Planning Committee, Thursday 24 March 2022

Application No DOV/20/00155 - 8 The Street, Ash

Approved Planning 2 papers

Planning Committee approved this item on Thursday 24 March 2022. Below is the council's own wording, with the papers it was decided on.

Item135

Resolved

(a) That, subject to the Local Planning Authority, as the ‘competent authority’ for the purposes of the Habitat Regulations, being satisfied (in consultation with Natural England as/if necessary) that discharges of wastewater from the Dambridge wastewater treatment works were not likely to have a significant effect on the integrity of the Stodmarsh SAC, SPA and Ramsar site or, alternatively, that satisfactory mitigation can be achieved, Application No DOV/20/00155 be APPROVED subject to the following conditions: (i) Three-year standard time limit; (ii) Approved plans; (iii) Samples of materials; (iv) Provision of bike and bin storage prior to first occupation; (v) Pre-commencement condition – Demolition and Construction Management Plan (Routing of demolition, construction and delivery vehicles and site personnel; Timing of HGV movements (these are likely to be restricted during school drop-off and pick-up periods); Provision of wheel-washing facilities; Temporary traffic management/signage; Before and after construction of the development, highway condition surveys for highway access routes should be undertaken and a commitment provided to fund the repair of any damage caused by vehicles related to the development; Site access arrangements); (vi) Provision of measures to prevent the discharge of surface water onto the highway; (vii) Provision and permanent retention of the vehicle parking spaces shown on the submitted plans prior to the use of the site commencing, including the retention of public access to the three spaces between units 1 and 2; (viii) Use of a bound surface for the first 5 metres of the access from the edge of the highway; (ix) Provision and permanent retention of secure, covered cycle parking facilities prior to the use of the site commencing, in accordance with details to be submitted and approved by the Local Planning Authority; (x) Completion of the access and associated highway alterations (parking restrictions) shown on the submitted plans prior to the use of the site commencing. Applicant to use best endeavours to secure the necessary Traffic Regulation Order and implement the parking restrictions; (xi) Gradient of the access to be no steeper than 1 in 10 for the first 1.5 metres from the highway boundary and no steeper than 1 in 8 thereafter; (xii) Provision and maintenance of 43 metres x 2.4 metres x 43 metres visibility splays at the access with no obstructions over 1 metre above carriageway level within the splays, prior to use of the site commencing; (xiii) Completion of the step-free paved connection to public footpath EE117 at the rear of the site prior to the use of the site commencing; (xiv) Provision of electric charging points; (xv) Removal of permitted development rights (classes A, B, C, D and E ); (xvi) Removal of permitted development rights for insertion of window openings at first-floor level; (xvii) Joinery details, eaves details, ridge details at 1:10 for the non-designated heritage asset; (xviii) Hand-dug condition and tree protection measures; (xix) Programme of archaeological works; (xx) Ecological mitigation and enhancement works; (xxi) Landscaping scheme; (xxii) Pre-commencement condition requiring submission of a detailed scheme for surface water disposal; (xxiii) Pre-commencement condition requiring submission of a detailed scheme for foul water drainage; (xxiv) Boundary treatment and hard surfacing. (b) That powers be delegated to the Planning and Development Manager to settle any necessary planning conditions in line with the issues set out in the recommendation and as resolved by the Planning Committee.
Word for word from the decision Dover published for this meeting. Source: moderngov.dover.gov.uk

Follow this further

Built from Dover's papers

What the report saysPro

Report to Planning Committee
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
8 The Street Ash: 00155 ReportReport 390 KB Copy on its way
PDF
Application No DOV/20/00155: 8 The Street, AshReport 176 KB Copy on its way

At this meeting

Whole meeting

On this subject at Dover

Search all
  1. Application No DOV/20/00155 - 8 The Street, AshThis decision
  2. Application Nos DOV/22/01701 & DOV/22/01702 - 74-80 High Street and 67 Middle Street, DealAgreed
  3. Application No DOV/25/01382 - Land East of Sports Pavilion, St George's Road, SandwichAgreed
  4. Application No DOV/24/00156 - Land Rear of 10 to 22 Malvern Meadow, Temple Ewell, DoverAgreed
  5. Application No DOV/26/00266 - 55 Bewsbury Cross Lane, WhitfieldApproved
  6. Application No DOV/26/00177 - Finglesham Well, The Street, FingleshamAgreed

More from Dover Planning Committee

All decisions
MeetingDecisionOutcome
16 Jul 2026 Application Nos DOV/22/01701 & DOV/22/01702 - 74-80 High Street and 67 Middle Street, Deal(a) That, subject to the completion of a Section 106 legal agreement to secure the required infrastructure and develo... Agreed Open
16 Jul 2026 Application No DOV/25/01382 - Land East of Sports Pavilion, St George's Road, Sandwich(a) That, subject to the completion of a Section 106 agreement to secure the development as self-build, Application N... Agreed Open
16 Jul 2026 Application No DOV/24/00156 - Land Rear of 10 to 22 Malvern Meadow, Temple Ewell, Dover(a) That, subject to the completion of a Section 106 legal agreement or online payment to secure the required contrib... Agreed Open
18 Jun 2026 Application No DOV/26/00266 - 55 Bewsbury Cross Lane, Whitfield(a) That Application No DOV/26/00266 be APPROVED subject to the following conditions: (i) Implement permission within... Approved Open
18 Jun 2026 Application No DOV/26/00177 - Finglesham Well, The Street, Finglesham(a) That, subject to the completion of a Section 106 legal agreement or online payment (to secure the required contri... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies