Developer contribution funding for community facilities at Mampitts Green, Shaftesbury

Agreed Executive 2 papers

AI summaryDorset Council Cabinet extends s106 funding milestones for Shaftesbury community hub and allows up to 10% early drawdown from a £919,563 award.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedInformation deadline to 9 June 2026, on-site start to 9 July 2026
Money£919,563 s106 award, 10% early drawdownProject cost now estimated at £1.44m
What happens nextNew milestones: 9 June 2026 and 9 July 2026Further appraisal delegated to Head of Planning with Cabinet member
Who it affectsShaftesbury Town Council and local communityCommunity hub, café, office space, open space at Mampitts Green

What was decided

Cabinet extended the timescale condition for completing all required information to 9 June 2026 and the on-site commencement milestone to 9 July 2026. Report P6, P7

Cabinet approved provision for up to 10% of the £919,563 award to be drawn down early, to recover costs to date and fund design refinement. Report P9, P10, 3.16

Appraisal of further information and any transfer of funds or land is delegated to the Head of Planning in consultation with the Cabinet Member for Planning and Emergency Planning, with referral back to Cabinet if milestones are missed. Report P8, 3.14

Why

The Town Council has made partial progress against most conditions, with project costings and delivery requiring further work, including a quantity surveyor validation of build costs. Report 1.2, P20, P21

Estimated project cost has risen to £1.44m, an increase of around £0.5m since October 2024, and external grants and contributions are not yet secured. Report 3.7, 6.1

The Town Council has spent £27.8k and needs a further £58.3k to reach RIBA Stage 4 technical design, requiring early access to s106 funds to keep the project moving. Report 3.16

What happens next

Officers will continue to liaise with the Town Council and monitor progress against the new June and July 2026 milestones, with a main drawdown process to follow if suitable progress is made. Report 3.13, 3.17

If milestones are not met, the matter will be referred back to Cabinet for further consideration. Report P8

Early drawdown expenditure above the 10% allowance must be agreed in advance with Dorset Council and will be monitored. Report P10, 3.16

The money

  • £876,278 Original s106 award value approved on 15 October 2024 Report 1.1
  • £919,563 Current total s106 award value including accrued interest Report P9, 3.16, 6.1
  • £27.8k Cost incurred to date by Shaftesbury Town Council on the project Report 3.16
  • £58.3k Further investment needed to reach RIBA Stage 4 technical design
  • £1.44m Current estimated total project cost Report 3.7, 6.1
  • £0.5m Approximate increase in estimated cost since October 2024 Report 3.7
  • £45,000 Capital investment committed by the Town Council, around 3% of the budget Report 3.7
  • approximately £200,000 Further s106 funds for neighbourhood hall facilities identified by the Town Council Report P25

Options considered

  • Chosen: Extend milestones and allow up to 10% early drawdown. Increases flexibility to support delivery of community infrastructure while maintaining officer oversight Report 3.1, P4, P9
  • Rejected: Withdraw the funding offer. Would reset the s106 process, cause significant delay and increase build and associated costs, adding further delivery risks Report 4.1, P41

Implications

  • Financial: Total project cost has risen to £1.44m, with s106 funds now making up 65% of the budget and around 32% still to be secured from external grants or other contributions. Report 3.7, 6.1
  • Legal: Legal advice confirmed that officer delegation could consider material against conditions but could not change the conditions, milestones or funding amount, requiring this Cabinet decision. Report 5.1
  • Equalities: Officers identified no equalities implications, noting the proposal conforms to planning policy requirements established in 2007. Report 11.1
  • Climate: Long-term environmental impact is considered positive, with renewable energy technology and construction materials expected to reduce reliance on external power sources. Report 8.1, P45
  • Risk: Current and residual risk levels are identified as Medium and Medium/Low respectively. Report 10.1, P60, P61
  • Other: Progression depends on transfer of land from Persimmon Homes to Dorset Council initially. Report 9.1

