Decision of the Portfolio Holder for Planning That the following changes to the governance arrangements for Community Infrastructure Levy (CIL) be approved. (a) That Dorset Council uses the Infrastructure Funding Statement to update members on progress with developer contributions. The findings can also be reported in the quarterly finance reports. (b) That the principle of widening the scope of CIL spend beyond current geographical limits set by the charging areas is taken forward when Dorset Council adopt and implements a replacement single charging schedule across the Council. (c) That the infrastructure categories associated with habitat mitigation be removed from the scope of the next spending round. (d) That the categories and proportions for the remaining in-scope infrastructure be revisited following the completion of the next spending round. (e) That the measures to support “up front” engagement with town and parish councils including the measures to support greater awareness of developer contributions as set out in in the report to Cabinet 8 November 2021, be implanted as part of future spending rounds. Reason for the decision To ensure the delivery of important infrastructure to support growth and development. Executive Decision - Review of Community Infrastructure Levy (CIL) - Dorset Council
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
To approve changes outlined in paragraphs 11.4, 12.5, 13.11, 13.12, and 14.5 of this report relating to governance arrangements for Community Infrastructure Levy (CIL) expenditure following examination by Place & Resources Scrutiny Committee 13th July 2021 and Place & Resources Overview Committee 19 th October 2021.
Reason for recommendation
To ensure the delivery of important infrastructure to support growth and development.
Executive summary
The Community Infrastructure Levy (CIL) together with Planning Obligations (s106) represent additional sources of developer contribution funding to provide infrastructure or services necessary to enable or support development.
Governance arrangements for the expenditure of Community Infrastructure Funds collected by Dorset Council were approved by Cabinet in July 2020. Those arrangements have enabled approximately £3m of CIL funds to support 37 wide-ranging infrastructure projects across the Dorset Council area. To ensure the continued delivery of important infrastructure, a review of the approach to CIL expenditure has since taken place with both Place & Resources Scrutiny Committee and Place & Resources Overview Committee reviewing the arrangements to ensure that the right information is delivered in the right place at the right time.
The recommendations to and the findings of Place & Resources Overview Committee form the basis of this report.
Financial implications
The Community Infrastructure Levy (CIL) together with Planning Obligations (s106) represent additional sources of developer contribution funding to provide infrastructure or services necessary to enable or support development.
Such funding normally only represents a proportion of the total cost of the infrastructure, therefore additional funding, from other sources, may be required to deliver the infrastructure necessary.
Dorset Council recovers the cost of administering the Community Infrastructure Levy by top slicing 5% of each CIL payment. That income covers the cost of staff responsible for the collection and processing of the levy and associated systems and implementation costs. The governance arrangements require no additional corporate expenditure.
3. Well-being and Health Implications
Provision of infrastructure, which, for instance, facilitate cycling or walking or provide health facilities to support development’s future needs are important for individuals’ and communities’ wellbeing and contribute to healthier environments and support people’s health and wellbeing.
Climate implications
The use of CIL and s106 agreements to help provide supporting infrastructure commensurate with development is a key component in ensuring there are sustainable integrated spatial plans for housing, infrastructure, employment and the environment at the towns, suburbs and rural areas. This will also contribute to developing plans which bring together different sectors or local government departments to achieve shared objectives. Examples could include strategies which exploit the connections between active travel and public health. Without the necessary supporting infrastructure development would be less sustainable thereby having a corresponding effect on climate change.
5. Other Implications
Infrastructure which is necessary to make development acceptable in planning terms will have implications for, inter alia Sustainability; Property and Assets; Public Health, Community Safety and physical activity depending upon the nature of the development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.