Decision (a) That the creation of a full business case to accelerate the deployment of full fibre and wireless / mobile connectivity predominately in the rural parts of the Dorset Council area, be supported; (b) That the Dorset Council budgetary commitment of up to £1m capital (from the Ringfenced Superfast Broadband budget) and revenue implementation commitment of £285k (funded from the Dorset Council Transformation fund) to leverage in external capital and commercial investment of up to £8.9m, be agreed; (c) That the commencement of the required public procurements be agreed; (d) That authority be delegated to the portfolio holder for Corporate Development, in consultation with the Executive Director of Place , to submit a full business case, procure and award services and enter into the necessary grant agreements to deliver this programme of activity; (d) That the unusually short timescales involved in developing these proposals, and the importance of responding and mobilising quickly to meet delivery deadlines to facilitate economic recovery from the impacts of the Coronavirus pandemic be noted. Reason for the Decision To enable the business case process to be submitted, complete due diligence and to facilitate the quickest possible deployment by March 2022.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
a) Supports the creation of a full business case to accelerate the deployment of full fibre and wireless / mobile connectivity predominately in the rural parts of the Dorset Council area. b) Subject to the bid to the LEP being successful, agrees the Dorset Council budgetary commitment of up to £1m capital (from the Ringfenced Superfast Broadband budget) and revenue implementation commitment of £285k (funded from the Dorset Council Transformation fund) to leverage in external capital and commercial investment of up to £8.9m c) Approves the commencement of the required public procurements d) Delegates authority to the portfolio holder for Corporate Development, in consultation with the Executive Director of Place, to submit a full business case, procure and award services and enter into the necessary grant agreements to deliver this programme of activity e) Notes the unusually short timescales involved in developing these proposals, and the importance of responding and mobilising quickly to meet delivery deadlines to facilitate economic recovery from the impacts of the Coronavirus pandemic.
Reason for recommendation
To enable the business case process to be submitted, complete due diligence and to facilitate the quickest possible deployment by March 2022.
Executive summary
The Secretary of State for Housing, Communities and Local Government wrote to Local Enterprise Partnership (LEP) chairs on 10 June 2020 inviting them to come forward with ideas for accelerating existing Government funded capital projects, to generate new activity within 18 months, to help create jobs and raise overall demand in the economy. The funding available is the Covid Recovery Infrastructure Fund and will be managed through LEPs.
In response to this, a business case is in rapid development for bringing multiple interventions together under one programme that will accelerate activity and close the digital connectivity gap, continuing progress in Dorset in the next 18 months or so, before the next major full fibre government intervention programme begins delivery during 2022 and beyond.
This report outlines progress to date, addresses high-level budget issues and seeks to delegate decisions to enable the work to progress against very tight timescales.
Financial implications
Capital Budget to March 2022
£k Description Notes 5,084 Capital requirement from Covid Subject to business case approval and actual Recovery Infrastructure Fund spend confirmed through procurement 2,000 (up to) Consumption of voucher capital Utilises Gigabit voucher scheme funds – actual (DCMS) value dependent on number of schemes developed (up to £3,500 per business, £1,500 per residential premise) 1,850 Estimated commercial investment from Infrastructure providers contribution confirmed infrastructure providers through procurement for hubs and for each scheme package agreed 1,000 (up to) Voucher top-up where required Where scheme costs are greater than the from Dorset Council capital sourced aggregate national voucher value (top up from underspend and claw-back capped at additional £2,500 per business, generated from Superfast Dorset £1,000 per residential premise). programme 9,934 Funded from Dorset Council Transformation (Max) total capital programme value fund.
£285 Additional project management and admin cost of running these projects to March 2022
Capital investment from Dorset Council of up to £1.285m will unlock and leverage in capital grant and inward investment from infrastructure suppliers of up to £8.649m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.