Western and Southern Area Planning Committee decided this item on Thursday 27 February 2025. Below is the council's own wording, with the papers it was decided on.
That authority be delegated to the Service Manager for Development Management and Enforcement and the Development Management Area Manager for the Southern and Western Team to grant planning permission subject to: 1. receiving written confirmation from the Marine Management Organisation that the parallel marine licencing application secures appropriate mitigation and compensation for marine ecology; and 2. the planning conditions set out in the appendix to these minutes.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
Site address: Weymouth Harbour, Weymouth, DT4 8AJ Proposal: Replacement and strengthening of harbour walls F and G through installation of new sheet pile walls in front of the existing walls, for the portion of the new wall where it is located above the mean low water mark, tie bar extension and ground works, works to the footpaths, creation of open space along with ancillary works.
Applicant name: Dorset Council
Case Officer: Matthew Pochin-Hawkes
Ward Member(s): Cllr Orrell
1.0Reason for Planning Committee Consideration 1.1 This application is being re-reported to planning committee due to proposed changes to planning conditions which were resolved at the 23 January 2025 Western and Southern Area Planning Committee.
2.0Summary of Recommendation 2.1 Delegate authority to the Service Manager for Development Management and Enforcement and the Development Management Area Manager for the Southern and Western Team to grant planning permission subject to: 1. receiving written confirmation from the Marine Management Organisation that the parallel marine licencing application secures appropriate mitigation and compensation for marine ecology; and 2. the planning conditions at Section 7 of this report.
3.0Background and assessment 3.1 At the 23 January 2025 Western and Southern Area Planning Committee Members resolved to grant planning permission for this application subject to planning conditions and receiving written confirmation from the Marine Management Organisation (MMO) that the parallel marine licencing application secures appropriate mitigation and compensation for marine ecology. The earlier Committee Report and Update Sheet is included at Appendix 1. 3.2 The January 2025 Committee Report noted at Paragraph 16.47 that a Habitat Management and Monitoring Plan (HMMP) would be required at the pre- commencement stage for Intertidal Green and Grey Infrastructure and that ongoing monitoring and management should be secured within a Section 106 Agreement. 3.3 Since the committee meeting, officers have explored securing the ongoing monitoring and management via a Section 106 Agreement (Unilateral Undertaking). However, as the applicant and Local Planning Authority is Dorset Council, colleagues in the Council’s legal team advise that a Unilateral Undertaking is not an appropriate mechanism for securing ongoing monitoring and management. 3.4 This report outlines the proposed alternative mechanism for securing ongoing monitoring and management via planning conditions. The report sets out a revised recommendation with two new planning conditions. 3.5 Unless otherwise stated, all other matters set out in the 23 January 2025 Committee Report and Update Sheet relating to: the description of the site, proposed development, planning history, constraints, relevant policies, human rights, public sector equalities duty, benefits and environmental implications remain unchanged. The report and Update Sheet are provided at Appendix 1 for ease of reference.
4.0Consultations 4.1 No further consultation has been carried out and no additional comments have been received.
5.0Material Planning Considerations 5.1 On 7 February 2025 MHCLG published an amended version of the NPPF. The amended version corrects cross-references from footnotes 7 and 8, and amends text at Paragraph 155 related to Green Belt development. The changes are not relevant to the determination of this planning application.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Western and Southern Area Planning Committee at Dorset and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.