resources through the Hampshire County Council Gen 3 Highways Frameworks After careful consideration of the benefits, risks and costs it has been determined that the preferred option is to re-procure a new Contractor Resource (Labour Top-Up) Multi-Supplier Framework.

Equalities Impact Assessment: N/A Budget: Based on past expenditure it is estimated that the Total Value will be £6m. More detail is shown in Appendix 1, Section 2 - Spend Overview.

Risk Assessment: Having considered the risks associated with this decision, the level of risk has been identified as:

Current Risk: MEDIUM

We have insufficient numbers of employed staff to deliver one of our most critical services: winter maintenance (level 3), carriageway defect repairs, safety critical improvement works.

Residual Risk: LOW

Additional labour resources can be hired in to accommodate peaks in workload. These can then be off-hired quickly and simply when work returns to normal, manageable levels. Failure to re-procure the Dorset Highways Contractor Resource Framework would put the service under extreme pressures to deliver the vital and critical highway functions:  Maintenance - winter maintenance, carriageway defect repairs  Improvements - capital funded safety improvement schemes

Climate implications: By procuring local suppliers from Dorset and the surrounding counties, we can reduce travel and commuting miles. This will help the new Climate Emergency Policy Development Panel meet their carbon reduction targets which are currently being discussed in response to Dorset Council’s declaration of a climate emergency.

Other Implications: N/A

Recommendation: The Cabinet is asked to consider the contents of this report and give approval for the procurement and award of a Dorset Highways Contractor Resource (Labour Top-Up) Framework (re-procurement exercise)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurements over £5 million in respect of: Highways Contractor ResourceReport 133 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 34 attended
SF
Councillor Spencer FlowerChairman, present
PW
Councillor Peter WharfVice-Chair, present
AA
Councillor Anthony AlfordCommittee Member, present
RB
Councillor Ray BryanCommittee Member, present
GC
Councillor Graham Carr-JonesCommittee Member, present
TF
Councillor Tony FerrariCommittee Member, present
LM
Councillor Laura MillerCommittee Member, present
AP
Councillor Andrew ParryCommittee Member, present
GS
Councillor Gary SuttleCommittee Member, present
DW
Councillor David WalshCommittee Member, apologies
MP
Matt ProsserOfficer, in attendance
AD
Aidan DunnOfficer, in attendance

All 34 on the meeting page

On this subject at Dorset

Search all
  1. Procurements over £5 million in respect of: Highways Contractor ResourceThis decision
  2. Procurements over £5 million in respect of: Electricity and GasDeferred
  3. Approval for procurements over £500kApproved
  4. Further approval for procurements over £500kApproved

More from Dorset Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 July 2026 (period 4) financial management report 26/27Decision (a) That the Senior Leadership Team’s forecast as of July 2026 including progress in addressing demand for s... Noted Open
8 Sep 2026 Additional Procurement Pipeline Report - over £500k (2026 - 27) and Modern Slavery Transparency Statement 2025 - 2026Decision (a) Cabinet considered the contents of the report (of 8 September 2026) in respect of proposed additional mo... Approved Open
8 Sep 2026 Exempt BusinessDecision That the press and the public be excluded for the following item(s) in view of the likely disclosure of exem... Decided Open
28 Jul 2026 Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ... Noted Open
28 Jul 2026 Dorset Local Visitor Economy Partnership Destination Management Plan(a) That the Dorset Local Visitor Economy Partnership Destination Management Plan (DLVEPDM) be adopted and (b) That a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies