Place and Resources Scrutiny Committee agreed this item on Tuesday 21 September 2021. Below is the council's own wording, with the papers it was decided on.
It was agreed that councillors would be kept better informed, in order to be able to respond to questions and comments from the public · Representations had been made to MPs in respect of the pressures put on local councils during this time · As the service migrated to a single register, the level of manual checking would be reduced · The Head of Legal Services provided an overview of staffing and budget issues in the area In accordance with the Constitution, at this point in the meeting it was proposed by J Andrews seconded by D Shortell that the meeting continue beyond 3 hours. This was supported by the committee. · The Head of Legal Services provided information on the project plan for migration of the service to a single IT system · There was a need for timely and effective communications with the public and the Head of Legal Services would discuss this with the Communications Team · The Chairman requested that a further report be brought to the next meeting of the committee to provide an update on performance and response times · The Chairman also requested a further report to a future meeting of the committee about project governance and arrangements for the convergence of the land charges registers.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
Report Author: Grace Evans Title: Head of Legal Services Tel: 01305 225021 Email: [email protected]
Report Status: Public
Recommendation: Members are asked to note and comment on the current service position.
Reason for Recommendation: To provide Members with information about the current service, actions which have been taken and those which are planned.
1. Executive Summary 1.1 The Council is responsible for processing land charges search requests, which are commonly made as part of property purchases.
1.2The government has a target of a maximum of 10 working days within which these searches should be returned to applicants.
1.3This target date has not been achieved for the whole Dorset Council area since October 2020.
1.4Understandably, concerns have been raised and questions asked about how the delays have arisen, action taken to address the delays and future action to improve response times and return to the government target time. 1.5 The unexpected changes to the residential stamp duty threshold from 8 July 2020, generated a rapid, substantial and sustained increase in search numbers, at a time when the team had vacancies and while the service was migrating to a new ICT system.
1.6The Service has worked tirelessly to process the increased volume of searches. The Service has also undertaken several recruitments to employ additional permanent and temporary staff and has been supported by staff made available by other services. Further appointments have been made and staff will be joining the team in September, with the expectation that the larger team will continue to work through the backlog of searches and improve response times. Staff numbers will be monitored and further recruitment will be arranged if required.
1.7The new system is required to enable the systems and processes of former councils to be converged and harmonised, to enable maximum automation of search processing with seamless access within the system to relevant data from other services; a one council approach not just to land charges service, but all related services.
1.8The timescale for the migration was driven by the need to replace legacy land charges systems before they expired. They could not be extended as the systems would no longer be supported. Upgrades to newer versions of those legacy systems would have been required. This would have resulted in a continuation of four legacy systems, each entirely separate, with their own processes and without direct access to the data of other services which were being migrated to the new system. Data from other services must be included in searches. Proceeding with upgrades would have impacted the Council’s ability to process searches and created a greater risk of non-compliance and delay.
1.9At each stage of the phased migration the service and project team managing the migration have considered whether and when to proceed. Some migrations have been delayed to avoid a clash with a change in the stamp duty land tax threshold.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Housing delivery against targetsIt was agreed that Councillors Shortell, Tooke and Bartlett would meet to scope a potential review to cover the issue...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.