Western and Southern Area Planning Committee decided this item on Thursday 23 January 2025. Below is the council's own wording, with the papers it was decided on.
That authority be delegated to the Head of Planning and Service Manager for Development Management and Enforcement to grant planning permission subject to: 1. receiving written confirmation from the Marine Management Organisation that the parallel marine licencing application secures appropriate mitigation and compensation for marine ecology; and 2. the planning conditions outlined in the appendix to these minutes.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
Report to Western and Southern Area Planning Committee
P/FUL/2024/05538 Application Number: Webpage: https://planning.dorsetcouncil.gov.uk/ Site address: Weymouth Harbour, Weymouth, DT4 8AJ Proposal: Replacement and strengthening of harbour walls F and G through installation of new sheet pile walls in front of the existing walls, for the portion of the new wall where it is located above the mean low water mark, tie bar extension and ground works, works to the footpaths, creation of open space along with ancillary works. Applicant name: Dorset Council Case Officer: Matthew Pochin-Hawkes Ward Member(s): Cllr Orrell
1.0Reason application is going to committee:
1.1The applicant is Dorset Council.
2.0Summary of recommendation: 2.1 Delegate authority to the Head of Planning and Service Manager for Development Management and Enforcement to grant planning permission subject to: 1. receiving written confirmation from the Marine Management Organisation that the parallel marine licencing application secures appropriate mitigation and compensation for marine ecology; and 2. the planning conditions at section 18 of this report.
3.0Reason for the recommendation: • The proposed works subject to this planning application are located above the mean-low water mark where the Local Planning Authority has jurisdiction. The Marine Management Organisation has jurisdiction for works below the mean- high water mark. • Para. 11 of the NPPF establishes that permission should be granted for development proposals that accord with an up-to-date development plan without delay. • The existing sea defences are in urgent need of replacement. • The proposals would upgrade existing flood defences with necessary protection taking into account anticipated sea level rise and flood risks. • The design is acceptable, would not cause harm to heritage assets or the amenity of the area. • Remodelled and new open spaces would provide appropriate public amenity space and maintain panoramic views over the sea defences. • Public access would be improved through an updated pedestrian and cycle route around the perimeter of the site. • There are no material considerations which would warrant refusal of this application.
4.0Key planning issues Issue Conclusion Principle of development The replacement of existing sea defences and provision of improved open space and pedestrian/cycle route is wholly acceptable in principle and compatible with the area.
Design, landscape and local The proposals are compatible within the area and the character design and landscaping is acceptable subject to conditions.
Heritage Harm to designated heritage assets would be outweighed by public benefits and harm to non- designated heritage assets would be outweighed by the benefits of the proposal.
Amenity The proposals would not have a significant adverse impact on residential amenity. The new and improved public open spaces would improve public amenity within the local area.
Highways, access, parking and The proposals would not give rise to danger to road highway safety users or have severe highway impact. Construction traffic impacts can be appropriately managed via planning condition and the slight reduction in car parking-post construction is acceptable.
Ecology and biodiversity Biodiversity net gains would be delivered through on- site provision and the purchase of credits. Subject to mitigation and compensation being secured by the Marine Management Organisation through the parallel marine licencing application, impacts on marine ecology would be acceptable.
Flood risk and drainage The proposals would upgrade existing sea defences and would not cause increased risk of flooding elsewhere. Adequate drainage is proposed. Ground conditions Acceptable subject to conditions.
Environmental Impact The development is not considered to be EIA Assessment development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Western and Southern Area Planning Committee at Dorset and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.