Resolved
That it be recommended to Cabinet (a) That decision CAB109 be endorsed and that the overspend on the Kearsney Abbey and Russell Gardens project be financed from contingencies identified in the Medium-Term Financial Plan, namely £250,000 from a specific contingency established for this project, and £100,000 from general contingencies. (b) That an investigation be undertaken as to why the project was not sufficient in respect of the pre-project survey data. (c) That the worst- and best-case scenarios be provided in respect of the costs for the project. (d) That the Council’s asset maintenance programme be added to the work programme.