Capital Programme 2003/04 - Shildon Sunnydale Leisure Centre Entrance PDF 80 K

Approved Executive

Cabinet (SBC) approved this item on Thursday 22 January 2004. Below is the council's own wording, with the papers it was decided on.

Item132

Resolved

RESOLVED : That the tender submitted by Contract Services in the sum of £57,751.62 be approved and that work commence as soon as possible.
Word for word from the decision Durham published for this meeting. Source: democracy.durham.gov.uk

Follow this further

Built from Durham's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

On this subject at Durham

Search all
  1. Capital Programme 2003/04 - Shildon Sunnydale Leisure Centre Entrance PDF 80 KThis decision
  2. Capital programme expenditure and financing position to 31st december 2008 pdf 128 kNoted
  3. Budgetary control report 2008/09 - updated capital programme expenditure and financing position to 30th november 2008 pdf 126 kNoted
  4. Capital programme expenditure and financing position to 30th september 2008 pdf 112 kNoted
  5. General Fund Capital Programme 2008/9Approved
  6. 2008/2009 General Fund Capital ProgrammeAgreed

More from Durham Cabinet (SBC)

All decisions
MeetingDecisionOutcome
19 Mar 2009 Redevelopment of 'the rows', ferryhill station pdf 173 kRESOLVED : 1. That the request from Three Rivers Housing Group to alter the tenure mix of the properties be agreed. 2... Agreed Open
19 Mar 2009 Area forums pdf 67 kRESOLVED : That the Minutes be received. Decided Open
19 Mar 2009 Employment Issues Panel PDF 57 KRESOLVED : That the Minutes be received. Decided Open
19 Feb 2009 Revenue budgetary control report - position at 31st december 2008 and probable outturn 2008/09 pdf 153 kRESOLVED : That the position as at 31 st December 2008 and the projections for the final year be noted. Noted Open
19 Feb 2009 Capital programme expenditure and financing position to 31st december 2008 pdf 128 kRESOLVED : That the updated nine month spend position to 31 st December 2008, the amendments to the Capital Programme... Noted Open