P/HOU/2025/04198, Linden Grove Manor Road Gussage St Michael BH21 5HX.
DecidedPlanning1 paper
AI summaryPlanning permission granted for two-storey extensions and porch at a home in Gussage St Michael, with conditions including a swift box for biodiversity gains.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedTwo-storey front and side extensions, raised ridge, porch
MoneyNot stated
What happens nextBuild within three yearsAlso install swift box before first use
Who it affectsA dwelling in Gussage St MichaelAlso neighbours and local ecology
What was decided
The committee granted planning permission subject to the conditions in the officer's report, plus an additional condition requiring a swift box to be installed before first use and kept thereafter. Report P1
An additional condition was added requiring one swift box on the site before first use, retained thereafter, to provide biodiversity gains.
Why
Conditions are imposed to safeguard neighbour privacy through obscure glazing, to ensure the development follows the approved plans, and to require a start within three years. Report P3, P5, P8, P9
A biodiversity condition is needed to mitigate and compensate for ecological impacts and to deliver biodiversity gains, supported by a plan certified by the council's Natural Environment Team on 15/10/2025. Report P6, P7
What happens next
The development must begin no later than the expiration of three years from the date of permission. Report P2
Before first use, obscure glazing must be fitted to bathroom and ensuite windows on the north, south and west elevations, and one swift box must be installed and retained. Report P8
The approved Biodiversity Plan must be completed in full, with photographic evidence supplied to the council, and a separate European Protected Species or Low Impact Class Licence may still be required. Report P6, P10, P11
Options considered
Chosen: Grant planning permission subject to conditions plus an added swift box condition. Recommended by officers and adopted by the committee with the additional biodiversity condition. Report P1
Implications
Legal: Planning permission does not guarantee an EPS or Low Impact Class Licence, which is a separate process and the applicant's own responsibility. Report P10
Legal: Without the required licence the applicant could commit an offence under the Conservation of Habitats and Species Regulations (2017) (as amended). Report P10
Equalities: Obscure glazing on north, south and west bathroom and ensuite windows is required in perpetuity to protect neighbour privacy. Report P8, P9
Climate: A Biodiversity Plan certified on 15/10/2025 must be carried out, with mitigation, compensation and enhancement measures permanently maintained. Report P6, P7
Risk: Failure to follow the approved plans or Biodiversity Plan would be a breach of condition. Report P5, P6
Who and where
The applicant at Linden Grove, Manor Road, Gussage St Michael BH21 5HX Report P4, P10
Occupiers of adjoining residential property Report P8, P9
Protected species and local ecology on and near the site Report P6, P7, P10
Timeline
15/10/2025: Biodiversity Plan certified by the Dorset Council Natural Environment Team. Report P6
Within three years of the date of permission: Development must be begun. Report P2
Before first use of the development: Swift box installed, obscure glazing fitted, and Biodiversity Plan measures completed with evidence supplied. Report P6, P8
Plain English for the jargon
EPS Licence: European Protected Species Licence, a separate permit from Natural England needed where protected species may be affected.
LIC Licence: Low Impact Class Licence, a simpler form of EPS permit for low impact work on protected species.
Biodiversity Plan: A plan setting out mitigation, compensation and enhancement measures for ecological receptors, certified by the council's Natural Environment Team.
NPPF: National Planning Policy Framework, the government's national planning policy.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item114
Resolved
To grant planning permission with conditions set out in the officer’s report and outlined in the appendix of the minutes. Additional Condition was added Prior to first use of the development; 1 no. swift box shall be installed on the site and thereafter retained. Reason: To provide biodiversity gains.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
Application Number: P/HOU/2025/04198 Webpage: https://planning.dorsetcouncil.gov.uk/ Site address: Linden Grove Manor Road Gussage St Michael BH21 5HX Proposal: Erect two-storey front and side extensions, raise ridge height and erect porch. Applicant name: [name removed]: Claire Lewis Ward Member(s): Cllr Brown
1. Reason application is going to committee:
The application was referred for a Committee decision by the Chair of the North Dorset Planning Committee following a Scheme of Delegation referral. The application was referred to the Scheme of Delegation due to consultation responses from Gussage St Michael Parish Council in objection to the proposed scheme. 2. Summary of recommendation:
GRANT planning permission subject to conditions.
3. Key planning issues
Issue Conclusion
Principle of development The principle of extending and altering a residential dwelling within a village location such as this is acceptable where it accords with wider material planning considerations.
Scale, design, impact on character and There is no demonstrable harm to the character appearance and appearance of the area.
Impact on the living conditions of the There is no demonstrable harm to neighbour occupants and neighbouring properties amenity.
Impact on landscape There is no demonstrable harm to the landscape or scenic beauty of the Cranborne Chase & West Wiltshire Downs National Landscape.
Flood risk and drainage There is no demonstrable increased flood risk.
Biodiversity Biodiversity will be protected throughout the development, with mitigation secured. 4. Description of site
The proposal site is a large, mid-century, detached residential dwelling constructed in brick with hung tiles to the front gable and existing dormers and dark grey concrete roof tiles over. The dwelling is located centrally within the village of Gussage St Michael, on the east side of Manor Road, opposite the village hall. The site is flat and bounded by a combination of mature trees, fencing and hedgerow. The dwelling has extensive private grounds to the front and rear, including the original rear garden and additional land beyond which was once agricultural but granted lawful use as ‘garden’ in 2010 following application reference 3/10/0902/CLU. A former stable block on this land has been replaced with a garden outbuilding comprising office and gym, granted retrospective consent following application reference P/HOU/2025/04127.
When built, ‘Linden Grove’ and neighbouring ‘Chestnuts’ to the west were constructed in a similar chalet bungalow style, typical of their era, but it is otherwise surrounded by houses of varying heights, styles, materiality and age. With the exception of the Village Hall, the remaining buildings on both sides of Manor Road are of varying design, detached or semi-detached residential dwellings. Most are set back from the highway with large front amenity spaces used as gardens, often with the addition of extensive driveways and off-road parking. All buildings along the road are two or one and a half storeys in height and of traditional brick construction with occasional elements of render, timber cladding and hung tiles. With the exception of the Old Rectory site and adjacent woodland, all the land along Manor Road is occupied with low density dwellings. Moving northwest toward Manor Farm and Business Centre from the Village Hall and Old School House, residential development is limited to the western side of the road with farmland and woodland to the east stretching towards the Gussage Stream.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.