Who and where

  • Shaftesbury Town Council, as s106 funding recipient and project lead Report 1.1, 3.1
  • Local community users of the proposed community hub, café, office space and open space at Mampitts Green, Shaftesbury Report 3.1, 7.1
  • Dorset Council, as fund holder and accountable body for the s106 agreement Report P10, 14.1
  • Persimmon Homes, which is to transfer the land to Dorset Council Report 9.1
  • Potential Dorset Council Family Hub users, if the first-floor family services proposal proceeds Report 7.1

Timeline

  • 15 October 2024: Original Cabinet decision to award up to £876,278 of s106 funding to Shaftesbury Town Council, subject to conditions Report 1.1, 3.1, 13.1
  • 15 April 2025: Original deadline for completion of all necessary information required by condition Report 3.3
  • 15 October 2025: Original deadline for commencement of work on-site Report 3.3
  • 9 June 2026: New extended deadline for completion of all necessary information required by condition Report P6
  • 9 July 2026: New extended deadline for commencement of work on-site Report P7
  • Summer 2026: Indicative commencement date in the Town Council's project plan Report 3.11

Plain English for the jargon

  • s106: Section 106 of the Town and Country Planning Act 1990, used by councils to secure developer contributions toward local infrastructure and community facilities.
  • RIBA Stage 4: Technical Design stage in the Royal Institute of British Architects' plan of work, producing detailed drawings and specifications for tendering and construction.
  • Family Hub: A proposed Dorset Council service offering support for children, young people and families in a single location.
  • Early drawdown: Release of a portion of the s106 funding ahead of the agreed milestones, to recover costs already incurred and fund further design work.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item59

Resolved

Part 1 – That the previously set timescale milestone for the award of s106 funding to Shaftesbury Town Council, be extended as follows: (a) That the timescale condition requiring the completion of all necessary information required by condition, extended to 9 June 2026. (b) That the commencement of work on-site, extended to: 9 July 2026 That the appraisal of further information required by the conditions be agreed by the Head of Planning in consultation with the Cabinet Member for Planning and Emergency Planning, and any subsequent transfer of funds (and land) be made under the relevant officer delegation in accordance with the s106 protocol process. Failure to comply with either milestone extension would result in referral to Cabinet for further consideration. Part 2 – That provision for up to 10% of the current total award value of £919,563 be available for early drawdown prior to the new milestone deadlines, to support the recovery of costs to-date and future expenditure relating to the refinement of the design. Any further expenditure which required payment via the early draw down must be agreed in advance with Dorset Council. To ensure that the amount spent against the10% early drawdown was monitored and not exceeded. Reason for the decision To increase the level of flexibility in the award of s106 funding to Shaftesbury Town Council to support delivery of important community infrastructure at Mampitts Green, Shaftesbury.
Word for word from the decision Dorset published for this meeting. Source: moderngov.dorsetcouncil.gov.uk

Follow this further

Built from Dorset's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1On the 15th October 2024, Dorset Council Cabinet decided to award Shaftesbury Town Council up to £876,278 of s106 developer contribution funding for the purpose of building and operating a Community Hub and landscaped open space and recreational facilities at Mampitts Green, Shaftesbury. The award was subject to condition with the appraisal of further information required by condition delegated to the Head of Planning in consultation with the Cabinet Member for Planning and Emergency Planning.

1.2Since the award was agreed, the Town Council has been making progress towards satisfying the conditions, but several key conditions including those associated with budget and project delivery remain partially completed, therefore failing to meet in full the milestones that were set. Due to the nature of the issues raised through the appraisal of conditions, the matter has been referred to Cabinet by the delegated officer. This report provides an update on progress with the project, setting out the main findings of the appraisal of conditions. 1.3 One of the reasons for milestones not to have been reached has been the need to further develop and refine the design to be clearly costed. It is recognised that for a project of this scale and complexity, there needs to be financial investment in the preparation of detailed plans to help take the project forward. Key detail such as the clarification of build cost requires further design investigation and refinement. To date, the Town Council has invested £27.8k in the proposal and requires further investment of £58.3k to reach technical design stage (Royal Institute of British Architects (RIBA) Stage 4. With s106 funds being a key component of the overall budget, the situation requires there to be capability for an ‘early drawdown’ proportion of the award to be available to the Town Council to cover the costs associated with the work undertaken to date and with work required going forward.

