Resolved 1)That progress in meeting the recommendations made by the previous Task and Finish Group to improve the shared service model be noted. 2)That support be given to the recommended timeline and process for renewing a decision on the Partnership agreement for Public health. Reason for Decision During local government reorganisation the Public Health Partnership was supported for a further minimum 12 months. This was due to expire in spring 2020. Continuing as a partnership would ensure we could provide the Public Health services to both unitary councils and the integrated care system in an efficient, effective and equitable way. To support both new councils in fulfilling their legal duty to improve health and reduce inequalities for their respective populations.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
This paper has two purposes. To update Members of the Joint Public Health Board on progress against the recommendations of the original task and finish group on the future of Public Health Dorset, to improve the shared service model for Dorset, Bournemouth and Poole, and to ask the Board to consider the future status of the partnership agreement for the shared service.
Equalities Impact Assessment:
Not required as no significant change to policy or services
Budget:
The Public Health revenue budget for 2019/20 within the partnership agreement is £27.7m.
Risk Assessment:
Having considered the risks associated with this decision, the level of risk has been identified as: Current Risk: LOW Residual Risk: LOW
Climate implications
Not applicable
Other Implications:
None Recommendation:
Board members are asked to note the progress in meeting the recommendations made by the previous task and finish group to improve the shared service model.
The Board is asked to support the recommended timeline and process for renewing a decision on the partnership.
Reason for recommendation
During local government reorganisation the Public Health partnership was supported for a further minimum 12 months. This is due to expire in spring 2020. Continuing as a partnership will ensure we can provide the Public Health services to both unitary councils and the integrated care system in an efficient, effective and equitable way. To support both new councils in fulfilling their legal duty to improve health and reduce inequalities for their respective populations.
Appendices
Appendix A – Progress against suggested development proposals from 2018 task and finish group
Appendix B – Task and finish group on future of Public Health Dorset – a shared service model for Dorset, Bournemouth and Poole – Findings from interviews with stakeholders
1.1Public health services have been provided to Councils under a shared service model ever since transition from the NHS in 2013. During the past 6 years, the service has successfully recommissioned most major public health services, developed an innovative integrated health behaviour change service, and provided systems leadership for prevention and population health management, working with Councils and the developing Integrated Care System.
1.2Local government reorganisation provided an opportunity to review the partnership and shared service model, in preparation for the creation of 2 new unitary Councils. The Interim Director of Public Health commissioned depth interviews with Joint Public Health Board members to consider the strengths and weaknesses of the shared service model. This made recommendations for improving the service model to the Joint Public Health Board in February 2019.
1.3Proposals for improvement were broadly in two categories:
• recommendations about how the Board functioned, including updating terms of reference to focus the Board’s work more clearly on the shared service; • developmental proposals designed to increase the effectiveness of integrated public health support to the 2 new unitary Councils and wider system.
1.4This paper has two purposes. To update Members of the Joint Public Health Board on progress against the recommendations of the original task and finish group. And to ask the Board to consider the future status of the partnership agreement for the shared service.
1.5During LGR the Board supported a recommendation in November 2018 to continue the shared service arrangement for a minimum of 12 months, in order that the shared service continue beyond the point of creation of the 2 new Unitary Councils in April 2019.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.