P/LBC/2025/05844 - Lyme Regis Harbour, The Cobb, Lyme Regis, DT7 3JJ

Decided Planning 1 paper

AI summaryDorset Council's Western and Southern Area Planning Committee has granted listed building consent for emergency repairs to The Cobb at Lyme Regis, including filling a void with marine concrete.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to conditions set out in the appendix
MoneyNot stated
What happens nextWorks must begin within three yearsOr the consent expires
Who it affectsThe Cobb, Lyme RegisGrade I listed historic harbour structure

What was decided

Listed building consent was granted for the repair works, subject to the conditions set out in the appendix to the minutes. Report 15.1

Why

The conditions require the work to begin within three years and to be carried out in accordance with the approved plans, to preserve the architectural and historical qualities of the building. Report P2, P3, P4, P5, P6

A further condition requires strict adherence to the Design and Method Statement produced by the council, to preserve the special interest of the heritage asset and prevent harm to it. Report P7, P8

What happens next

The works must follow the approved location map and three outline design sheets for the emergency repairs. Report P5

The works must be carried out in strict accordance with the Design and Method Statement by Sean Norsworthy, Dorset Council, dated 3 October 2025. Report P7

A note states the decision only covers listed building consent and does not grant planning permission or confirm the works would be permitted development. Report P9

Options considered

  • Chosen: Grant listed building consent subject to conditions. Standard conditions imposed to preserve the heritage asset Report 15.1, P2, P3, P4, P5, P6, P7, P8

Implications

  • Legal: The consent must be implemented within three years or it will expire, as required by Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990. Report P2, P3
  • Other: The decision only covers listed building consent and does not grant planning permission for the proposed works. Report P9

Who and where

  • The Cobb at Lyme Regis, a designated heritage asset Report P8
  • Dorset Council as applicant Report P7

Timeline

  • 3 October 2025: Design and Method Statement produced by Sean Norsworthy, Dorset Council Report P7
  • 29 January 2026: Listed building consent granted by the Western and Southern Area Planning Committee
  • Within three years of the grant of consent: Work to which the consent relates must be begun Report P2

Plain English for the jargon

  • Listed building consent: Permission required for works to a building that is on the statutory list of buildings of special architectural or historic interest.
  • The Cobb: A historic curved harbour wall at Lyme Regis, a designated heritage asset.
  • Haki steps: Temporary modular access steps made from standard scaffold components.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item57

Resolved

That the application be granted subject to the conditions set out in the appendix to these minutes.
Word for word from the decision Dorset published for this meeting. Source: moderngov.dorsetcouncil.gov.uk

Follow this further

Built from Dorset's papers

What the report saysPro

Report to Western and Southern Area Planning Committee

Application Number: P/LBC/2025/05844 Site address: Lyme Regis Harbour The Cobb Lyme Regis DT7 3JJ Proposal: Repair to void under The Cobb by filing with marine concrete and repair to damaged/destroyed concrete toe. Erection of temporary counterbalance scaffold and Haki steps Applicant name: Adam Steele Case Officer: Eve Van der Steen Ward Member(s): Cllr Bawden

1. Reason application is going to committee:

This application has been brought to committee as the structure to which the application relates is owned by Dorset Council and Dorset Council is also the applicant.

2. Summary of recommendation:

GRANT subject to conditions as set out at the end of this report. 3. Key issues

Issue Conclusion

Impact on Heritage Asset, Setting and No adverse impact. Conservation Area.

4. Description of site

4.1The Cobb is a monolithic sea wall of medieval origins which contains the harbour at Lyme Regis. It is grade I listed and provides some defence of the town against the effects of coastal erosion and storm damage. The Cobb shelters the harbour, a working fishing port. 4.2 The part of the Cobb to which this application relates is the base of the outer face of the area locally known as the ‘Ginshop Turn’. This is the curved section of walling between the High Wall and the Southern Arm, as indicated on the plan within the submitted Design and Access Statement. 4.3 The Cobb is built of various types of stone, but the outer face of the area to which this application relates is of massive, squared blocks thought to date from an 18th or 19th century phase of repairs and rebuilding. 5. Description of development

5.1These emergency works seek to repair a section of deep voiding beneath the Cobb and advanced stage deterioration of the structure’s concrete toe. This work involves the infilling of the void with marine concrete and the repair and reinstatement of the failed concrete toe. 6. Background and relevant planning history

WD/D/17/001111 - Decision: RESPONDED Decision Date: 15/06/2017 Pre-Application Consultation - Installation of cylindrical steel piles for the permanent anchoring of pontoons

WD/D/20/001420 - Decision: GRANT Decision Date: 17/12/2020 Extension and repairs to existing slipway and extension of existing boat storage

1/W/03/001935 - Decision: WITHDRAWN Decision Date: 28/11/2003 Erect extension to existing rock armour

1/D/10/001057 - Decision: GRANT Decision Date: 23/09/2010 Fix 3 hardwood timber fenders

P/ESC/2021/03181 - Decision: EIA Decision Date: 27/09/2021 EIA Screening Opinion - Lyme Regis Structures and Breakwater Improvements.

P/ESP/2021/03192 - Decision: SCOPED Decision Date: 29/10/2021 EIA Scoping Opinion - Lyme Regis Structures and Breakwater Improvements.

7. List of constraints

Grade I Listed Building: The Cobb Piers and Walls, Including North Wall: HE Reference: 1229437 (statutory duty to preserve or enhance the significance of heritage assets under the Planning (Listed Buildings & Conservation Areas) Act 1990).

Grade II Listed Building: Buildings on the Cobb Pier occupied by Lyme Regis Sailing Club HE Reference: 1279078 ((statutory duty to preserve or enhance the significance of heritage assets under the Planning (Listed Buildings & Conservation Areas) Act 1990).

Within the Lyme Regis Conservation Area (statutory duty to preserve or enhance the significance of heritage assets under the Planning (Listed Buildings & Conservation Areas) Act 1990).

8. Consultations

All consultee responses can be viewed in full on the website.

Consultees

1. Lyme Regis Town Council - The town council supports the emergency works to maintain the integrity of the Cobb structure. 2. Lyme Regis Ward Member– no comments received.

3. Historic England – No comment: Historic England provides advice when our engagement can add most value. In this case we are not offering advice.

4. National Amenity Societies – no comments received.

Representations received – None.

9. Duties

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P/LBC/2025/05844: Lyme Regis Harbour, The Cobb, Lyme Regis, DT7 3JJReport 115 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 36 attended
DB
Councillor Dave BolwellChair, present
NE
Councillor Neil EysenckVice-Chair, present
BB
Councillor Belinda BawdenCommittee Member, apologies
MB
Councillor Matt BellCommittee Member, present
SC
Councillor Simon ChristopherCommittee Member, present
PK
Councillor Paul KimberCommittee Member, present
CM
Councillor Craig MonksCommittee Member, present
DN
Councillor David NorthamCommittee Member, present
LO
Councillor Louie O'LearyCommittee Member, present
PR
Councillor Pete RoperCommittee Member, present
DS
Councillor David ShortellCommittee Member, present
KW
Councillor Kate WhellerCommittee Member, apologies

All 36 on the meeting page

On this subject at Dorset

Search all
  1. P/LBC/2025/05844 - Lyme Regis Harbour, The Cobb, Lyme Regis, DT7 3JJThis decision
  2. P/LBC/2023/00767 The Town Mill, Mill Lane, Lyme Regis, DT7 3PUDecided
  3. P/LBC/2021/03958 - Gun Cliff SPS, Bridge Street, Lyme RegisDecided

More from Dorset Western and Southern Area Planning Committee

All decisions
MeetingDecisionOutcome
10 Sep 2026 Declarations of InterestIt was agreed that she would speak as the Local Ward Member and would not take part in the debate or vote. Cllr Louie... Agreed Open
10 Sep 2026 P/FUL/2026/01894 - 13 The Esplanade, Weymouth, DT4 8EBTo grant for the reasons set out in Section 15 of the officer’s report. Decided Open
10 Sep 2026 P/LBC/2026/01893 - 13 The Esplanade, Weymouth, DT4 8EBTo grant for the reasons set out in Section 15 of the officer’s report. Cllr Peter Dickenson returned at 10:25 Decided Open
10 Sep 2026 P/FUL/2026/00983 - Former Vehicle Maintenance Building, Sec Depot & Southern Electric Depot, Westwey Road, WeymouthTo grant for the reasons set out in Section 17 of the officer’s report. Decided Open
15 Jul 2026 P/FUL/2025/06223 - Pavement opposite 32 The Esplanade, WeymouthThat the application be refused for the reasons set out in the appendix to these minutes. Refused Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies