Developer contribution funding for community facilities at Mampitts Green, Shaftesbury
AgreedExecutive2 papers
AI summaryDorset Council Cabinet extends s106 funding milestones for Shaftesbury community hub and allows up to 10% early drawdown from a £919,563 award.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedInformation deadline to 9 June 2026, on-site start to 9 July 2026
Money£919,563 s106 award, 10% early drawdownProject cost now estimated at £1.44m
What happens nextNew milestones: 9 June 2026 and 9 July 2026Further appraisal delegated to Head of Planning with Cabinet member
Who it affectsShaftesbury Town Council and local communityCommunity hub, café, office space, open space at Mampitts Green
What was decided
Cabinet extended the timescale condition for completing all required information to 9 June 2026 and the on-site commencement milestone to 9 July 2026. Report P6, P7
Cabinet approved provision for up to 10% of the £919,563 award to be drawn down early, to recover costs to date and fund design refinement. Report P9, P10, 3.16
Appraisal of further information and any transfer of funds or land is delegated to the Head of Planning in consultation with the Cabinet Member for Planning and Emergency Planning, with referral back to Cabinet if milestones are missed. Report P8, 3.14
Why
The Town Council has made partial progress against most conditions, with project costings and delivery requiring further work, including a quantity surveyor validation of build costs. Report 1.2, P20, P21
Estimated project cost has risen to £1.44m, an increase of around £0.5m since October 2024, and external grants and contributions are not yet secured. Report 3.7, 6.1
The Town Council has spent £27.8k and needs a further £58.3k to reach RIBA Stage 4 technical design, requiring early access to s106 funds to keep the project moving. Report 3.16
What happens next
Officers will continue to liaise with the Town Council and monitor progress against the new June and July 2026 milestones, with a main drawdown process to follow if suitable progress is made. Report 3.13, 3.17
If milestones are not met, the matter will be referred back to Cabinet for further consideration. Report P8
Early drawdown expenditure above the 10% allowance must be agreed in advance with Dorset Council and will be monitored. Report P10, 3.16
The money
£876,278 Original s106 award value approved on 15 October 2024 Report 1.1
£919,563 Current total s106 award value including accrued interest Report P9, 3.16, 6.1
£27.8k Cost incurred to date by Shaftesbury Town Council on the project Report 3.16
£58.3k Further investment needed to reach RIBA Stage 4 technical design
£1.44m Current estimated total project cost Report 3.7, 6.1
£0.5m Approximate increase in estimated cost since October 2024 Report 3.7
£45,000 Capital investment committed by the Town Council, around 3% of the budget Report 3.7
approximately £200,000 Further s106 funds for neighbourhood hall facilities identified by the Town Council Report P25
Options considered
Chosen: Extend milestones and allow up to 10% early drawdown. Increases flexibility to support delivery of community infrastructure while maintaining officer oversight Report 3.1, P4, P9
Rejected: Withdraw the funding offer. Would reset the s106 process, cause significant delay and increase build and associated costs, adding further delivery risks Report 4.1, P41
Implications
Financial: Total project cost has risen to £1.44m, with s106 funds now making up 65% of the budget and around 32% still to be secured from external grants or other contributions. Report 3.7, 6.1
Legal: Legal advice confirmed that officer delegation could consider material against conditions but could not change the conditions, milestones or funding amount, requiring this Cabinet decision. Report 5.1
Equalities: Officers identified no equalities implications, noting the proposal conforms to planning policy requirements established in 2007. Report 11.1
Climate: Long-term environmental impact is considered positive, with renewable energy technology and construction materials expected to reduce reliance on external power sources. Report 8.1, P45
Risk: Current and residual risk levels are identified as Medium and Medium/Low respectively. Report 10.1, P60, P61
Other: Progression depends on transfer of land from Persimmon Homes to Dorset Council initially. Report 9.1
Who and where
Shaftesbury Town Council, as s106 funding recipient and project lead Report 1.1, 3.1
Local community users of the proposed community hub, café, office space and open space at Mampitts Green, Shaftesbury Report 3.1, 7.1
Dorset Council, as fund holder and accountable body for the s106 agreement Report P10, 14.1
Persimmon Homes, which is to transfer the land to Dorset Council Report 9.1
Potential Dorset Council Family Hub users, if the first-floor family services proposal proceeds Report 7.1
Timeline
15 October 2024: Original Cabinet decision to award up to £876,278 of s106 funding to Shaftesbury Town Council, subject to conditions Report 1.1, 3.1, 13.1
15 April 2025: Original deadline for completion of all necessary information required by condition Report 3.3
15 October 2025: Original deadline for commencement of work on-site Report 3.3
9 June 2026: New extended deadline for completion of all necessary information required by condition Report P6
9 July 2026: New extended deadline for commencement of work on-site Report P7
Summer 2026: Indicative commencement date in the Town Council's project plan Report 3.11
Plain English for the jargon
s106: Section 106 of the Town and Country Planning Act 1990, used by councils to secure developer contributions toward local infrastructure and community facilities.
