Item49
Resolved
RESOLVED : 1. That the lowest tender submitted by Duffell Roofing in the sum of £360,954 for both Centres be accepted. 2. That the roof work at Spennymoor Leisure Centre be undertaken within the 2005/06 financial year at a cost of £147,000. 3. That the agreed Capital Programme be altered with £37,000 ear-marked for the refurbishment of the pool hall at Spennymoor Leisure Centre and the provision of a playing pitch at Sedgefield being deferred until 2006/07. 4. That £110,000 be allocated from capital contingencies to meet the balance of costs for the roof replacement at Spennymoor Leisure Centre. 5. That the roof work required at Newton Aycliffe Leisure Centre, amounting to £213,964 be a first call against the 2006/07 Capital Programme.
Word for word from the decision Durham published for this meeting.
Source: democracy.durham.gov.uk