Sure Start Local Programme: Shildon and Newton Aycliffe West: Capital Programme PDF 102 K

Approved Executive

Cabinet (SBC) approved this item on Thursday 3 February 2005. Below is the council's own wording, with the papers it was decided on.

Item147

Resolved

RESOLVED : 1. That a financial contribution of up to £75,000 be approved to support the development of two Childrens Centres as part of the Local Sure Start Shildo and Newton Aycliffe West Programme. 2. That a planned capital programme of £1,517,200 (inclusive of VAT) be submitted to the Sure Start Unit on behalf of the Local Sure Start Shildon and Newton Aycliffe West Programme and agreement be sought from the Sure Start Unit to meet the non recoverable VAT on the expenditure supported by the Sure Start capital grant.
Word for word from the decision Durham published for this meeting. Source: democracy.durham.gov.uk

Follow this further

Built from Durham's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

On this subject at Durham

Search all
  1. Sure Start Local Programme: Shildon and Newton Aycliffe West: Capital Programme PDF 102 KThis decision
  2. Sure Start Programmes In The BoroughAgreed

More from Durham Cabinet (SBC)

All decisions
MeetingDecisionOutcome
19 Mar 2009 Redevelopment of 'the rows', ferryhill station pdf 173 kRESOLVED : 1. That the request from Three Rivers Housing Group to alter the tenure mix of the properties be agreed. 2... Agreed Open
19 Mar 2009 Area forums pdf 67 kRESOLVED : That the Minutes be received. Decided Open
19 Mar 2009 Employment Issues Panel PDF 57 KRESOLVED : That the Minutes be received. Decided Open
19 Feb 2009 Revenue budgetary control report - position at 31st december 2008 and probable outturn 2008/09 pdf 153 kRESOLVED : That the position as at 31 st December 2008 and the projections for the final year be noted. Noted Open
19 Feb 2009 Capital programme expenditure and financing position to 31st december 2008 pdf 128 kRESOLVED : That the updated nine month spend position to 31 st December 2008, the amendments to the Capital Programme... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies