AI summaryDorset Council Cabinet approved £2m from the climate capital programme for solar PV (£700k) and LED street lighting (£1.3m), with delegated authority for further spend on the remaining £1.4m.
Written from the decision and the officer reportPDF Pro
OutcomeApproved£700k solar PV, £1.3m LED street lighting
Money£2m approved, £1.4m delegatedFrom £4m remaining climate capital
What happens nextOfficers to procure and deliverDirector signs off further items
Who it affectsCouncil estate and street lightingUp to 4,000 lanterns and 2.25MW solar
What was decided
Cabinet approved £700k for the next phase of solar PV across the council's estate, and £1.3m for replacing more old, obsolete street lighting with LEDs using the PFI contract. Report 1.1, 3.4, 3.5
Authority was delegated to the Corporate Director for Strategy, Performance and Sustainability, in consultation with the Leader and Cabinet Member for Climate, Performance and Safeguarding, to approve further individual item spend within the remaining climate capital allocation. Report 1.2, 2.2
Why
There is £4m remaining in the climate capital programme for 2025 to 2027, and two workstreams within it require spend above the £500k cabinet approval threshold, totalling £2m. Report 1.3, 2.1, 6.1
Approving these projects keeps the council on its decarbonisation trajectory to 2035 and delivers invest to save reductions in carbon and energy costs. Report 4.1, P20, P21
What happens next
The next phase of solar PV is ready for procurement and the LED street lighting upgrade will be added to the existing PFI provider's programme, with up to 4,000 lanterns replaced over 2026 to 2027. Report P17, P21, P24
The Corporate Director will approve further individual items of spend within the remaining £1.4m of climate capital, covering energy efficiency, EV infrastructure, low carbon grants and small solar upgrades. Report 2.2, 6.5
The money
£10 million Capital allocated in 2022/23 budget for climate programme 2022 to 2027 Report P1, 6.1
£6 million Spent to date on the climate programme Report 1.2, 3.2
£4m Remaining climate capital allocation for 2025 to 2027 Report 1.3, 2.1, 6.1
£700k Approved for the next phase of solar PV across the council estate Report 1.1, 3.4
£1.3m Approved for LED street lighting upgrade via the PFI contract Report 1.1, 3.5, P21
£2 million Total of the two over £500k workstreams Report 2.1, 6.2
£2.35m Total cost of the wider solar PV programme delivering 2.25MW Report P17
£1.65m Additional solar funding approved by Cabinet in March 2025 Report P18
£6.025 million Additional capital allocated by Cabinet in March 2025 to accelerate climate programmes Report P18, 6.6
£600k Approved in February 2023 to match fund the LEVI programme Report 6.4
£1.4m Remaining climate capital falling under the £500k threshold Report 6.5
£115k/yr Estimated annual energy cost saving from LED upgrades Report P34
425,000 kWh Estimated annual electricity saving from LED upgrades Report P34
£70k/yr Estimated annual energy cost saving from the £700k solar PV allocation, with potential export income Report P35
330,000 kWh Estimated annual electricity saving from the £700k solar PV allocation Report P35
Options considered
Rejected: No action. Would significantly impact the council plan priority of decarbonising council operations by 2035 and forgo associated savings and income Report 4.1
Rejected: Partial funding. Current investments are required to keep the council on its required decarbonisation trajectory and use the £10m for its original purpose Report 4.2
Rejected: Seek alternative sources of capital. Alternative sources of funding are continuously explored but no viable alternatives have been found Report 4.3
Implications
Climate: LED upgrades are estimated to cut approximately 82 tonnes of CO2 per year, and the £700k solar PV share is estimated to cut approximately 64 tonnes of CO2 per year. Report 7.2
Financial: LED upgrades are forecast to save around £115k per year in energy costs, and the solar PV share is forecast to save around £70k per year, with potential export income. Report P34, P35
Legal: Legal and procurement elements of the next phase of solar installations have been considered and the scheme is on the procurement forward plan; LED work can be awarded to the current supplier Enerveo under the existing PFI. Report 5.1, 5.2
Risk: Current risk is identified as high, residual risk as medium; non-delivery would damage the council's reputation and leadership in this area. Report P46, P47, 10.2
Equalities: The IPCC and Climate Change Committee have highlighted the disproportionate impact of climate change on vulnerable people; a Dorset specific scoping exercise is under way. Report 11.1
Who and where
Dorset Council estate buildings receiving new solar PV installations Report 3.4, P17
Road users and residents served by approximately 4,000 upgraded street lanterns Report P21, P34
Dorset Council, which will own the legacy street lighting asset again after the PFI contract ends in 2032 Report P22, P23
Dorset organisations eligible for low carbon grants from the remaining £1.4m allocation Report 6.5
Vulnerable residents identified as disproportionately affected by climate change Report 11.1
Timeline
2022/23: £10 million capital allocated in the Dorset Council budget to deliver the climate programme Report P1, 6.1
2022 to 2027: Five year capital delivery period for the climate programme Report 3.1, 6.1
2025-2027: Remaining £4m climate capital allocation period Report 1.3, 3.3, 6.1
September 2025: Council's street lighting policy adopted, which the LED work aligns with Report 1.1
