What the committee will consider, in order, with every paper attached to its item.
To receive any apologies for absence.
To note appointments of Substitute Members.
To receive any declarations of interest from Members in respect of business to be transacted on the agenda.
To confirm the attached notes of the meeting of the Advisory Group held on 12 September 2023.
To receive an update on the following: Procuring main contractor and Social Value Securing tenants Funding arrangements Communications Plan Archaeology
To receive a presentation from Lee Evans Partnership.
Decision: That the presentation be noted. Decision page
To receive a verbal update.
Decision: That the update be noted. Decision page
RIBA 4/Second Stage: D & B award/enabling works package (if applicable)/PAG RIBA 4 sign-off meeting Underpass: Target for initiating PEP – May 2024/Target completion date – September 2025 Signage: Target for initiating PEP – April 2024/Target completion date – October 2024 Cycle Hubs: Target date for initiating PEP – June 2024/Target completion date – March 2026
Decision: That the update be noted. Decision page
To be agreed.
Decision: It was agreed that a date would be confirmed. Decision page
The recommendation is attached.
Decision: That, under Section 100(A)(4) of the Local Government Act 1972, the public be excluded during consideration of the following items of business on the grounds that they involve the likely disclosure of exempt information as defined in paragraph 3 of Schedule 12A of the Local Government Act 1972. Decision page
To receive a verbal update.
Decision: That the update be noted. Decision page
To receive a verbal update.
Decision: The Project Advisory Group acknowledged the potential for cost overruns and, given the stage that the project had reached, recommended that Cabinet satisfies itself that there is a robust plan in place prior to signing off the RIBA Stage 3 report, and that other key risks have been looked at and mitigations established. Decision page
The committee last met on 12 September 2023. None of its items return this time; 1 item is new. Point at any item to follow a thread. Procedural items are left out.
Notes, Dover Beacon Update, Dover Beacon Discussion Forum - Draft Terms of Reference do not return this time.
See the 12 September meetingEvery Dover Beacon and Dover Town Regeneration Project Advisory Group meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Dover, Dover Beacon and Dover Town Regeneration Project Advisory Group
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Dover Beacon and Dover Town Regeneration Project Advisory Group, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.