Western and Southern Area Planning Committee approved this item on Thursday 12 December 2024. Below is the council's own wording, with the papers it was decided on.
That authority be delegated to the Head of Planning and Service Manager for Development Management and Enforcement to approve the application subject to planning conditions set out in the appendix to these minutes and if the revised NPPF has been published prior to the issuing of the planning decision not to issue the planning decision unless and until officers have agreed with the chair of the Western and Southern Area Planning Committee that there are no changes in the revised NPPF which could have led to members reaching a materially different conclusion on the application.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
Report to Western and Southern Area Planning Committee
P/FUL/2024/02884 Application Number: Webpage: Planning application: P/FUL/2024/02884 - dorsetforyou.com Site address: Redlands Community Sports Hub Dorchester Road Weymouth DT3 5AW Proposal: Refurbishment of existing floodlit Artificial Grass Pitch & construction of a new floodlit Artificial Grass Pitch. Erection of maintenance building with toilet, spectator area, new pedestrian perimeter path, relocation of practise cricket nets & new cricket match wicket. Construct reinforced grass matting overflow parking area and landscaping works. Applicant name: Active Dorset Case Officer: James Lytton-Trevers Ward Member(s): Cllr Northam
1.0Reason for committee determination The land the subject of the application is owned by Dorset Council. 2.0 Summary of recommendation: GRANT subject to conditions. 3.0 Reason for the recommendation: • Para 11 of the National Planning Policy Framework (NPPF) sets out that permission should be granted for sustainable development unless specific policies in the NPPF indicate otherwise. • The location is considered to be sustainable and the proposal is acceptable in its design and general visual impact. • There is not considered to be any significant harm to neighbouring residential amenity. • There are no material considerations which would warrant refusal of this application. 4.0 Key planning issues
Issue Conclusion Principle of development. The proposals would be compatible with the existing use of the site and bring enhancement to sport provision. Character and appearance of the area. The proposal would have limited intrusion in this location amongst existing similar facilities. Amenity of neighbouring properties. The design of the floodlighting and car park would be acceptable. Flood risk and drainage. Adequate methods would be provided to deal with drainage. Highway safety, access and parking. The proposal would not give rise to danger to road users. Trees and landscape. There would be suitable hard and soft landscaping within the development. Biodiversity. Suitable BNG can be provided and protected species would not be adversely affected. 5.0 Description of Site 5.1 The site is approximately 2 miles to the north of Weymouth and occupies a site of approximately 13.5 hectares, of which a substantial proportion is playing field. There are a number of buildings of which the largest is the Sports Centre containing two indoor sports halls, squash courts, several activity rooms, creche, café and changing rooms spread over two floors. Other small buildings located adjacent to the Sports Centre are used for storage and maintenance. There are two artificial grass pitches (AGP), one a hockey pitch located adjacent to the access road and the other a sports pitch located immediately north of the hockey pitch. There are two car parks, one located adjacent to the Sports Centre and the other adjacent to the existing artificial grass hockey pitch. These can accommodate 80 cars with 4 disabled spaces. The site is accessed from the Dorchester Road (B3159) via a single, two way access with pavement and which enters the main car park and then passes the Sports Centre to reach the second car park. There is also a large electricity substation in a cordoned area adjacent to the access road. There are currently 14 outdoor pitches for a variety of different sporting activity of which 2 are artificial grass.
5.2The land is almost flat with a nominal fall of 1m across the entire site and almost entirely laid to grass with a few standard trees lining the access road and the remaining boundaries are either unmanaged scrub, woodland or fencing. A line of tall conifers lies next to the electricity substation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Western and Southern Area Planning Committee at Dorset and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.