1.4This report seeks to introduce amended milestones to support the progression of the project, along with provisions to enable early drawdown of a proportion of the award.

2. Recommendation(s)

2.1Part 1 - To extend the previously set timescale milestone for the award of s106 funding to Shaftesbury Town Council, as follows:

a) timescale condition requiring the completion of all necessary information required by condition, extended to: 9 June 2026

b) commencement of work on-site, extended to: 9 July 2026

That the appraisal of further information required by the conditions is agreed by the Head of Planning in consultation with the Cabinet Member for Planning and Emergency Planning, and any subsequent transfer of funds (and land) is made under the relevant officer delegation in accordance with the s106 protocol process. Failure to comply with either milestone extension would result in referral to Cabinet for further consideration.

Part 2 – To make provision for up to 10% of the current total award value of £919,563 to be available for early drawdown prior to the new milestone deadlines, to support the recovery of costs to-date and future expenditure relating to the refinement of the design.

Any further expenditure which requires payment via the early draw down must be agreed in advance with Dorset Council. To ensure that the amount spent against the10% early drawdown is monitored and not exceeded. 3. Reason for the recommendation(s)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Mampitts: Accessible Impact Assessment & Table of RecommendationsAppendix A 140 KB Download
PDF
Developer contribution funding for community facilities at Mampitts Green, ShaftesburyReport 278 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 48 attended
NI
Councillor Nick IrelandChair, present
RB
Councillor Richard BiggsVice-Chair, present
JA
Councillor Jon AndrewsCommittee Member, present
SB
Councillor Shane BartlettCommittee Member, present
SC
Councillor Simon CliffordCommittee Member, present
RH
Councillor Ryan HopeCommittee Member, present
SR
Councillor Steve RobinsonCommittee Member, present
CS
Councillor Clare SuttonCommittee Member, present
GT
Councillor Gill TaylorCommittee Member, present
BW
Councillor Ben WilsonCommittee Member, present
PB
Councillor Piers BrownGuest, in attendance
SC
Councillor Simon ChristopherGuest, in attendance

All 48 on the meeting page

On this subject at Dorset

Search all
  1. Developer contribution funding for community facilities at Mampitts Green, ShaftesburyThis decision
  2. Allocation s106 developer contribution funding for community facilities at Mampitts Green ShaftesburyAgreed
  3. Recommendations for the allocation of developer contributions for enhancement of recreation and community infrastructure provision in DorchesterApproved
  4. A new way of securing developer contributions for NHS infrastructureApproved
  5. Response to (MHCLG) Consultation on proposed revisions to the National Planning Policy Framework and Supporting Housing Delivery through Developer ContributionsAgreed
  6. Allocation of developer contributions for enhancement of recreation provision in DorchesterApproved

More from Dorset Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 July 2026 (period 4) financial management report 26/27Decision (a) That the Senior Leadership Team’s forecast as of July 2026 including progress in addressing demand for s... Noted Open
8 Sep 2026 Additional Procurement Pipeline Report - over £500k (2026 - 27) and Modern Slavery Transparency Statement 2025 - 2026Decision (a) Cabinet considered the contents of the report (of 8 September 2026) in respect of proposed additional mo... Approved Open
8 Sep 2026 Exempt BusinessDecision That the press and the public be excluded for the following item(s) in view of the likely disclosure of exem... Decided Open
28 Jul 2026 Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ... Noted Open
28 Jul 2026 Dorset Local Visitor Economy Partnership Destination Management Plan(a) That the Dorset Local Visitor Economy Partnership Destination Management Plan (DLVEPDM) be adopted and (b) That a... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies