Harbour Budget and Setting of Fees and Charges 2026/27
ApprovedCommittee4 papers
AI summaryDorset Harbours Advisory Committee has recommended Cabinet ask Full Council to approve 2026/27 fees and charges and forecasted budgets for Bridport, Lyme Regis and Weymouth Harbours, with fees generally rising 3.4%.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRecommend Cabinet ask Full Council to approve 2026/27 fees and budgets
MoneySurpluses of £90,400 and £603,300Bridport £90,400 and Weymouth £603,300 surpluses forecast
What happens nextCabinet then Full CouncilRecommendation goes to Cabinet, then Full Council
Who it affectsThree Dorset harbours and usersBridport, Lyme Regis and Weymouth harbour users, fishermen and visitors
What was decided
The committee agreed to recommend that Cabinet ask Full Council to approve fees and charges for Bridport, Lyme Regis and Weymouth Harbours for 2026/27. Report P4, 2.1
The committee also agreed to recommend that Cabinet ask Full Council to approve the forecasted budget for all three harbours for 2026/27. Report P5, 2.1
Why
The Harbours Advisory Committee is responsible for informing Cabinet on the 2026/27 budget, reserve balances and proposed fees and charges for the three harbours. Report 3.1
A benchmarking exercise reviewed comparable harbours' fees, looking at annual mooring, visitor rates, commercial berthing and storage charges, to help set prices. Report 4.1, 4.2, 4.4, 4.5
Dorset Council has set a minimum expectation of a 3.4% increase, with specific Bridport, Lyme Regis and Weymouth fees held flat, including winter mooring, boat lifting, quayside parking, commercial fishing and visiting overnight stays. Report 5.1, 5.3, P25, P29, P30, P31, P34
What happens next
Cabinet will be asked to recommend the fees and the forecasted budget to Full Council for approval. Report 2.1
Budget assumptions on pay, inflation and shared services may still change in line with the council's budget setting timetable. Report 6.7, 6.8
A Water Injection Dredging trial at Bridport and Lyme Regis is ongoing and could reduce future maintenance dredging costs if successful, though no change has yet been made to the 2026/27 dredging budget. Report 7.6, 8.6, P61
The money
£90,400 Bridport projected surplus for 2026/27 Report 7.1
£603,300 Weymouth projected surplus for 2026/27 Report 9.1
£1,500,000 Weymouth Development and Projects spend 2026/27 Report P79
£1.48M Approved funding from Weymouth reserves for harbour walls F and G Report 10.9
£291,000 Bridport Asset Management Plan spend 2026/27 Report P74
£28,400 Lyme Regis Asset Management Plan spend 2026/27 Report P74
£364,000 Weymouth Asset Management Plan spend 2026/27 Report P74
£1.46 million Weymouth predicted year end forecast reserve Report 10.7
Implications
Financial: Bridport (£90,400) and Weymouth (£603,300) surpluses are forecast, while Lyme Regis is expected to operate on a cost neutral basis with no surplus in 2026/27. Report 7.1, 8.1, 9.1, 10.6
Financial: Most fees would rise by 3.4%, with several held flat; larger increases are proposed for annual and summer vessel storage (+£30 per meter), launch and recovery (+20%) and Weymouth fishermen's storage (from £2.15 to £5.00 per pallet per month). Report 5.1, 5.3, P26, P29, P36
Financial: Most existing reserves are committed to planned investment, with £1.48M approved for harbour walls F and G and a partial Peninsular car park closure forecast to affect Weymouth 2026/27 income. Report 9.2, 10.2, 10.3, 10.9
Financial: Forecasts assume a 3.2% pay award, electricity cost rises of 7% and water and fuel cost rises of 3.4%, with a general 3.4% inflationary increase where appropriate. Report P43
Legal: The report has been reviewed and signed off by the Monitoring Officer and Section 151 Officer, confirming compliance with legal and financial regulations. Report 12.1, 21.1
Risk: The level of risk associated with this decision has been identified as Low for both current and residual risk. Report 17.1, P100, P101
Equalities: There are no equalities implications arising from the report. Report 18.1
Climate: Future harbour budgets will be used to consider how carbon output can be minimised and operations made more sustainable. Report 14.1
Who and where
Recreational boaters and mooring holders at Bridport, Lyme Regis and Weymouth harbours Report 4.6, 4.7, P26, P28
Commercial fishing and berthing operators at the three harbours Report 4.8, P31
Local fishermen using storage and overnight facilities, especially at Weymouth Report 4.9, P18, P36
Slipway users and quayside parkers at Bridport and Lyme Regis Report P27, P29, P30
Harbour Consultative Group and Harbours Advisory Group stakeholders Report 16.1
Timeline
2025-12-03: Harbours Advisory Committee considered the report and agreed the recommendation.
2026/27: Proposed fees and charges and forecasted budgets would apply for the 2026/27 financial year, subject to Full Council approval. Report P4, P5
2026/27: Final transfer of the £1.48M funding for harbour walls F and G repairs from Weymouth reserves is scheduled. Report 10.9
2026/27: Partial closure of the Peninsular car park in Weymouth for harbour walls F and G works is forecast to impact income. Report 9.2
Plain English for the jargon
Section 151 Officer: The local authority officer with statutory responsibility for financial administration and proper accounting.
Asset Management Plan: A planned schedule of maintenance and replacement spend on harbour infrastructure over future years.
Water Injection Dredging: A dredging technique being trialled at Bridport and Lyme Regis that could reduce maintenance dredging costs.
Harbour walls F and G: Specific walls at Weymouth Harbour scheduled for repair, with funding approved from Weymouth reserves.
Harbour Consultative Group: A group consulted on harbour issues, alongside the Harbours Advisory Group.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item148
Resolved
That the Harbours Advisory Committee recommend that Cabinet asks Full Council to 1. Approve fees and charges for Bridport, Lyme Regis and Weymouth Harbours for 2026/27. 2. Approve the forecasted budget for Bridport, Lyme Regis and Weymouth Harbour for 2026/27
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
1. The purpose of the report is to set out the budget and the predicted balance of harbour reserves for Bridport, Lyme Regis, and Weymouth Harbours for 2026/27. This requirement includes setting fees and charges for all harbours. The financial summaries are given in the appendices.
2. Recommendation(s)
2.1That Cabinet asks Full Council to
1. Approve fees and charges for Bridport, Lyme Regis and Weymouth Harbours for 2026/27.
2. Approve the forecasted budget for Bridport, Lyme Regis and Weymouth Harbour for 2026/27 .
3. Reason for the recommendation(s)
3.1The Harbours Advisory Committee is responsible for informing Cabinet on the 2026/27 budget, reserve balances and proposed fees and charges for Bridport, Lyme Regis and Weymouth Harbours.
4. Fees and charges 2026/27
4.1The harbours have carried out a bench marking exercise to assist with reviewing fees and charges.
4.2Benchmarking provides a good starting point; however, consideration must also be given to the differing facilities and services on offer and historic price increases. Over the past three years, most harbour fees have increased by between 5% and 7.5%.
4.3We need to ensure we have confidence that any price increase reflects the service provision and facilities we offer.
4.4For Weymouth the bench marking focused on four key areas: annual recreational mooring fees, rates for visiting vessels, commercial berthing charges, which included charges levied for storage
4.5Some key points from benchmarking that need to be considered when evaluating pricing strategy are:
4.6Annual mooring fees for recreational craft: We remain competitively priced, with fees generally lower than those charged by comparable harbours. However, it is important to acknowledge that our facilities are not of the same standard or quality as those found in higher-priced locations.
4.7Current rates for visiting recreational vessels are slightly above average and over the past three years, price increases for these visitors have risen more sharply than those applied to our other fees. Our visitor berths are typically offered alongside or rafted, whereas many competing harbours provide dedicated marina-style berthing at comparable rates. This difference in berth type may impact perceived value and visitor experience.
4.8Annual commercial fees are slightly higher than those at some comparable harbours. However, unlike certain other locations, we do not levy separate harbour dues. This means that while headline fees may appear higher, the overall cost to commercial users remains competitive when considered in full.
4.9Weymouth harbour provides a substantial amount of dedicated storage space for local fishermen to safely store their gear. This provision plays a vital role in .
maintaining clear and safe working conditions on the pontoons. During our benchmarking exercise, we found that many other ports and harbours do not offer similar storage facilities. Among those that do, the associated charges are significantly higher than those currently applied at Weymouth.
5 Pricing recommendations for 2026/27:
5.1Dorset Council has set a minimum expectation of a 3.4% increase in fees and charges. It is proposed that in general, this is applied across all three harbours.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.