2026-2027: Accelerated two year period for replacing up to 4,000 obsolete street lighting lanterns via the PFI contract Report P21
2032: End of the PFI street lighting contract, after which Dorset Council again owns the full street lighting asset Report P22, P23
Plain English for the jargon
PFI contract: Private Finance Initiative contract, here the existing street lighting contract with provider Enerveo under which capital works can be added
LED: Light Emitting Diode, a more energy efficient type of street lighting than older lamp technology
Solar PV: Solar Photovoltaic panels that generate electricity from sunlight
LEVI: Local Electric Vehicle Infrastructure, a programme for public electric vehicle charge points
Decarbonisation: Reducing or removing carbon emissions, here from the council's own operations, with a target year of 2035
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item24
Resolved
(a) That the spend from the corporate climate capital programme for those elements identified as over £500k, as set out in the report to Cabinet or 29 January 2026, be approved. Specifically: (i) £700k for the installation of the next phase of solar PV across the council’s estate, and (ii) £1.3m for replacement of more old, obsolete street lighting with LED street lighting using the PFI contract and in line with the Council’s street lighting policy adopted September 2025. (b) That authority be delegated to the Corporate Director for Strategy, Performance and Sustainability in consultation with the Leader and Cabinet Member for Climate, Performance and Safeguarding, to approve further individual item spend within the remaining climate capital allocation, for the identified projects. Reason for the Decision There is £4m remaining in the climate capital programme. Two workstreams allocated within the current climate capital programme had identified the requirement for spend above the £500k cabinet approval threshold, with the total of these amounting to £2m. Delegating approval for the further spend within the remaining allocation would allow the projects outlined in the report to proceed.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
Dorset Council allocated £10 million capital in the 2022/23 Dorset Council budget to deliver the council’s Natural Environment, Climate and Ecology Strategy between 2022-2027. This was primarily focused on reducing the council operational carbon footprint.
1.2To date approximately £6 million of this capital allocation has been spent on a wide range of projects reported to Place and Resources Scrutiny committee as part of the Natural Environment, Climate and Ecology Strategy 2023 to 25 Refresh - Dorset Council progress reports What's happened so far - Dorset Council
1.3The remaining £4m allocated for 2025-2027 includes two workstreams that require expenditure above the £500k threshold and therefore require Cabinet approval. These are additional LED street lighting upgrades based on the new policy position and part funding for the next phase of solar installations on council buildings. V2/25
1.4This paper seeks approval for these projects and delegated authority to approve the spend on the remainder of the allocated capital for these project areas.
1. Recommendation(s)
1.1That cabinet approves the spend from the corporate climate capital programme for those elements identified as over £500k, as set out in this paper. Specifically- • £700k for the installation of the next phase of solar PV across the council’s estate, and • £1.3m for replacement of more old, obsolete street lighting with LED street lighting using the PFI contract and in line with the Council’s street lighting policy adopted Sep 2025.
1.2That cabinet delegate authority to the corporate director for Strategy, Performance and Sustainability in consultation with the Leader and Cabinet member for Climate, Performance and Safeguarding, to approve further individual item spend within the remaining climate capital allocation, for the identified projects.
2. Reason for the recommendation(s)
2.1There is £4m remaining in the capital programme for workstreams supporting the council’s climate objectives. Two workstreams allocated within the current climate capital programme have identified the requirement for spend above the £500k cabinet approval threshold, with the total of these amounting to £2m.
2.2The delegation in paragraph 2.2 to approve further individual items of spend within the remaining capital allocation will enable projects described in paragraph 7.5 of this report to proceed.
3. The report
3.1Dorset Council allocated £10 million capital in the 2022/23 Dorset Council budget to deliver the council’s climate change programmes between 2022- 2027. This was to deliver the council’s Natural Environment, Climate and Ecology programme and was allocated to a number of workstreams such as – energy efficiency and renewable energy projects on council buildings, developing an electric vehicle charging infrastructure across our estate, purchase of electric vehicles for our pool and operational fleet, installing LED lamps in Dorset streetlights and supporting external programmes such as Low V2/25
Carbon Dorset, Healthy Homes Dorset and public electric vehicle charging infrastructure.
3.2Progress against this capital programme and the council’s Natural Environment, Climate and Ecology strategy is reported bi-annually to Place and Resources Scrutiny Committee and to the public What's happened so far - Dorset Council. To date approximately £6m of this allocation has been spent.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.