RIBA Stage 4: Technical Design stage in the Royal Institute of British Architects' plan of work, producing detailed drawings and specifications for tendering and construction.
Family Hub: A proposed Dorset Council service offering support for children, young people and families in a single location.
Early drawdown: Release of a portion of the s106 funding ahead of the agreed milestones, to recover costs already incurred and fund further design work.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item59
Resolved
Part 1 – That the previously set timescale milestone for the award of s106 funding to Shaftesbury Town Council, be extended as follows: (a) That the timescale condition requiring the completion of all necessary information required by condition, extended to 9 June 2026. (b) That the commencement of work on-site, extended to: 9 July 2026 That the appraisal of further information required by the conditions be agreed by the Head of Planning in consultation with the Cabinet Member for Planning and Emergency Planning, and any subsequent transfer of funds (and land) be made under the relevant officer delegation in accordance with the s106 protocol process. Failure to comply with either milestone extension would result in referral to Cabinet for further consideration. Part 2 – That provision for up to 10% of the current total award value of £919,563 be available for early drawdown prior to the new milestone deadlines, to support the recovery of costs to-date and future expenditure relating to the refinement of the design. Any further expenditure which required payment via the early draw down must be agreed in advance with Dorset Council. To ensure that the amount spent against the10% early drawdown was monitored and not exceeded. Reason for the decision To increase the level of flexibility in the award of s106 funding to Shaftesbury Town Council to support delivery of important community infrastructure at Mampitts Green, Shaftesbury.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
1.1On the 15th October 2024, Dorset Council Cabinet decided to award Shaftesbury Town Council up to £876,278 of s106 developer contribution funding for the purpose of building and operating a Community Hub and landscaped open space and recreational facilities at Mampitts Green, Shaftesbury. The award was subject to condition with the appraisal of further information required by condition delegated to the Head of Planning in consultation with the Cabinet Member for Planning and Emergency Planning.
1.2Since the award was agreed, the Town Council has been making progress towards satisfying the conditions, but several key conditions including those associated with budget and project delivery remain partially completed, therefore failing to meet in full the milestones that were set. Due to the nature of the issues raised through the appraisal of conditions, the matter has been referred to Cabinet by the delegated officer. This report provides an update on progress with the project, setting out the main findings of the appraisal of conditions. 1.3 One of the reasons for milestones not to have been reached has been the need to further develop and refine the design to be clearly costed. It is recognised that for a project of this scale and complexity, there needs to be financial investment in the preparation of detailed plans to help take the project forward. Key detail such as the clarification of build cost requires further design investigation and refinement. To date, the Town Council has invested £27.8k in the proposal and requires further investment of £58.3k to reach technical design stage (Royal Institute of British Architects (RIBA) Stage 4. With s106 funds being a key component of the overall budget, the situation requires there to be capability for an ‘early drawdown’ proportion of the award to be available to the Town Council to cover the costs associated with the work undertaken to date and with work required going forward.
1.4This report seeks to introduce amended milestones to support the progression of the project, along with provisions to enable early drawdown of a proportion of the award.
2. Recommendation(s)
2.1Part 1 - To extend the previously set timescale milestone for the award of s106 funding to Shaftesbury Town Council, as follows:
a) timescale condition requiring the completion of all necessary information required by condition, extended to: 9 June 2026
b) commencement of work on-site, extended to: 9 July 2026
That the appraisal of further information required by the conditions is agreed by the Head of Planning in consultation with the Cabinet Member for Planning and Emergency Planning, and any subsequent transfer of funds (and land) is made under the relevant officer delegation in accordance with the s106 protocol process. Failure to comply with either milestone extension would result in referral to Cabinet for further consideration.
Part 2 – To make provision for up to 10% of the current total award value of £919,563 to be available for early drawdown prior to the new milestone deadlines, to support the recovery of costs to-date and future expenditure relating to the refinement of the design.
Any further expenditure which requires payment via the early draw down must be agreed in advance with Dorset Council. To ensure that the amount spent against the10% early drawdown is monitored and not exceeded. 3. Reason for the recommendation(s)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.