Resolved
Grant the application as per the officer recommendation.
Strategic and Technical Planning Committee decided this item on Monday 27 January 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Grant the application as per the officer recommendation.
Officer Report
P/VOC/2024/07289 Application Number: Webpage: https://planning.dorsetcouncil.gov.uk/ Site address: Land south-east of Sunrise Business Park and north of the A350 Blandford Bypass, Blandford Forum. Proposal: Development of a waste management centre for the bulking and transfer of waste and recyclables, comprising a covered waste transfer station, with waste storage, sprinkler tank and pump house, and a split-level household recycling centre with vehicle unloading bays and partially covered central yard, a dedicated 're-use centre', WEEE storage building, office building, staff parking area, weighbridge and associated landscaping. Formation of new access from A350 (with variation of condition 3 of planning permission P/VOC/2022/06369 to allow archaeological and certain construction works to proceed concurrently). Applicant name: Dorset Council Case Officer: Tony Cosgrove Ward Member(s): Cllr Lacey-Clarke and Cllr Byron Quayle
Publicity Officer site 18/12/24 13 January 2025 expiry date: visit date:
Decision due 12 March 2025 Ext(s) of time: date:
No of Site Two Notices:
SN displayed reasoning:
1.0Reason application is going to committee
Under Para 134 of the Officer Scheme of Delegation states that, any application: • submitted by or on behalf of the Council and/or,
• when one or more town and/or parish councils in whose area the application is situated (in whole or part) have made a written representation relating to the application at least one of which has not been withdrawn at the time that the application Officer Report
is to be determined by committee.
2.0Summary of recommendation: Grant the application deleting pre-commencement Condition 3 and replacing it with a new condition to read: ‘Archaeology: prior to commencement of development an archaeological plan shall be produced in accordance with the AC General Site Recording Manual V2 (2012) and submitted to and approved in writing by the Waste Planning Authority. All archaeological preparation and recording shall be implemented in accordance with the approved management plan. The management plan shall include details on:
• Site preparation • Archaeological recording • Finds management • Reporting & monitoring process
Reason: To ensure the proper recording and preservation of features of archaeological merit and interest in accordance with Policy 19 of the Bournemouth, Christchurch, Poole and Dorset Waste Plan.
3.0Reason for the recommendation: This application seeks a minor amendment to facilitate the on-site archaeological examination and commencement of the proposal to construct a new Waste Management Centre in Blandford.
The existing condition was worded such that the development was only allowed to commence after all the archaeological work was completed. However, some areas of the site would not be subject to any archaeological work and others would have their archaeological works completed. Waiting for all the archaeological work to finish before any construction work can commence places a disproportionate burden on the applicant.
The new amended condition will allow work to commence in areas where: 1) archaeological digging has never been proposed; and, 2) in those areas where the archaeologists have finished their fieldwork.
The current planning permission requires development to commence before April 2025. It is possible this date could be missed because work cannot begin until all the archaeological work is complete. The current condition could result in the commencement of development being delayed (by years) adding significant costs to the project. The County Archaeologist is content with the amended condition and is satisfied it will protect the site in archaeological terms.
4.0Key planning issues Officer Report
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
P/VOC/2024/07289: Land south-east of Sunrise Business Park and north of the A350 Blandford Bypass, Blandford Forum.Report | 238 KB | DownloadRead as text |
Follow Strategic and Technical Planning Committee at Dorset and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Oct 2025 | P/VOC/2023/02551 - Lyme Regis Golf Club, Timber Hill, Lyme Regis, Dorset, DT7 3HQTo grant for ... view the full minutes text for item 27. | Decided | Open |
| 23 Sep 2025 | Declarations of InterestIt was agreed that she would take part in the debate and vote on the item. | Agreed | Open |
| 30 Jun 2025 | P/FUL/2025/00591 - Rainbarrow Farm, Monkey Jump Roundabout to Junction Below Alington Place, Martinstown, DT2 9JFTo grant for the reasons set out in Sections 16 and 17 of the officer’s report. | Decided | Open |
| 14 Mar 2025 | Application to divert part of Footpath 11, Compton Abbas at Compton Abbas AirfieldSubmit the Public Path Order for the diversion of part of footpath 11, Compton Abbas, to the Secretary of State and t... | Decided | Open |
| 17 Oct 2024 | Declarations of InterestIt was agreed that he would take part in the debate and vote as he would consider the application on its own merits, ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.