(a) That, in principle, the proposed three-year delivery programme in line with the TCF Strategic Outline Business Case, already approved by Cabinet, and guidance set out by the DfT in the Assurance Framework, be approved; (b) That the proposed Governance Framework be approved and authority be delegated to the Head of Highways in consultation with the Portfolio Holder for Highways, Travel and the Environment through the TCF Council Governance Board (CGB), for approval of future TCF proposals, detailed programme delivery decisions and the detailed design of each element of the programme ; (c) That the principle of regular TCF update reports going to the CGB and from there to DfT as stipulated within point 8 of the award letter, with consideration of Traffic Regulation Orders (TROs) associated with the programme being considered in line with current Dorset Council approvals, be approved. Reason for Recommendation : The delegations are designed to: (i) Allow maximum flexibility in meeting the strict DfT timeline for delivery over the next three years, with appropriate Dorset Council approvals in place. (ii) To ensure that the authority is best placed to progress scheme delivery at the pace required to meet the funding profiles set by the DfT.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
(a) Approves in principle the proposed three-year delivery programme in line with the TCF Strategic Outline Business Case, already approved by Cabinet, and guidance set out by the DfT in the Assurance Framework.
(b) Approves the proposed Governance Framework and delegates authority to the Head of Highways in consultation with the Portfolio Holder for Highways, Travel and the Environment through the TCF Council Governance Board (CGB), for approval of future TCF proposals, detailed programme delivery decisions and the detailed design of each element of the programme.
(c) Approves the principle of regular TCF update reports going to the CGB and from there to DfT as stipulated within point 8 of the award letter, with consideration of Traffic Regulation Orders (TROs) associated with the programme being considered in line with current Dorset Council approvals. Reason for Recommendation:
The delegations are designed to:
• Allow maximum flexibility in meeting the strict DfT timeline for delivery over the next three years, with appropriate Dorset Council approvals in place.
• Ensure that the authority is best placed to progress scheme delivery at the pace required to meet the funding profiles set by the DfT.
Executive summary
1.1A report was submitted to Cabinet in November 2019 outlining the Transforming Cities Fund (TCF) bid proposal and seeking to delegate authority for the submission of a TCF bid to the Department for Transport (DfT). Delegation was agreed at that Cabinet meeting and Dorset Council and BCP Council jointly submitted the Strategic Outline Business Case (SOBC) to DfT on 28th November 2019.
1.2On 11 March 2020 we were informed that we had been awarded the full, low ask. The DfT award letter is provided at Appendix 1. This provides a total of £79 million of external funding which has to be spent over a 4 year period with all delivery expected in years 2, 3 and 4.
1.3Delivering this amount of infrastructure over a three year period will be challenging and governance, assurance framework, project management and communications strategy are being set up to ensure that the project continues as planned.
1.4The DfT require an Assurance Framework to be in place and the South East Dorset TCF Assurance Framework sets out the policies, rules and processes to be applied throughout the TCF programme. The framework provides details of roles and responsibilities, policies and procedures, accounting arrangements, governance, stakeholder and public engagement, programme delivery and financial arrangements. A draft copy of the Assurance Framework has been submitted to the DfT for approval.
1.5Part of that governance, provided in Appendix 2, includes the creation of a Councils Governance Board (CGB) which will be attended by portfolio holders and key local members from both councils alongside senior officers. To ensure that the project can move forward at a pace which allows the DfT funding profile to be met, it is necessary to delegate authority for TCF related decisions to the CGB. 1.6 CGB members from Dorset Council are Cllr Ray Bryan, Cllr Mike Parkes, Cllr Rod Adkins and Jack Wiltshire, Head of Highways.
1.7Detailed decisions at the CGB will be informed by the TCF Assurance Framework.
1.8This delegated authority most importantly relates to decisions on spend within the overall £79 million budget as key scheme elements will frequently exceed a ‘key decision’ value of £500,000 which would require Cabinet approval were there to be no delegation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.