Brit Valley Natural Flood Management Project

Approved Executive 1 paper

Cabinet approved this item on Tuesday 9 July 2024. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

That the project be approved, and the Executive Lead for Place enter into the funding agreement for both Phase 1 and Phase 2 via the scheme of delegation. Reason for the decision Funding had been secured externally and the project delivery would make a positive impact on the residents of Dorset. This contributed towards Dorset Council’s Plan 2022-2024 priorities of ‘protection of our natural environment, climate and ecology’ and ‘stronger, healthier communities’.
Word for word from the decision Dorset published for this meeting. Source: moderngov.dorsetcouncil.gov.uk

Follow this further

Built from Dorset's papers

What the report saysPro

Report to Cabinet

Cabinet 9 July 2024 Brit Valley Natural Flood Management Project

For Decision Cabinet Member and Portfolio: Cllr N Ireland, Leader of the Council

Local Councillor(s): Cllr Bridget Bolwell Cllr David Bolwell Cllr Sarah Williams Cllr Simon Christopher Cllr Neil Eysenck Cllr Craig Monks

Executive Director: Jan Britton, Executive Lead for Place

Report Author: Ian Rees Job Title: Dorset National Landscapes Countryside Projects Manager Tel: 01305 228235 Email: [email protected]

Report Status: Public (the exemption paragraph is N/A)

Brief Summary:

An offer for Phase 1 funding has been made by the Environment Agency to the Dorset National Landscape team to deliver a project in the Brit Catchment (covering all or part of Bridport, Eggardon, Beaminster and Marshwood Vale wards). Dorset National Landscape Partnership, hosted by Dorset Council, is asking Cabinet to accept this offer and approve securing Phase 2; allowing the Executive Lead for Place to sign the agreement under the scheme of delegation.

The project aim is to reduce flood risk to properties and flood defence maintenance costs in the area by 'natural' interventions higher in the catchment slowing the flow of water. A parallel monitoring programme will also evidence effectiveness. Activity timeline starts with installation of monitoring equipment (c£240k) by September 2024 to unlock second stage funding of c£433k to deliver a series of leaky dams, floodplain reconnection and land use changes by March 2027.

This project requires no Dorset Council funding; it is fully costed to deliver with the majority of funds (Phase 1 £235k; Phase 2 £389k) directly from the Environment Agency. The modest proportion of match will be provided by the partnership’s staff time (Phase 1) and landowner maintenance of flood management interventions (Phase 2). The budget includes income to cover input by Dorset Council's Flood Risk Management Team.

Recommendation: Cabinet approves the project and enables the Executive Lead for Place to enter into the funding agreement for both Phase 1 and Phase 2 via the scheme of delegation.

Reason for Recommendation: Funding has been secured externally and the project delivery will make a positive impact on the residents of Dorset.

This contributes towards Dorset Council’s Plan 2022-24 priorities of ‘protection of our natural environment, climate and ecology’ and ‘stronger, healthier communities’.

1. Report

1.1Project background

1.2The risk of flooding in the wider Brit Catchment is significant. Dorset Council’s Flood Risk Management Team have recorded 177 flooding incidences in the catchment between 1994 and 2023. There are also 816 properties at risk from surface water flooding.

1.3Over the past two years, Dorset National Landscape team has been working with the Environment Agency, an independent geomorphologist, and Dorset Wildlife Trust, to identify high-risk fields where runoff could cause problems and where sediment is being eroded. Dorset National Landscape team have also been working with landowners to identify opportunities to work with nature to overcome these issues. The aim is to reduce local flooding issues and stop sediment entering the rivers and ending up behind the flood defences in Bridport. This funding provides the opportunity to deliver on this research and engagement.

1.4Dorset Council’s Flood Risk Management Team along with Farming and Wildlife Advisory Group and Environment Agency are also interested in the risk posed by flooding and have been working on rural runoff projects over the past three years, which aim to tackle flooding in high-risk communities. This project aligns with this work.

1.5In late 2023, The Natural Flood Management Programme called for Expressions of Interest (EOI). The Natural Flood Management programme is a Department of Environment, Food, and Rural Affairs project, administered through the Environment Agency.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Brit Valley Natural Flood Management ProjectReport 335 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 66 attended
NI
Councillor Nick IrelandChair, present
RB
Councillor Richard BiggsVice-Chair, present
JA
Councillor Jon AndrewsCommittee Member, apologies
SB
Councillor Shane BartlettCommittee Member, present
SC
Councillor Simon CliffordCommittee Member, present
RH
Councillor Ryan HollowayCommittee Member, present
RH
Councillor Ryan HopeCommittee Member, present
SR
Councillor Steve RobinsonCommittee Member, present
CS
Councillor Clare SuttonCommittee Member, present
GT
Councillor Gill TaylorCommittee Member, present
RB
Councillor Ray BryanGuest, in attendance
PD
Councillor Peter DickensonGuest, in attendance

All 66 on the meeting page

More from Dorset Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 July 2026 (period 4) financial management report 26/27Decision (a) That the Senior Leadership Team’s forecast as of July 2026 including progress in addressing demand for s... Noted Open
8 Sep 2026 Additional Procurement Pipeline Report - over £500k (2026 - 27) and Modern Slavery Transparency Statement 2025 - 2026Decision (a) Cabinet considered the contents of the report (of 8 September 2026) in respect of proposed additional mo... Approved Open
8 Sep 2026 Exempt BusinessDecision That the press and the public be excluded for the following item(s) in view of the likely disclosure of exem... Decided Open
28 Jul 2026 Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ... Noted Open
28 Jul 2026 Dorset Local Visitor Economy Partnership Destination Management Plan(a) That the Dorset Local Visitor Economy Partnership Destination Management Plan (DLVEPDM) be adopted and (b) That a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies