AI summaryDorset Council Cabinet approved £5 million in funding for two Swanage seafront projects: a £2.5 million capital grant for Green Seafront ground stabilisation and £2.5 million from the Local Transport Grant for Shore Road improvements.
Money£5 million total£2.5m grant and £2.5m transport grant
What happens nextDesign, planning, procurementTRO consultation autumn 2026
Who it affectsSwanage seafront usersResidents, visitors, businesses, highway users
What was decided
Cabinet approved £2.5 million as a capital grant to Swanage Town Council for the New Option of the Green Seafront Ground Stabilisation Project, and delegated authority to agree terms and enter into a grant agreement to the Executive Director for Regeneration, Infrastructure and Growth in consultation with the Cabinet Member for Place Services and the Section 151 Officer. Report 2.1
Cabinet approved the allocation of £2.5 million from the Local Transport Grant for the Shore Road Highway Improvement Project, and delegated authority to the Executive Director for Regeneration, Infrastructure and Growth in consultation with the Cabinet Member for Place Services to update the Highway Improvements Capital Programme. Report 2.2
Why
Monitoring in February 2026 identified 56 defects on the Green Seafront, with progressive ground movement already affecting the highway network on De Moulham Road and putting traffic management in place on Walrond Road, creating risks to public safety, highway resilience and the local economy. Report 1.4, 4.3, 4.4, 11.1
Shore Road has longstanding pedestrian safety and accessibility issues, including narrow footways, traffic concerns and parked cars reducing crossing visibility, which the Shore Road Improvement Project is designed to address. Report 4.12, 4.13, 4.14
The two projects together support Dorset Council Plan 2024 to 2029 priorities on the climate and nature crisis, supporting communities and growing the local economy, with tourism in Swanage worth £77 million per annum and supporting over 1000 jobs. Report 1.8, 3.1, 3.2, 4.1
What happens next
Swanage Town Council will submit a planning application, with a stopping-up order application to the Secretary of State for the eastern section of Walrond Road, and an application to the Charity Commission to transfer ownership of Sandpit and Weather Station Fields from charitable trust. Report 6.1, 6.2
Formal Traffic Regulation Order consultation on the Shore Road scheme is anticipated in autumn 2026, with tender responses for the Green Seafront project expected in early 2027 and construction currently estimated to start in September 2027. Report 6.3, 11.2, 7.2
The grant to Swanage Town Council will be formalised through a grant agreement under Section 1 of the Localism Act 2011, using the Community and Regeneration streamlined subsidy route with a maximum subsidy value of £2.5 million. Report 6.5, 6.6
The money
£2.5 million Capital grant to Swanage Town Council for the Green Seafront Ground Stabilisation Project, New Option Report 2.1, 7.3
£2.5 million Allocation from the Local Transport Grant for the Shore Road Highway Improvement Project Report 2.2, 7.4
£6,900,000 Estimated cost of the Green Seafront New Option, based on a September 2027 construction start with inflation Report 1.5, 7.2, P51
£4,400,000 Total capital funding already secured by Swanage Town Council for the Green Seafront project Report 1.5, 7.1, P49
£2,500,000 Funding gap on the Green Seafront project that the £2.5 million capital grant would close Report 7.2, P51
£500,000 Already committed by Cabinet in November 2025 from the Local Transport Grant for the Shore Road project Report 1.6, 7.4, P54
£1,700,000 Swanage Town Council Capital Receipts Reserve Report 7.1, P49
£1,910,000 Swanage Town Council Earmarked Reserves Report 7.1, P49
£2890,000 Community Infrastructure Levy contributions, Swanage Town Council, as written in the funding table Report 7.1, P49
£500,000 Community Infrastructure Levy contributions, Dorset Council Report 7.1, P49
£77 million per annum Value of tourism in Swanage to Dorset's economy, supporting over 1000 jobs Report 4.1
£80,000 per annum Estimated loss of parking income to Dorset Council from removal of on street parking on Shore Road Report 7.5
Options considered
Rejected: Green Seafront: do nothing. Fails to manage risk adequately and would result in unacceptable long term consequences Report 5.1, 5.2
Rejected: Green Seafront: asset disposal. Would not generate sufficient funding and would undermine the Town Council's strategic objectives Report 5.1, 5.2, 5.3
Rejected: Green Seafront: do minimum intervention. Does not meet project objectives and would result in unacceptable long term consequences Report 5.1, 5.2
Chosen: Green Seafront: full re stabilisation, New Option. Only option delivering required outcomes, with wider accessibility, biodiversity, climate and economic benefits Report 4.10, 4.11, 5.2
Rejected: Shore Road: full pedestrianisation. Raised concerns around access, traffic displacement, servicing and emergency access Report 5.4
Rejected: Shore Road: one way traffic system. Introduced wider network impacts and received mixed public support Report 5.4
Rejected: Shore Road: do nothing. Did not address existing safety, access and public realm concerns Report 5.4
Chosen: Shore Road: retain two way traffic, remove on street parking. Ranked highest overall in public engagement, balanced solution maintaining vehicle access with pedestrian improvements Report 4.15, 4.16, 5.5
Implications
Financial: Loss of approximately £80,000 per annum in parking income for Dorset Council, offset by reduced maintenance liability, environmental and accessibility benefits. Report 7.5
Financial: Total Dorset Council capital commitment across both projects is £5 million, with no additional liabilities or ongoing revenue costs to Dorset Council from the Green Seafront grant. Report 1.7, 7.3
Legal: Grant given under Section 1 of the Localism Act 2011, with subsidy controlled under the Community and Regeneration streamlined route, capped at £2.5 million and not exceeding 80% of total project costs. Report 6.5, 6.6
Legal: Stopping up order required to extinguish highway rights on the eastern section of Walrond Road, and Traffic Regulation Order amendments needed for Shore Road. Report 6.2, 6.3
Equalities: Both schemes assessed as delivering neutral to positive equalities outcomes, with positive impacts for older people, disabled people, families and carers; short term impact on Blue Badge users from parking removal mitigated by dedicated bays. Report 12.1, 12.2, 12.3
Climate: Major positive impact on natural assets, ecology and climate adaptation through long term stabilisation, with at least 10% biodiversity net gain and minor negative energy impact from new lighting mitigated by efficient design. Report 8.1
Risk: Current risk assessed as High and residual risk as Medium Low after approval, with remaining risks relating to potential cost escalation and statutory consent timescales. Report 11.4, 11.5, P77, P79
Staffing: Dorset Council officers are providing project management and professional consultancy services to Swanage Town Council, including access to existing Dorset Highways contracts, formalised through a Collaboration Agreement. Report 6.4
Who and where
Swanage Town Council, as recipient of the £2.5 million capital grant and lead on the Green Seafront project Report 2.1, 4.6, 6.4
Residents of Swanage, who use the Green Seafront, Sandpit Field, Weather Station Field and Shore Road Report 1.1, 4.1, 4.6
Visitors to Swanage seafront, with events on Sandpit Field alone attracting over 100,000 visitors a year Report 4.1
Highway users on Shore Road and De Moulham Road, which are already affected by ground movement Report 1.3, 11.1
Blue Badge holders, who face short term impact from loss of on street parking on Shore Road, mitigated by dedicated bays Report 4.16, 12.3
Local businesses and the visitor economy, supported by tourism worth £77 million per annum and over 1000 jobs Report 4.1, 11.1
2023: First round of public engagement on the Green Seafront project Report 4.9
November 2025: Cabinet approved £500,000 from the Local Transport Grant for the Shore Road project, as part of the Highways Capital Programme Forward Plan Report 7.4, P54
Summer 2025: Dorset Coast Forum carried out engagement on Shore Road alongside the Green Seafront project Report 4.14
2025: Second round of public engagement on the Green Seafront project, presenting Essential Option and New Option Report 4.9, 4.10
February 2026: Monitoring identified 56 defects across retaining walls, steps, paths and associated structures on the Green Seafront Report 4.3
19 May 2026: Dorset Council Cabinet approved £5 million in funding across both projects Report 2.1, 2.2
Autumn 2026: Formal Traffic Regulation Order consultation anticipated for the Shore Road scheme Report 6.3
Early 2027: Tender responses expected for the Green Seafront construction contract Report 11.2
September 2027: Current estimated construction start date for the Green Seafront project, with inflation included in cost estimates Report 7.2
Plain English for the jargon
TRO: Traffic Regulation Order, the legal mechanism used to amend parking, speed limits and traffic restrictions on the highway
LTG: Local Transport Grant, from the Department for Transport, funding the Shore Road improvement
CIL: Community Infrastructure Levy, a charge on new development used to fund infrastructure
ECI: Early Contractor Involvement, used here through Heidelberg Materials Ltd to refine cost estimates
EqIA: Equality Impact Assessment, completed for both projects
S151 Officer: Statutory chief finance officer, responsible for the proper administration of the council's financial affairs
New Option: Preferred design variant for the Green Seafront project, estimated at £6.9 million
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
(a) That funding of £2.5 million as a capital grant for the New Option of Swanage Town Council’s Green Seafront Ground Stabilisation Project be approved; and, authority be delegated to agree the terms and enter into a grant agreement for this purpose to the Executive Director for Regeneration, Infrastructure and Growth in consultation with the Cabinet Member for Place Services and Dorset Council’s Section 151 Officer. (b) That the allocation of £2.5 million funding from the Local Transport Grant for the Shore Road Highway Improvement Project, be approved; and, authority be delegated to the Executive Director for Regeneration, Infrastructure and Growth in consultation with the Cabinet Member for Place Services to update the Highway Improvements Capital Programme. Reason for the decision The decision promotes targeted investment in two complementary Swanage seafront projects that enhance safety, accessibility and public spaces while strengthening coastal resilience, supporting communities and boosting the local economy.
Word for word from the decision Dorset published for this meeting.Source: moderngov.dorsetcouncil.gov.uk
1.1Swanage’s seafront plays a central role in the town’s identity, community life and visitor economy. However, increasing ground instability of the Green Seafront and longstanding accessibility issues along Shore Road now present escalating risks to public safety, highway network resilience and the long‑term sustainability of this important seafront environment. These pressures are expected to intensify as a result of climate change, sea‑level rise and more extreme weather events.
1.2Dorset Council and Swanage Town Council have worked closely to develop two complementary projects to address ground instability affecting the Green Seafront and the longstanding safety and accessibility concerns along Shore Road.
1.3Dorset Council’s contribution to the Green Seafront project will stabilise part of the highway that is subject to ground movement. This collaborative working helps to ensure that stability issues on the Green Seafront do not further affect Dorset Council’s highway network.
1.4Swanage Town Council’s Green Seafront Ground Stabilisation Project responds to confirmed evidence of progressive ground movement across Sandpit Field and adjoining areas. Professional monitoring has identified extensive defects affecting retaining structures, access routes and public spaces. Without intervention, continued deterioration would be likely to result in V2/26
progressive restrictions on access, increased unplanned highway maintenance and heightened public safety risk.
1.5Swanage Town Council has developed a Strategic Outline Business Case which confirms that intervention is necessary, deliverable and aligned with local, regional and national policy objectives. Through public engagement, a preferred ‘New Option’ has been identified, delivering improved accessibility, enhanced biodiversity, increased climate resilience and adaptation along with wider community and economic benefits, at an estimated cost of £6.9 million. Swanage Town Council has secured £4.4 million towards the project and is seeking a £2.5 million capital grant from Dorset Council to address the remaining funding gap and complete the stabilisation necessary to support Dorset Council’s highway.
1.6Dorset Council’s Shore Road Improvement Project addresses pedestrian safety, accessibility and public realm quality along a key seafront route. Following feasibility work and public engagement, a preferred option has been identified at an estimated cost of £2.5 million. Dorset Council has already committed £0.5 million through its Local Transport Grant. Approval is sought for a further £2 million from the Local Transport Grant to enable delivery.
1.7Taken together, the projects represent a coordinated capital investment of £5 million by Dorset Council. This comprises £2.5 million of direct funding to support the stabilisation element of the Green Seafront project and £2.5 million for the Shore Road improvements, funded through the Department for Transport’s Local Transport Grant.
1.8The projects support the Council Plan 2024–2029 priorities and will help secure the long‑term safety, resilience and quality of Swanage’s seafront for residents, visitors and future generations. Helping Swanage to thrive now and into the future.
2. Recommendation(s)
That Cabinet approves the following:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dorset Council Annual Report 2025 - 2026That the Dorset Council Annual Report for 2025-2026 be received and noted. Reason for the decision The annual report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.